About this file

This document is a Statement of Work (SOW) for a federal contract opportunity related to snow removal services at the Brown v. Board of Education National Historical Park in Topeka, Kansas.

The SOW outlines the requirements for the snow and ice removal services, including clearing snow accumulation over 1 inch from concrete sidewalks, courtyards, steps, ramps, and asphalt/gravel parking lots, as well as applying eco-friendly ice melt. The contract has a base year with up to four additional option years. Contractors must have a minimum of 3 years' experience in lawn care and snow removal, and must comply with all applicable local, state, and federal regulations. The contract is a total small business set-aside, with a solicitation number of 140P6024Q0036. Quotes are due by noon CDT on August 15, 2024, and the contract will be awarded based on best value to the government considering price, technical capability, and past experience.

View the file

Other files for this federal contract opportunity

Other files attached to BRVB SNOW REMOVAL SERVICE, newest first.
File Type Posted
B08_Solicitation_140P6024Q0036_(Attachment_3_PPQ).doc DOC document
Sol_140P6024Q0036.pdf PDF
B08_Solicitation_140P6024Q0036_(Attachment_2_SCA_Wage_Determination).pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Service Contract Requirements V. 2021-10-18 Page | 1

BROWN v. BOARD OF EDUCATION

NATIONAL HISTORICAL PARK

SNOW REMOVAL SERVICES

PROJECT STATEMENT OF WORK or

PERFORMANCE WORK STATEMENT

NATIONAL PARK SERVICE

5-22-2024

TABLE OF CONTENTS

Page | 2

Service General Requirements

Service General Requirements

Drawings and Photographs

Appendix A: Site Plan

Page | 3

SERVICE GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 – LOCATION AND DESCRIPTION OF WORK

1.1 Background: The project will include snow and ice removal of parking lots and sidewalk surface within Brown v. Board of Education National Historical Park.

1.2 Work Covered by the Contract Documents:

A. Project Location: Brown v. Board of Education National Historical Park, 1515 SE Monroe, Topeka, Kansas 66614

B. 1. Work consist of: Snow and Ice Removal

2. Removal of snow above 1” accumulation of concrete sidewalks, East concrete courtyard, steps and ramps, asphalt, gravel parking lot.

3. Ice removal of above surfaces excluding gravel parking area using eco-friendly ice melt approved by the COR before application.

4. Pre-treatment of concrete areas, ramps and steps and asphalt parking lot when warranted.

Product used will be approved by COR before application.

C. All work will be performed under a single contract.

Period of performance: Work shall be completed within one calendar year based on season of snow removal from notice to proceed with the option to renew for four (4) years.

ITEM 2 - EXISTING UTILITIES

This section is not applicable.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent. . BRVB Superintendent Compendium - Brown v. Board of Education National Historical Park (U.S. National Park Service) (nps.gov) https://www.nps.gov/brvb/learn/management/brvb-superintendent-compendium.htm https://www.nps.gov/brvb/learn/management/brvb-superintendent-compendium.htm

Page | 4

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the site or within the park unless approved by the Contracting Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Saturday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day Martin Luther King, Jr’s Birthday Washington’s Birthday Memorial Day Juneteenth National Independence Day Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday;

holidays falling on Sunday will be observed on the following Monday. The specific day that each holiday is recognized for each year can be found at the following site: Federal Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site. Limit use of premises to area of service provided as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated.

B. Limits: Not applicable

C. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

D. Utilities https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022 https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2022

Page | 5

E. Security and Protection facilities:

This section is not applicable.

3.4 Storage - Staging Areas:

3.5 Preservation of Natural Features:

Avoid damage to building and cultural landscape during all work performed.

3.6 Hauling Restrictions:

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

3.8 Photo Documentation:

3.9 Fire and Life Safety:

1 Comply with the requirements of NFPA.

3.10 Noise and Acoustics Management:

ITEM 4 - EXAMINATION OF THE SITE

4.1 All interested contractors are urged to visit the job site and examine existing conditions before submitting quotes. Contractors will be expected to complete the work as quoted.

ITEM 5 – SUBMITTALS

5.1 General Submittal Procedures:

A. Proposal and cost

A. Product Data: Provide component and specification data sheets.

B. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

Page | 6

C. After approving submittals, Contracting Officer and/or COR will return one copy to the Contractor.

If submittals are not approved, Contracting Officer will return all copies to Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

5.3 Approved Equals:

ITEM 6 – TEMPORARY SERVICES

This section is not applicable.

ITEM 7 - PROJECT CLOSEOUT

This section is not applicable.

7.3 Warranties

END OF SECTION

Brown v. Board of Education National Historical Park 1515 SE Monroe St Topeka, KS 66612

STATEMENT OF WORK:

Snow Removal Services

1.0 Objective and Location

This project will consist of snow and ice removal service during winter where the of snow fall or ice treatment are required by accumulation. This includes Snow and Ice removal on concrete surfaces along with asphalt parking and gravel parking lot. Service contract will include a base year with up to four additional option years to be exercised at the discretion of the Park.

2.0 Scope of Work

Work includes, but is not limited to, providing all labor, materials, equipment, tools, and services required to provide full snow and ice removal on properties.

This contract is based on snow fall and ice accumulations amount dictated by the Park.

