A02_added_work_STATEMENT_OF_WORK_Q5_and_Q6_0002.pdf
PDF 1 MB Posted
- Attached to
- STRI REPLACE PLUMBING AND MOLD REMEDIATI
- Solicitation number
- 140P5226R0007
About this file
This is a Statement of Work for comprehensive rehabilitation of two residential structures (Quarters 5 and Quarters 6) located at Stones River National Battlefield in Murfreesboro, Tennessee, dated 2026. The project encompasses demolition of deteriorated plumbing and HVAC components, mold remediation, installation of new PVC plumbing systems (both interior and exterior), HVAC ductwork replacement, crawlspace encapsulation with dehumidification systems, and drainage improvements. Quarters 5 work includes full crawlspace encapsulation, dehumidifier installation with condensate pump, and cast iron to PVC plumbing replacement. Quarters 6 work includes similar scope plus demolition and replacement of deteriorated plumbing fixtures (two toilets with Kohler Arch fixtures specified), approximately 316 lineal feet of French drain installation, gutter downspout extensions, HVAC duct system installation for a 1,750 square foot house, and negative air machine operation during mold remediation activities. All work must comply with International Residential Code, International Plumbing Code, International Mechanical Code, OSHA 29 CFR 1926, and local and state building codes.
Work is to be phased sequentially with Quarters 6 completed entirely before Quarters 5 commences. Quarters 5 is currently occupied government housing, and occupants will be relocated to Quarters 6 upon completion. The contractor must maintain continuous access and utility services to adjacent facilities (NRM building, Maintenance Yard, and Quarters 5), with any temporary shutdowns requiring advance written approval from the Contracting Officer's Representative. Operating hours are 7:00 AM to 4:00 PM, Monday through Friday, excluding federal holidays and government closures. Contractor obligations include submitting safety plans, plumbing and HVAC layout drawings, product data sheets, and test reports on Government CM-16 forms for COR approval. Payment is a lump sum price with invoicing through the Invoice Processing Platform at www.ipp.gov. Final inspection and punch list completion are required before government acceptance. All employees must be legally authorized to work in the United States and have no prior felony convictions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK:
“Quarters 6 Plumbing Replacement, Mold
Remediation, HVAC Installation, and Crawlspace Encapsulation”
“Quarter 5 Plumbing Replacement and Crawlspace Encapsulation”
DATED:
“2026”
Stones River National Battlefield 3501 Old Nashville Hwy Murfreesboro, TN.37129
1. Summary of Work
This project consists of comprehensive rehabilitation of Quarters 5 and Quarters 6, two residential structures located within Stones River National Battlefield. The project includes demolition of deteriorated plumbing and HVAC components, mold remediation, installation of new PVC plumbing (interior and exterior), HVAC duct system replacement, crawlspace encapsulation, installation of dehumidification systems, and drainage improvements.
Work at Quarters 5 includes full crawlspace encapsulation, installation of a dehumidifier system with condensate pump, and replacement of existing cast iron plumbing piping with new PVC piping.
Work at Quarters 6 includes demolition and replacement of deteriorated plumbing components, crawlspace encapsulation, HVAC ductwork replacement, installation of a dehumidification system, installation of approximately 316 lineal feet of French drain to direct water away from the structure, and installation of gutter downspout extensions to improve drainage away from the building foundations.
All work shall comply with applicable International Residential Code (IRC), International Plumbing Code (IPC), International Mechanical Code (IMC), OSHA 29 CFR 1926, and all local and state building codes.
The contractor shall maintain continuous access and utility service to adjacent facilities throughout the duration of the project. Access to the Natural Resource Management (NRM) building (111 Old Lodge Lane), the Maintenance Yard (115 Old Lodge Lane), and Quarters 5 (Q5) (107 Old Lodge Lane) shall not be obstructed or restricted without prior coordination and approval from the NPS Facility Manager. Sewer services to the NRM building, Maintenance Yard, and Q5 shall remain operational at all times during construction. Any required temporary shutdowns shall be minimized during duration and scheduled in advance with written approval from the Contracting Officer’s Representative (COR).
2. Project Tasks
Quarters 6 Demolition and Removal – Contractor Shall:
• Remove all existing HVAC ductwork within the crawlspace.
• Remove approximately:
o 36 LF of 4” cast iron pipe from interior.
o 20 LF of cast iron pipe and 20 LF of PVC pipe from exit point to past the sag section.
