Statement_of_Work_(Revised)_0001.pdf

PDF 309 KB Posted

Attached to
REPLACE HVAC CONDENSERS SYSTEMS PARKWIDE Federal contract opportunity
Solicitation number
140P5423Q0032
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This statement of work outlines the requirements for replacing HVAC condenser systems at San Juan National Historic Site housing and administrative buildings under solicitation number 140P5423Q0032 issued by the National Park Service Southeast Region. The contractor shall remove 21 inoperative and 10 end-of-life HVAC mini-split systems across 4 buildings, and install new energy efficient mini-split systems along with related components. Key requirements include replacing specific HVAC models at each building, providing warranty and training documentation, and completing work within 90 days of the notice to proceed while coordinating with park staff. The proposal due date is August 1, 2023, and the pre-bid site visit will take place on July 21, 2023.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE HVAC CONDENSERS SYSTEMS PARKWIDE, newest first.
File Type Posted
Sol_140P5423Q0032_Amd_0001.pdf PDF
Line_Item_Schedule.pdf PDF
SCA_Wage_Determination.pdf PDF
Sol_140P5423Q0032.pdf PDF
Statement_of_Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Replace HVAC Condensers System at Park Housing Units and Administrative Buildings

Parkwide

PMIS: 334789

SAN JUAN NATIONAL HISTORIC SITE

OLD SAN JUAN, PUERTO RICO

STATEMENT OF WORK

DATED:

July 18, 2023

NATIONAL PARK SERVICE

SOUTHEAST REGION

SOUTH MAJOR ACQUISITION BUYING OFFICE

Replace HVAC Condensers System at Park Housing Units and Administrative Bldgs.

SOW Format

1. Background

2. Objectives

3. Place of performance

4. Period of performance

5. Scope

6. Tasks

7. Deliverables

8. Government-Furnished Property (GFP)

9. Safety

10. Security Considerations

11. Travel

12. Special Material Requirements

13. Other Unique Requirements and Considerations

14. Quality Control Requirements

15. Project Personnel

16. Attachments

1. BACKGROUND

The current Heating, Ventilation and Air Conditioning (HVAC) need replacement due to inoperative units (21 ea.) and end of life cycle (10 ea.) at San Juan National Historic Site

(SAJU).

2. OBJECTIVES:

This contract is to Replace the HVAC Condensers System at Park Housing Units in Historic Building # 210, 211 and Administrative Buildings # 208 and 209. There are (24) Twenty-four HVAC Mini Splits (Wall Mounted Evaporator Units and Exterior Condensing Units) and (7) Seven condenser/evaporator unit to be replaced.

3. PLACE OF PERFORMANCE:

Street Address: San Juan National Historic Site, NPS

511 Calle Norzagaray, San Juan, Puerto Rico, 00901

Park Law Enforcement Bldg. 208 Park Headquarters Bldg. 209

Park Housing Units 210 [A & B] Park Housing Unit 211

4. PERIOD OF PERFORMANCE:

All tasks and deliverables for this contract shall be completed within calendar 90 days after Notice to Proceed. Days listed herein refer to calendar days. The work schedule is Monday through Friday between the hours of 6:30 am to 3 pm. Any changes to the work schedule shall be approved by the Contracting Officer’s Representative (COR) in advance.

5. SCOPE:

The project consists of replacing the HVAC equipment listed below. The new equipment shall meet the latest technology and energy efficiencies available with current industry standards.

The Contractor shall deliver the following services and provide an itemized cost breakdown to include materials/equipment, labor, administrative, and other fees. The Contractor shall have an on-site superintendent/foreman present at all times.

6. TASKS:

Under this contract, the Contractor shall perform the following tasks and requirements to Install new HVAC Mini Splits (Wall Mounted Evaporator Units and Exterior Condensing Units) at Buildings 208,209,210 and 211 at the indicated locations.

