Q_A___0002.pdf
PDF 80 KB Posted
- Attached to
- HI FIBER Federal contract opportunity
- Solicitation number
- 140P5322Q0032
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5322Q0032_Amd_0002.pdf | ||
| HI_Visitors_Center_Buxton_Sheet_2_0002.pdf | ||
| Sol_140P5322Q0032_Amd_0001.pdf | ||
| SOW_CAHA_HI_Fiber_Optics.pdf | ||
| Appendix_C_Splice_Plans_CAHA_HI_Fiber_Optics.pdf | ||
| 003_Form_2_.pdf | ||
| Price_Schedule_5_14__21.pdf | ||
| Appendix_A_Site_Plan_CAHA_HI_Fiber_Optics.pdf | ||
| Dare_wages_nc65.pdf | ||
| Sol_140P5322Q0032.pdf | ||
| 002_Form_1___Past_Performance_Quesionnaire.pdf | ||
| Appendix_B_NPS-Cable-Standard-v-1_0.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Will the government be providing the Hatteras Island Page 2 Drawing? Currently there are two drawings labeled Page 3.
Page 2 is added as an amendment to the SOW.
2. The Statement of Work lists Key Personnel (Section 2.2) as Fiber Optics Fuser, and Cable Tester.
However, the Solicitation Document lists Key Personnel (Section H.4) as Project Manager, Site Superintendent, Subcontractor Superintendent. Please confirm which positions are Key Personnel and clarify the supporting documentation required.
Fiber Optics Fuser and Cable Tester require a certificate to be submitted to show qualification. We only need a list names and contact info for the Project Manager, Site Superintendent , and sub contractor superintendent.
3. Solicitation Section L.10.3.2a States “Complete Past Performance Form”. Does this refer to
002_Form_1___Past_Performance_Quesionnaire? If so, is the intent of the COR to have the bidders collate the Past Performance Questionnaires as part of our Proposal Package – or does the COR intend to receive these separately from each example contract COR directly?
Both Forms must be completed and submitted with the Quote.
4. In lieu of completed 002_Form_1___Past_Performance_Quesionnaire would CPAR copies be acceptable?
No
5. Due to the similarity of the work of CAHA-HI and CAHA-BI (Solicitation 140P5322Q0031) is it to be assumed that intended work is to be completed concurrently during the Periods of Performance (09/01/2022 to 11/30/2022), or in succession?
The projects can be completed either concurrently or in succession.
6. Is it the intent of the government to receive the supplementary documentation (SF 1442, SF30, Certs & Reps, etc.) as a single file or separate files? The content may be submitted as a single PDF file or multiple files within one email.
7. Does the government expect a single file for the response? Or Technical Volume, Relevant Prior Experience Volume, Price Volume as listed in Section M.1 Evaluation Factors?
A multiple file response or a single PDF file which incorporates all the required documents will be acceptable in lieu of strict organization of the Technical approach as described in the
Instructions for the Submission of Offers and Other Information.
8. Will the proposal package require a Cover Letter?
No
9. Is there a page limit for Relevant Prior Experience Form responses? There is no page limit.