• Remove existing:
o 2 Toilets o 2 Flanges o 2 Traps o All associated plumbing fixtures
• Remove all debris from crawlspace.
• Protect existing utilities, framing members, flooring systems, and structural components during demolition activities.
• Level crawlspace floor and backfill any existing animal intrusion holes.
• Properly dispose of all demolition debris in approved landfill facilities in accordance with applicable federal, state, and local regulations.
• Protect structural components and utilities during demolition.
• Follow OSHA demolition safety standards (29 CFR 1926 Subpart T).
Quarters 5 Demolition and Removal - Contractor Shall:
• Remove existing deteriorated cast iron plumbing piping located within the crawlspace and accessible plumbing components as required for installation of new PVC piping.
• Remove all debris from the crawlspace.
• Level crawlspace floor.
• Protect existing utilities, framing members, flooring systems, and structural components during demolition activities.
• Properly dispose of all demolition debris in approved landfill facilities in accordance with applicable federal, state, and local regulations.
Mold Remediation – Contractor Shall:
• Install negative air machines in the crawlspace during remediation activities.
• Apply approved microbial growth treatment to crawlspace surfaces.
• Remove negative air machines after remediation is complete.
• Dispose of contaminated materials in accordance with EPA mold remediation guidelines.
Quarters 6 Interior PVC Plumbing Installation – Contractor Shall:
• Install new PVC plumbing system servicing:
o Two new Kohler Arch 12 in. 1.28 GFP single flush toilets or equivalent o Three existing sinks
• Connect 1.5 bathrooms, sinks, and kitchen sink to new PVC main exiting the home.
• Inspect subfloor at toilet flange locations; replace deteriorated subfloor as necessary.
• Repair any wall or floor surface that required to be removed related to access for the plumbing install.
• Install two new pressure-assisted toilets (one per bathroom).
• Ensure proper slope of horizontal drainage lines per IPC.
• Test all plumbing for leaks and proper drainage.
Quarters 5 Interior PVC Plumbing Installation – Contractor shall:
• Connect exiting 1.5 bathrooms, sinks, and kitchen sink to new PVC main exiting the home.
• Inspect subfloor at toilet flange locations; replace deteriorated subfloor as necessary.
• Repair any wall or floor surface that required to be removed related to access for the plumbing install.
Quarters 6 Exterior PVC Plumbing Installation – Contractor Shall:
• Use a camera to identify and mark the length of the sag in the pipe.
• Excavate approximately:
o 20 LF of cast iron pipe o 20 LF of PVC pipe
• Use concrete saw to remove two sidewalk sections as required.
• Replace cast iron with PVC pipe
• Correct sag (belly) to ensure proper gravity flow in accordance with IPC.
• Install:
o One cleanout near house o Once cleanout near belly section area
• Backfill trench per building code requirements.
• Repair the two sections of sidewalk that were removed.
• Compact trench backfill in lifts to prevent settlement.
• Patch removed concrete sections
• Seed and straw disturbed ground after final grading
Quarters 6 Drainage Improvements – Contractor Shall:
• Install approximately 316 lineal feet of French drain system at Quarters 6 to intercept and redirect surface and subsurface water away from the structure foundation.
• Coordinate drain routing to avoid damage to existing utilities, sidewalks, vegetation, and cultural landscape features.
• Install geotextile fabric, washed gravel, perforated drain pipe, and discharge piping in accordance with industry standards.
• Ensure positive draining away from the structure to discharge on the low side of the yard.
• Install gutter downspout extensions at Quarters 6 to discharge roof runoff away from the building foundation.
• Restore all disturbed lawn areas through grading, seeding, and straw stabilization.
• Compact trench in lifts to minimize settlement.
Quarters 6 HVAC Ductwork Installation– Contractor Shall:
• Install complete ductwork system for 1,750 SF house (3BR, 1.5BA).
• Insulate all ductwork to prevent condensation.
• Secure ductwork with hangers at proper spans per IMC.
• Connect ductwork to existing 1-ton air-cooled electric AC unit.
• Seal all duct connections to prevent air leakage.
• Balance airflow system.
Quarters 5 and 6 Crawlspace Encapsulation – Contractor Shall:
• Seal all crawlspace vents and openings from interior.
• Seal foundation cracks using caulk or hydraulic cement if present.
• Install minimum 14-mil polyethylene vapor barrier on:
o Crawlspace floor o Crawlspace walls
• Install rigid foam insulation on crawlspace walls.
• Install minimum 70 PPD Aprilaire dehumidifier (or equivalent) with:
o Condensate pump discharge o Dedicated electrical outlet o Wall-mounted controller in utility closet
• Properly dispose of all construction debris.
Testing and Commissioning – Contractor Shall:
• Test plumbing system for leaks and proper drainage.
• Test HVAC system for airflow and performance.
• Test dehumidifier operation and controller functionality.
• Provide written confirmation of system testing and performance.
3. Submittals
• Contractor shall submit safety plan for approval.
• Plumbing layout drawing
• HVAC duct layout
• Dehumidifier product data
• Mold remediation product data
• Test reports for plumbing and HVAC.
• Product data for all next fixtures (e.g. toilets)
• All submittals shall be on the Government CM-16 form and approved by the project
COR.
4. Security
• The contractor is responsible for all materials and equipment on the job site at all times.
• All employees working on the job site shall be legal to work in the United States of America and not be a prior convicted felon.
• Park hours are from 7:00 AM until 4:00 PM. The Contractor may plan to work on site from 7 AM to 4:00 PM Monday thru Friday; except for Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. Contractor shall not work outside of these hours, without prior approval from STRI Facility Manager.
5. Administrative Requirements
• Contractor shall provide all safety equipment to include warning cones and barricades while on site to protect the public and staff members while work is ongoing.
• Jobsite superintendent shall ensure all jobsite personnel are following the site safety plan as submitted and approved.
• Contractor shall sweep the area of dirt and debris at the conclusion of the work.
• Contractor shall verify and locate all underground utilities prior to excavation activities.
• All disturbed areas shall be restored to original grade and appearance.
Work under this contract shall be phased and completed sequentially and shall not occur simultaneously between Quarters 5 and Quarters 6.
The contractor shall complete all work associated with Quarters 6, including final inspections, testing, commissioning, and Government acceptance, prior to beginning construction activities at Quarters 5.
Quarters 5 is currently occupied Government housing. Occupants of Quarters 5 will be temporarily relocated to Quarters 6 upon completion and acceptance of the Quarters 6 work. No demolition, plumbing replacement, crawlspace work, encapsulation activities, or utility interruptions affecting Quarters 5 shall occur until the Government has confirmed relocation of occupants and authorized commencement of work in Quarters 5.
Contractor shall coordinate all scheduling and sequencing activites with the Contracting Officer’s Representative (COR) to minimize operational disruptions and maintain safe occupancy conditions throughout the project duration.
The contractor shall maintain safe access, utility services, and operational continuity to occupied facilities at all times unless temporary interruption s are approved in advanced by the COR.
6. Substantial Completion and Final Inspection
• Contractor shall submit a written request that the project is complete and request a final inspection. The COR will complete the inspection and develop a punch list if there is work remaining o If the COR determines that the work is not complete, he will immediately notify the Contractor, in writing, stating the reasons. After completing the work, the Contractor shall resubmit a request for another final inspection.
7. Post-Construction Inspection
The COR and the contractor’s project manager shall conduct the walk around to do a final inspection after the contractor notifies the COR that the punch list is complete. Any, and all deficiencies shall be corrected before the National Park Service will accept the project.
8. Acceptance of the Work
After all deficiencies have been corrected, and work has been accepted by the Government, payment will be made in accordance with the Schedule of Values.
9. Measure and Payment
Payment will be included under the lump sum price for this project. The contractor must ensure that they are registered in the Invoice Processing Platform at www.ipp.gov as that is the platform to submit invoices and receive payment.
10. Contracted Services Statement
Contractor’s employees, performing services under this award, shall be controlled, directed, and always supervised by the assigned project manager that is fluent in the English Language. Contractor’s management staff shall ensure that employees properly comply with the performance work standards outlined in the scope of work, specifications, and contract documents. The tasks, duties, and responsibilities set forth in the Statement of Work, and Specifications may not be interpreted or implemented in any manner that results in any contractor employee creating or modifying Federal policy, obligating the appropriated funds of the United States Government, overseeing the work of Federal employees, providing direct personal services to any Federal employee, or otherwise violating the prohibitions set forth in Parts 7.5 and 37.1 of the Federal Acquisition Regulation (FAR).
http://www.ipp.gov/
| STATEMENT OF WORK: |
| Stones River National Battlefield |
| 3501 Old Nashville Hwy Murfreesboro, TN.37129 |
File details come from the government source that posted it. Updated .