1. During snow removal months the snow clearing of the gravel parking lot area shall be done with a plow with shoe attachments to avoid movement of gravel. No salt or other mixtures shall be applied to the gravel parking area. This will prevent the area from deterioration with potholes later when the freeze and thaw states occur.

2. Parking lot behind the school and sidewalk spaces around the school will be treated with eco friendly ice melt. The requirement for the use of ice melt is 1 inch of snow. In the event of ice, any application of salt to back parking lot and sidewalks will be done automatically.

3. Pre-treatment of paved driveway, sidewalks around the school, will also be automatic. The park is officially closed on Thanksgiving, Christmas, and New Year’s.

2.1 Codes and Standards

The contractor shall be responsible for complying with regulations of all local, state, and federal agencies having jurisdiction over any portion of the work to be performed under this contract.

The contractor, as a minimum, shall meet or exceed the applicable requirements of the latest revision of the following codes and specifications published by the following organizations:

DOT - DEPARTMENT OF TRANSPORTION

EPA - ENVIRONMENTAL PROTECTION AGENCY

OSHA - OCCUPATIONAL SAFETY AND HEALTH ACT

It is not the intent of this specification to restrict the Contractor’s work. The Contractor shall be totally responsible for the work. These specifications are the minimal requirements acceptable.

2.2 Coordination of Work

Contractor shall be responsible for coordinating all work to be performed under this contract with the Contracting Officers’ Representative (COR), POC will be Karen Maraschino 785.354.4273 (Office)

785.409.2112 (Cell), Diana Merrill 816.853.7791 (Cell).

2.3 Professional Qualifications

Contractor and employees shall have a minimum of three (3) years’ experience in lawn care and snow removal.

2.4 Contractor Work Hours

All normal work for this contract shall be performed during normal daylight hours. Any exceptions will require the written approval of the (CO) Contracting Officer.

2.5 Supervision and Labor

The contractor shall provide a competent supervisor satisfactory to the COR, authorized to act for the contractor. The contractor shall promptly remove from the work site any supervisor or employee whose work or conduct is not satisfactory to the COR.

The Contractor’s supervisor shall be on the premises at all times during working hours and in charge of the work on behalf of the contractor.

The contractor shall enforce strict discipline and good order among the Contractor’s employees.

The contractor shall exercise the necessary supervision and control to prevent contractor’s employees from violating any rules and regulations.

2.6 Site Access

Access to the site is open and readily available to contractor, however NPS preference is for services to be performed on Monday – Friday to reduce impact on visitor services when the park is open from 9:00 AM – 5:00 PM. If inclement weather is expected the performance of this weekly service may occur on a previous day(s) Monday or Tuesday, or a day after on Thursday.

2.7 Contractor Care, Custody and Control

Upon commencement of work, contractor shall be fully responsible for the care, custody, and control of the work until it has been completed.

During the period of Contractor’s work, the contractor shall protect the property from all potential hazards or report these hazards immediately to the COR or local police.

Care shall be taken to protect any existing structure, windows, post, tree, electrical lights, and fence posts. If structure or historic item is destroyed or damaged, it shall be reported to the COR for assessment of damages.

2.8 Safety

The Contractor shall be responsible for employee and visitor safety on the worksite and shall establish an effective accident prevention program and provide a safe environment for all personnel and visitors. Report to the COR all accidents or injuries that occur. Place all required protective barriers and take all necessary measures to ensure unauthorized persons do not enter the worksite.

Assure there are no hazards to park visitors during the execution of the work. This safety zone shall be sufficiently sized to prevent damage to others or existing facilities and structures.

The successful Contractor agrees to adhere to and enforce all applicable local, state, federal, and OSHA safety regulations.

2.9 Environmental Protection

The contractor shall prevent hazardous material spills, in case of spill or release of any sort, contractor shall immediately notify the COR.

2.10 Debris

Do not permit debris or unsalvageable material resulting from the work to accumulate on site.

Remove debris, do not dispose of debris in waterways, and provide for off-site disposal areas.

2.11 Maintaining Traffic

Accomplish work with minimum interference to pedestrian and vehicular traffic around the property.

2.12 Underground Utilities

This section does not apply.

3.0 Contractor Performance

The contractor shall perform all work required as necessary to fulfill the intent of the contract. All work shall be performed in a professional manner, noise kept to a minimum, and work staged from a location on the site as to not interfere with the users’ access to entrances to buildings and parking facilities.

The NPS reserves the right to conduct any inspection it may deem necessary prior to acceptance and approval of payment to assure that all work conforms to the Statement of Work and any applicable standards, regulations, or laws.

3.1 Contractors Responsibilities

Trees, shrubs, flowers, or turf that are damaged or killed due to contractors operations shall be replaced at the expense of the contractor.

Lighting system or structures, both on structures and in the landscape that are damaged due to contractor’s operations must be repaired or replaced by the contractor promptly at no expense to the NPS.

A notice by email should be provided to COR when mowing service have been completed on a weekly basis to ensure satisfaction of work or to provide date of when services were rendered.

By providing notice, this will help identify when mowing services have to be adjusted to due to weather or other circumstance beyond the control of the contractor.

D. Utilities
This section is not applicable.
E. Security and Protection facilities:
This section is not applicable.
3.4 Storage - Staging Areas:
This section is not applicable.
1 Comply with the requirements of NFPA.
.

File details come from the government source that posted it. Updated .