A. Base Line - Replace the following with equipment listed below or COR approved equal for all equipment listed.

Units in Building 208: 13, 14, 15, 16 18, 19 Units in Building 209: 23, 24, 25, 26 Units in Building 210: 28, 29, 33, 34, 35, 36 Units in Building 211: 38, 39, 41, 42, 44

1. Three (3) APH12AC230V1AH APHRO 12K 22 SEERS INDOOR 220-1-60

2. Six (6) APH18AC230V1AH APHRO 18K 22 SEERS INDOOR 220-1-60

3. Seven (7) APH12AC230V1AH APHRO 24K 22 SEERS INDOOR 220-1-60

4. One (1) APH36AC230V1AH APHRO 36K 22 SEERS INDOOR 220-1-60

5. Three (3) Trane 36MBH AHU 208-230/60/1PH - Three (3) Trane 3 Ton Condensing

Units HIGH EFFICIENCY 208-230/60/ IP

6. One (1) Trane 60 MBH AHU 208-230/60/1PH – one (1) Trane 5 Ton Condensing

Unit HIGH EFFICIENCY 208-230/60 1P

B. Additive Line - Replace the following with equipment listed below or COR approved equal for all equipment listed.

Units in building 208: 17, 20 Units in building 209: 21, 22, 27 Units in building 210: 30, 31, 32, 37, Units in building 211: 40

7. Two (2) APH12AC230V1AH APHRO 12K 22 SEERS INDOOR 220-160

8. Five (5) APH12AC230V1AH APHRO 24K 22 SEERS INDOOR 220-1-600

9. Three (3) Trane 60 MBH AHU 208-230/60/1PH – Three (3) Trane 5 Ton

Condensing Unit HIGH EFFICIENCY 208-230/60 1P

• All units will be Seasonal energy efficiency ratio (SEER) 22 or higher. Units will be 120/240-volt system single phase.

• Warranty: Minimum 7 Year Compressor 5 Years Parts.

• All exterior condensing units will have an Anti-corrosion Condenser Coil Coating applied.

• All exterior condensing units will have labels to indicate corresponding circuit number on breaker panel.

• For each exterior condensing unit, install a Disconnect Switch in the immediate area:

Non-Metallic Mennekes NEMA 4X rated enclosure or approved equal.

• All existing copper tubing will be removed, and new copper tubing (ACR Type or Type L copper) will be installed. Copper tubing will be installed with insulator (all weather) for suction line, and it will be sized correctly to the evaporator and condenser, this will be verified before units are accepted. The liquid line will also be sized correctly and will also be field verified for each unit.

• All existing electric connection from breaker panel will be removed and new wire will be installed for both condenser and evaporator.

• Each evaporator unit will require corrosion resistant rooftop wind anchoring with unit base pedestals.

• Each evaporator unit will require having a condensation pump and will need to be plumbed to the exterior of the building in the most efficient way.

• Each of the condenser unit will be rated for saltwater environment and have components and materials that will not corrode. Each of the condensers will be mounted systems that do not require any roof penetrations under any circumstance.

• Each condenser unit will be properly secured with stainless steel tie-down hardware.

• All hot work will require a fire extinguisher to be always present and for contractor to certify that areas are safe from any fire hazard.

• Safely dispose of all equipment to be removed in accordance (IAW) all Federal and local regulations. Remove and recover all refrigerants per EPA regulations and dispose of these refrigerants IAW all Federal and local regulations.

• Coordinate all work and utility service interruptions with park staff. No less than a 24-hour notice shall be given before any type of utility interruption is to occur. Interruptions shall not exceed more than one (1) working day.

• All affected areas shall be restored to their original condition from before the work began. Any damages shall be fixed and repaired at no cost to the Government.

• Clean jobsite of all dust and debris at the end of each workday and ensure that all work is performed in a professional manner.

• The Contractor shall be solely responsible for coordination with all Federal, state, and local authorities before commencement of the project to ensure project completion within the 90-day POP.

• The Contractor shall notify SAJU site Administration 24 hours prior to the start date of any excavation or job that requires the closing of some areas.

• Train Park's maintenance personnel to adjust, operate, and maintain new HVAC systems. A minimum two (2) hour training sessions for six (6) personnel shall be conducted.

7. DELIVERABLES:

Before notice to proceed

• Provide product submittals for all equipment to be installed for approval by COR.

• Provide Unit dimensions and weight.

Before contract close out

• Provide two (2) hard-bound copies of Operation and Maintenance (O&M) Manuals to the park for all equipment installed. O&M manuals are to include the manufacturer’s specifications and instructions for all new equipment.

• Provide one (1) hard-bound copy of all warranty information for new equipment to include a list of all model and serial numbers as applicable.

• Conduct training on new equipment and systems for park personnel.

8. GOVERNMENT-FURNISHED PROPERTY, MATERIAL, EQUIPMENT, OR INFORMATION

(GFP, GFM, GFE, OR GFI):

N/A.

9. SAFETY:

The Contractor shall follow all OSHA rules and procedures.

10. SECURITY:

Contractor shall not be permitted in archives without NPS supervision at all times.

11. TRAVEL:

Contractor shall be responsible for all travel related expenses for this project, including mobilization of equipment, tools, materials, manpower, lodging, meals, and per diem.

12. SPECIAL MATERIAL REQUIREMENTS:

N/A.

13. OTHER UNIQUE REQUIREMENTS AND CONSIDERATIONS:

Before using open flames or heat to solder pipes, notify the COR. The fire suppression is heat sensitive and must be shutoff while Contractor is soldering.

The Contractor shall not be permitted access to the artifacts room or file room without supervision from a park staff member.

14. QUALITY CONTROL REQUIREMENT:

The Contractor shall develop and maintain a quality control (QC) plan to ensure services are performed IAW commonly accepted commercial practices. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. As a minimum the Contractor shall develop QC procedures addressing the critical areas identified in this statement of work (SOW). The Government will periodically evaluate the Contractor’s performance IAW the SOW. All new equipment shall conform to the manufacturer’s instructions and guidelines for installation and start-up.

While performing work, the Contractor shall comply with the latest regulations, standards, policies and codes, as applicable identified below:

• NFPA 101 (National Fire Protection Association's Life Safety Code)

• Federal, State and Local Building Codes, Standards and Policies

• International Family of Codes, primarily the IBC (International Building Code)

• American Society of Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE)

Standards and Guidelines

• National Environmental Balancing Bureau (NEBB)

• Associated Air Balance Council (AABC)

• NFPA 101 (National Fire Protection Association's Life Safety Code)

• Federal, State and Local Building Codes, Standards and Policies

• Local codes only if required by utility companies for service connections.

• National Electrical Code (NEC)

• Occupational Safety and Health Administration (OSHA) requirements

Additional Requirements:

• All affected areas shall be restored to their original condition. Any damages shall be fixed and repaired at no cost to the Government.

• All new equipment shall conform to the manufacturer’s specifications.

15. PROJECT PERSONNEL:

Contracting Officer: TBD

Contracting Officer Representative (COR): TBD

Park Facility Manager: Brad Lenz

16. SITE VISIT:

A site visit is scheduled for Friday, July 21, 2023, at 11:00 A.M. AST. Please email the Contracting Officer at william_vazquz@nps.gov to confirm your attendance no later than 24 hours before the site visit time. If no emails of confirmed attendance are received, the site visit will be cancelled. Contractors will meet Facility Manager Brad Lenz at Plaza Norzagaray located at Castillo San Cristobal. Please contact Brad Lenz at 787-644-3338 if you are unable to find the location. Contractors must submit all questions in the form of an RFI to the Contracting Officer no later than Tuesday, July 25, 2023, at 1:00 P.M. AST. No questions will be accepted after this date and time.

17. PROPOSAL DUE DATE:

The new due date for quotes is Tuesday, August 1, 2023, at 3:00 P.M. AST. All quotes must be emailed to the Contracting Officer at william_vazquez@nps.gov. No quotes will be accepted after this date and time.

mailto:william_vazquz@nps.gov mailto:william_vazquez@nps.gov

1. Background
2. Objectives:
3. Place of Performance:
4. Period of Performance:
5. Scope:
6. Tasks:
7. Deliverables:
8. Government-Furnished Property, Material, Equipment, or Information (GFP, GFM, GFE, or GFI):
9. SAFETY:
10. Security:
11. Travel:
12. Special Material Requirements:
13. Other Unique Requirements AND CONSIDERATIONS:
14. Quality CONTROL REQUIREMENT:
15. Project Personnel:
16. site visit:
17. Proposal due date: