A04b_ELRO_and_TC_ALARM_SPEC.pdf

PDF 1 MB Posted

Attached to
ELRO-REPLACE OLD INTRUSION DETECTION Federal contract opportunity
Solicitation number
140P4524Q0039
Issued by
Department of the Interior National Park Service Northeast Region

About this file

This document is a project specification for the installation of new intrusion and fire alarm systems at the Eleanor Roosevelt National Historic Site in Hyde Park, New York.

The project consists of removing the existing intrusion detection systems at the Val Kill Factory and Stone Cottage, and installing new intrusion detection systems at those two locations. Additionally, a new fire alarm and intrusion detection system will be installed at the Top Cottage. The systems will be connected to the U.S. Department of Homeland Security Federal Protective Service MegaCenter for monitoring. Key requirements include providing separate point addresses for each initiating device, conducting functional testing, and addressing any deficiencies discovered during testing. The work must be completed by April 2024 and coordinated to minimize disruption to the government's ongoing operations and public access to the historic site.

View the file

Other files for this federal contract opportunity

Other files attached to ELRO-REPLACE OLD INTRUSION DETECTION, newest first.
File Type Posted
Sol_140P4524Q0039_Amd_0001.pdf PDF
B08_Price_Schedule_-_BLANK.docx DOCX document
B08_References_Worksheet.doc DOC document
B03_WD_NY20240007.pdf PDF
A06_ELRO_TC_ALARM_DWGs.pdf PDF
Sol_140P4524Q0039.pdf PDF
A04a_Statement_of_Work.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NEW INTRUSION AND FIRE ALARM SYSTEM

VAL KILL AND TOP COTTAGE

ELRO & HOFR 01 00 00

April 2024 GENERAL REQUIREMENTS

SECTION 01 00 00 – GENERAL REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. The Work of this Section includes the following:

1. Intent and Arrangement of Drawings

2. Definitions and Status of Individuals

3. Codes

4. Project Documents

5. Definitions

6. Site Examination

7. Field Verification

8. Coordination of Work

9. Construction Limits

10. Work Restrictions / Use of Premises

11. Historic Nature of Project

12. Archeological Findings

13. Hazardous Materials

1. Final Acceptance

1.2 INTENT AND ARRANGEMENT OF DOCUMENTS

A. The specifications and drawings are intended to include everything necessary to perform the entire work properly. Every item necessarily required may not be specifically mentioned or shown. Unless expressly stated, all systems and equipment shall be complete and operable.

B. Titles and headings to divisions, sections and paragraphs in these contract documents are introduced for convenience and shall not be taken as a correct or complete segregation of the several units of materials and labor. No responsibility either direct or implied is assumed by the government for omissions or duplications by the contractor or the contractor's lower-tier contractors, due to real or alleged error in arrangement of matter in the subcontract documents.

C. The terms of the contract, general provisions, and general requirements apply to each division of these specifications as fully as if repeated within that division.

D. Items listed under scope of work for each division of the specifications are not necessarily all inclusive.

The contractor shall be responsible for the complete job.

E. Portions of these specifications are of the abbreviated, simplified type and may include incomplete sentences.

1. Omissions of words or phrases such as: the contractor shall, in conformity with, shall be, as noted on the drawings, in accordance with details, a, the, and all are intentional. Omitted words or phrases shall be supplied by inference in the same manner as they are when a note occurs on the drawings.

2. Such terms as: approved, reviewed, equal, as directed, as required, as permitted, acceptable, and satisfactory mean by or to the government.

1.3 DEFINITIONS AND STATUS OF INDIVIDUALS

A. The terms defined in the contract, general conditions, and general provisions shall apply throughout. Certain additional terms and refinements shall apply as specified below.

B. Owner: the term “Owner” or “government” shall mean the United State Government, Department of the Interior, National Park Service.

C. Government: the term “government” shall mean the person duly authorized by the Owner to act as the Contracting Officer; and person or persons duly authorized by the Contracting Officer.

D. Contracting Officer (CO) shall mean the official Government Representative for the Project. The CO shall be assigned by the Government and made known to the Contractor at the time of Award.

The CO's contact information shall be issued at that time.

1. The designation of Contracting Officer (CO) may include:

a. Contracting Officer's Representative (COR).

b. Any other designated person as selected by the Government.

2. Lines of communication between the Government, the CO and the Contractor will be covered at the Preconstruction Meeting.

E. Contracting Officer’s Representative (COR): the term “contracting officer’s representative” shall mean the person designated by the contracting officer to be a liaison between the government and the contractor. During the construction phase, all submittals and communications with the government. The COR will administer the technical requirements of the subcontract and will coordinate the inspection of the work. The COR does not have the authority to make changes to the contract or to obligate the government.

F. Contractor shall mean the company or individual that holds the Contract for the Work of this Project with the Government.

1. Where the word Contractor is used throughout these documents it shall mean the Contractor and all applicable subcontractors.

2. The Contractor shall be responsible for ensuring that all subcontractors receive all pertinent information and perform the Work in compliance with the Project Documents.

G. Contractor: the term "contractor" shall mean the person or firm responsible for the execution of this contract, or any portion thereof. This shall include the prime contractor, all lower-tier subcontractors and any suppliers.

1.4 CODES

A. Applicable provisions of the State of New York Building Code and the codes and regulations of the Department of Energy are hereby referred to and made a part of this contract. All work performed shall be in accordance with such laws, codes, and regulations. The latest edition or supplement or amendment thereto in effect at the time of submittal of bid shall be considered to be the issue in effect (unless shown otherwise) of all applicable laws, codes, and regulations including, but not limited to:

1. New York State Building Code (NYSBC)

2. NFPA 70 National Electrical Code

B. Where codes or standard specifications other than those listed in this paragraph are referred to in the different Divisions of these Specifications, it is understood that they apply as fully as if cited here.

C. Where differences exist between codes affecting this work, the code affording the greatest protection to the government shall govern.

D. If the contractor observes that these drawings and specifications are at variance with the codes, the contractor shall notify the project manager in writing at once for resolution.

E. Pursuant to labor codes contractor shall include in its base bid all costs for provision of adequate sheeting, shoring, bracing, or equivalent method for the protection of life or limb, in conformance with applicable federal and state safety orders.

F. Maintenance clearances shall be maintained around equipment as required by the plans and specifications and/or codes and standards, and as recommended by the equipment manufacturers. The maintenance envelope and equipment access shall be kept clear of any permanent obstruction. It is the contractor’s responsibility to enforce these requirements with all lower-tier subcontractors. The contractor and lower-tier subcontractors shall be responsible for correcting any infringement on this requirement at no cost to the government.

1.5 PROJECT DOCUMENTS

A. In the event of a discrepancy between the requirements of the Specifications and/or Drawings and the Federal Acquisition Regulations (FAR), the FAR shall govern. The FAR can be accessed on the internet:

1. https://www.acquisition.gov/far

B. In case of a discrepancy either in the figures, in the Drawings, or in the Technical Specifications, the matter shall be promptly submitted to the Government, who will make a determination in writing. Any adjustment by the Contractor without such a determination will be at their own risk and expense.

1.6 DEFINITIONS

A. Period-of-Performance (Construction Period) shall mean the period designated in the Project Documents as the time frame, in calendar days, during which the Work of the Project will be performed.

1. See Division 01 Section “Project Schedule” for communication and coordination requirements.

B. Project Documents include:

1. Solicitation, Offer and Award Documents.

2. Drawings produced for the Project. See Document 00 01 50 - List of Drawings.

3. This Project Manual, which contains

a. The General Requirements for the Technical Specifications for the Project.

C. Weather protection shall mean the temporary protection of that work adversely affected by moisture, wind, heat, and cold by covering, patching, sealing, enclosing, ventilating, cooling and/or heating. This protection shall be provided for all work areas, the building and its contents, trafficked adjacent areas, and all construction materials and accessories. Each trade will be responsible for his/her own weather protection as it relates to the work scope.

1.7 SITE EXAMINATION

A. The Contractor and the Subcontractors, as appropriate, are strongly encouraged to visit and examine the existing conditions of the Project Site prior to submission of offer in order for the Contractor to better understand the Work, and aid in forming any questions the Contractor may have prior to the submission of offer.

B. If the Contractor wishes to perform additional site examinations after the pre-proposal meeting, Contractor shall contact the park Facility Manager to coordinate a time. The Park representative is, and may be contacted at:

1. Name: TBD

2. Address: 2400 East Fort Avenue, Baltimore, MD 21230

3. Telephone: TBD https://www.acquisition.gov/far

1.8 FIELD VERIFICATION

A. The Contractor shall verify all existing conditions and new and existing dimensions prior to the commencement of work and/or ordering of products and materials that may affect the Work of this Project. Any and all discrepancies shall be forwarded to the Government in writing for clarification prior to the commencement of work. Any work performed prior to clarification, particularly and including that which may require correction shall be corrected by the Contractor at no additional costs to the Project and the Government.

1.9 COORDINATION OF WORK

A. The contractor shall coordinate and schedule the work of all its lower-tier subcontractors, and shall furnish all information required by them for proper scheduling and execution of the work.

B. In the same manner, the contractor shall coordinate the work with that of the government including reasonable adjustments of schedule in order for other government operations to be conducted.

1.10 JOB CONDITIONS

A. Preservation of existing work:

1. Contractor shall preserve, protect and prevent damage to existing structures, exhibits, utilities and landscaping features. Where damage occurs, Contractor shall repair or replace damaged features to their original conditions at commencement of work to the satisfaction of Contracting Officer and without cost to the Government.

2. Special attention will be given to historic and non-historic fabric of Project and Project Site. Contractor shall request and obtain approval from the Contracting Officer before removing or cutting historic and non-historic fabric (including landscape features) not specifically described in Contract Documents.

B. Disposal of Artifacts: Any and all artifacts and items with historic significance which are uncovered or removed as part of Contractor's site or building work shall become property of the Government. Determination shall be made by Contracting Officer regarding disposition of these objects.

C. Permits: Contractor is responsible for obtaining all permits required by authorities having jurisdiction.

D. Work Areas: Contractor shall confine all operations to as small a space as required to complete Work. Contractor shall select spaces required for activities in support of the Project such as parking, staging, work breaks and other similar activities and propose them for review by Contracting Officer. Contractor shall not change approved work areas without prior review by Contracting Officer.

E. Job superintendent: A full-time superintendent and foreman acceptable to the Contracting Officer's representative shall be assigned to this project during the total period of construction.

There will be at all times an English speaking person in a position of authority at the job site.

F. Storage Areas: Storage shall be confined to areas proposed by Contractor and approved by Contracting Officer. Storage areas shall be left clean after completion of work and all areas restored to their conditions at commencement of work to approval of Contracting Officer.

G. Housekeeping and Rubbish Disposal:

1. Contractor shall maintain Project in neat, orderly and safe condition at all times.

2. Contractor shall provide containers for collection and disposal of waste and trash resulting from work.

3. Location: Location of container(s) larger than one cubic yard shall be proposed by Contractor for review by Contracting Officer. Contractor shall propose location(s) for container(s) to Contracting Officer. Nothing shall be delivered to site until their location(s) is approved by Contracting Officer.

4. No National Park Service containers shall be used for collection or disposal of waste and trash resulting from Work.

5. Contractor shall dispose of waste and trash legally at public or private dump areas beyond park boundary.

6. All deliveries to and collections from the Park of materials, equipment, surplus or waste must be agreed upon in advance with Contracting Officer or Site Supervisor.

7. No burning will be allowed within Park boundary.

H. Safety:

1. Equipment Erection: Barricades shall be safely erected and used to protect workmen, park visitors and building. Equipment operators shall comply with applicable safety codes.

Contractor shall comply with Department of Labor, Occupational Safety and Health Administration (OSHA) regulations.

a. All ladders providing access to the work site shall be removed during Contractor non-working hours.

b. Staging shall be blocked off during Contractor non-working hours to prevent access to the work site.

2. Accident Reports: Accidents shall be reported immediately to the Contracting Officer.

3. Fire Related Reports: Fire related incidents shall be reported immediately to the

Contracting Officer.

I. Air and Water Pollution Control: Contractor shall:

1. Take all necessary and reasonable measures to reduce air and water pollution by any materials or equipment used in Work.

2. Do not dispose of volatile or unstable waste or oils in storm or sanitary drains nor allow such materials to reach streams, rivers, bays or sounds.

J. Existing Utilities:

1. Contractor shall be responsible for protecting all known utilities. If damage occurs the contractor shall repair the utility with no additional expense to the government.

1.11 CONSTRUCTION LIMITS

A. Work Area: The area to be set aside for the work under this contract is shown on the drawings, and the contractor shall confine the construction to the immediate area within the construction limits.

B. Parking—the use of roads—site access:

1. Parking: parking for private vehicles is limited. Parking for contractors, sub-tier contractors and their workers will be limited to the construction limits and as agreed with the government.

2. Site access: The site is open daily at 7 A.M. and closes at 6:00 P.M. and at dusk during winter months. Access at other times must be coordinated with the government.

3. Access to Site: Permission for access to the site may be revoked for any and all persons who violate the university traffic regulations including speed limits, parking restrictions, and directions of the university police. All of the contractor's personnel, operating forces, and delivery personnel shall be made aware of and shall comply with traffic regulations at all times.

1.12 WORK RESTRICTIONS – USE OF PREMISES

A. Contractor's Use of Premises: During construction, Contractor will have use of building spaces, and site areas, within the construction area. Work areas are as indicated within the contract documents and as confirmed by the Government. Contractor's use of premises is limited only by Government's right to perform work, maintain public access and/or employ other contractors on portions of Project and as follows:

1. Buildings and site will be occupied by Government employees throughout the course of the work.

2. Government employees, park visitors and the public will occupy and use the area surrounding the

Project Site throughout the Construction Period.

3. Limits: Throughout the entire duration of the Project, including all Phases of the Work, confine all operations to the limits shown on the Construction Documents.

a. No site, land or earth disturbance shall occur for this Project without written approval of the Government.

4. Driveways, Walkways, and Entrances: Entrances serving premises, driveways pathways, pedestrian areas, sidewalks, parking areas and loading areas shall be kept clear and available to the Government, the public, park visitors and emergency vehicles at all times, unless otherwise agreed to in advance by the Government. Do not use these areas for staging, parking of vehicles or equipment, or storage of materials.

5. Storage of materials and products: Confine to immediate worksite as directed by the Government.

Contractor is allowed a storage container on the Project Site at a location mutually agreeable between Contractor and the Government.

6. Preservation of Adjacent Finishes, Contents and Grounds: Prevent damages to adjacent finishes and grounds. Restore all damages, repairing and/or replacing damaged elements to their original condition prior to damage, with no additional costs to the Government.

7. Existing Utilities and Utility Interruption: Notify the Government and utility company in writing of any proposed disturbances or planned interruptions of existing utilities. Contractor shall submit a Plan of Operations for utility disturbance.

a. Contractor shall be responsible for locating and preventing damage to known utilities. If any damage occurs, contractor shall take action relative thereto and repair utility at no additional expense to the Government. No additional time shall be added to Contract for repairs from damages. Repairs shall commence immediately and be carried out expeditiously and in a professional manner pursuant to and compliant with all federal, state and local codes and regulations, as applicable.

b. If damage occurs to an unknown utility, Contractor shall repair and reconnect utility immediately. An equitable adjustment shall be made in accordance with the Changes clause of the Contract.

c. Interruption of Existing Utility Service: Contractor shall notify the Government forty-eight

(48) hours in advance of utility interruption, and interruption shall be permitted with prior consent of the Government. Two (2) hours is the maximum time allowed for planned utility disruptions unless otherwise written approval by the Government

8. Hauling Restrictions: Contractor shall comply with all US DOT, State DOT and local legal load restrictions in the transport of all materials and products for the Project. The Government reserves the right to impose additional hauling restrictions within Park Boundaries.

a. Contractor is responsible for obtaining any and all permits, special or otherwise, required by authorities having jurisdiction that may be necessary for utilization of adjacent roads for construction operations.

b. Possession of a Permit by Contractor shall not relieve Contractor of liability for damage which may result from construction operations in utilization of said streets and sidewalks.

9. Contractor at all times shall conduct his operations to ensure the safety for all and minimize any inconveniences to the public. All operations shall be compliant with OSHA and other authorities’ regulations, including state and local bodies, having jurisdiction.

B. On-Site Work Hours: Limit work hours to normal business working hours of 8:00 a.m. to 4:00 p.m., Monday through Friday, unless otherwise indicated.

1. Weekend Hours: Weekend work may be permitted with written authorization of the Government.

2. Early Morning Hours: Early morning work may be permitted, with written authorization of the

Government.

C. Non-smoking Building/Premises: Smoking is not permitted within the limits of the Project Site and Park grounds.

D. The following items are prohibited on the premises, including the Project Site and Park grounds:

1. Firearms

2. Ammunition

3. Alcohol

4. Pets

E. All Contractor’s commercial vehicles, including material and product delivery vehicles, shall be equipped with fire extinguishing equipment and first aid supplies as required by U.S. DOT and state DOT.

F. Parking: Contractor shall park all commercial and personal vehicles in areas designated by the Government. Contractor is responsible for managing and coordinating parking for personnel, subcontractors and their personnel and deliveries in a legal manner that does not conflict with site usage by the Government.

G. Permission for access to the site may be revoked for any and all persons who violate the university traffic regulations including speed limits, parking restrictions, and directions of the university police. All of the contractor's personnel, operating forces, and delivery personnel shall be made aware of and shall comply with traffic regulations at all times.

1.13 HISTORIC NATURE OF PROJECT, PROJECT SITE AND SURROUNDS

A. The Contractor shall note and respect the historical significance of the Project, Project Site and surrounds where the work will be performed. Due to this, certain aspects of the Work of this Project may not be performed in a manner and/or with methods commonplace in the current construction industry of today.

It shall be incumbent upon the Contractor to furnish mechanics capable of executing first-class workmanship in the materials and methods specified, and who have the knowledge and experience to take any and all necessary precautions to protect elements of historic significance, structural and decorative, not scheduled to receive work.

B. See Division 01, Sections “Historic Preservation Treatment” and “Photo Documentation for Historic Projects” for further requirements.

1.14 ARCHEOLOGICAL FINDINGS

A. It is not anticipated that this project will require disturbance of the ground around the site, however, the Contractor is advised that there may be archeological remains in the area surrounding the site. Artifacts, structural features, domestic and /or archeological objects of nature, historic or prehistoric, above or sub-surface, found within the construction work area or otherwise on the premises, are and shall remain the property of the Government.

B. See Division 01 Section “Archeological Discoveries” for further requirements.

1.15 HAZARDOUS MATERIALS

A. If any additional Hazardous Material is encountered, all work shall stop in the area of the encounter and Contractor shall notify the Government immediately of discovery and its extent as known. Contractor shall not work in the encounter area until a resolution is established.

1. Contractor shall continue work in all other areas of the Project without interruption or delay, or

2. Contractor shall adjust work and/or begin other work on the Project that is not dependent upon the encounter area.

B. Should the temporary suspension of work at the site due to the discovery result in delays, re-mobilization or in additional work, Contractor will be compensated by an equitable adjustment under the Changes clause of the Contract.

1.16 FINAL ACCEPTANCE

A. Notice that the work is ready for final inspection and acceptance shall consist of a written notice issued to the COR by the contractor stating that the contractor has carefully inspected all portions of the work, has reviewed in detail the drawings and specifications, and that to the best of the contractor's knowledge all requirements and conditions of the contract documents have been fulfilled.

B. Upon receipt of this notice, the COR and the contractor shall make a joint inspection of the work. After deficiencies, if any, have been corrected or accounted for, and after all work is satisfactorily complete, the government will accept the work; and a notice of completion will be filed by the government.

C. Prior to final acceptance, filing of the notice of completion or processing of final payment, the following documents shall be submitted, reviewed, and accepted by the government:

1. Certificates of compliance and performance guarantees and manufacturers’ warranties required under various sections.

2. Record drawings: per paragraph 1.8.g.

3. Operating and maintenance manuals.

4. Instruction of government personnel, as required.

5. All required operations tests.

PART 2 PRODUCTS

2.1 GENERAL

A. See Division 1 Section “Product Requirements” and individual Specifications Sections for requirements.

PART 3 EXECUTION

3.1 GENERAL

A. The Project shall be executed and all construction activities completed by the Contractor as required by the Contract Documents.

B. See individual Specification Sections for specific Execution requirements.

3.2 HOUSEKEEPING

A. The Contractor shall maintain the site in a neat, orderly, and safe condition at all times.

3.3 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

2. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

3. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

4. Remove tools, construction equipment, machinery, and surplus material from Project site.

5. Waste Disposal: Remove all project generated waste from site and dispose of it in a legal manner.

END OF SECTION 01 11 00

ELRO & HOFR 01 11 00

April 2024 SUMMARY OF WORK

SECTION 01 11 00 – SUMMARY OF WORK

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SECTION INCLUDES

A. The Work of this Section includes the following:

1. Project Information

2. Summary of Work

3. Designer’s Estimate of Construction Costs

4. Work Sequence

1.3 PROJECT INFORMATION

A. Project Name: Eleanor Roosevelt National Historic Site – Replace Intrusion Detection Systems

1. Park Alpha Code: ELRO

2. PMIS No: 237533

3. Owner: United States Department of the Interior, National Park Service

4. Park Address: Roosevelt Vanderbilt NHS 4097 Albany Post Rd. Hyde Park NY 12538

5. Project Locations:

a. Factory (Valkill) and Stone Cottage. 106 Valkill Park Road, Hyde Park, NY

b. Top Cottage, 46 Valkill Drive, Hyde Park, NY. This location is not adjacent to the other two and is a drive of several miles away.

B. Any Project Information, including that requested through a Request for Information (RFI), shall be transmitted by e-mail in the appropriate format per the type of document transmitted. Pending the size of the electronic data file(s), the Government may elect to utilize a Teams folder where the receiver must be invited by the Government to access and retrieve the information and the receiver must accept all conditions and regulations relating to such.

1.4 SUMMARY OF WORK

A. The Work of the Project consists of furnishing all materials, labor, equipment and supervision as required for the Project by the Project Documents; as required by applicable codes and regulations; as required by site conditions; as required by the systems manufacturer’s requirements and recommendations; and as required to provide completely operable and operating systems.

B. The Project consists of installing an intrusion detection system in the Valkill factory, installing an intrusion detection system in the Valkill Stone Cottage installing a fire alarm and intrusion detection system in Top Cottage and connecting the new systems in each location with existing telecom connections.

1. Base:

a. Remove the existing Intrusion Detections Systems

b. Provide new Intrusion Detection Systems

c. Functional testing each device in the new systems

d. Addressing deficiencies discovered during testing

e. Retesting of systems, or portions of systems, found deficient is a previous test

f. Repeating testing until none the system have deficiencies

ELRO & HOFR 01 11 00

April 2024 SUMMARY OF WORK

C. Work shall be completed as required by all applicable prevailing codes, including but not limited to the International Building Code, latest edition including all state and local amendments and other codes, as applicable.

D. The Contractor shall perform the work in a manner as to minimize interference with the operation of the facility. The Contractor shall provide a Method-of-Procedure (MOP), for each building that clearly explains the method(s) proposed to implement the work within the limits of the Contract.

E. Contractor shall provide safe OSHA compliant access to the work areas for all personnel, for the moving of equipment and materials and to allow for Government Inspections.

F. Throughout the duration of the Work of this Project the Contractor shall be fully responsible for maintaining the weather-tightness of all portions of the structure effected by the work of the Contract..

1. Contractor or an authorized representative shall be available on two hour notice, twenty-four hours a day for the duration of this Project, to repair and prevent any and all leaks related to the Work.

2. The Contractor shall furnish the Government with the name (s) and personal telephone number(s) of person(s) that will respond in the event of an emergency.

1.5 WORK SEQUENCE

A. The Work will be conducted in One (1) phase.

1.6 GOVERNMENT'S AND THE PUBLIC'S OCCUPANCY REQUIREMENTS

A. Full Owner Occupancy: The Owner will occupy the site and buildings during the entire construction period.

Due to the sensitive historically and culturally important and valuable materials that will remain in each of the buildings, an active overnight security alarm system and fire alarm system must be operational during the entire period of construction. The contractor shall not leave the building without a functioning alarm system during any time when NPS personnel are not scheduled to be in the building (nights, weekends, holidays or periods when the government is shut down). Cooperate with the Owner during construction operations to minimize conflicts and facilitate owner usage. Perform the Work so as not to interfere with the Owner’s operations.

PART 2 PRODUCTS

2.1 GENERAL

A. See Division 1 Section “Product Requirements” and individual Specifications Sections for requirements.

PART 3 EXECUTION

3.1 GENERAL

A. The Project shall be executed and all construction activities completed by the Contractor as required by the Contract Documents.

B. See individual Specification Sections for specific Execution requirements.

3.2 HOUSEKEEPING

A. The Contractor shall maintain the site in a neat, orderly, and safe condition at all times.

B. No food or drinks are permitted within any of the buildings. Food attracts pests and vermin that are harmful to the fabric and furnishings.

3.3 FINAL CLEANING

A. General: Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

ELRO & HOFR 01 11 00

April 2024 SUMMARY OF WORK

B. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

1. Clean Project site, including all areas disturbed by installation activities, including basement areas, of rubbish, waste material, wrappers, cardboard, packing materials, litter, and other foreign substances.

2. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits. Do not use vacuum unless it is a HEPA vacuum to prevent distribution of fine particulate throughout the building.

3. Restore any turf areas outside the buildings that have been disrupted by the contractor’s vehicles or equipment.

4. Remove tools, construction equipment, machinery, and surplus material from Project site.

5. Waste Disposal: Remove all project-generated waste from site and dispose of it in a legal manner.

END OF SECTION 01 11 00

ELRO & HOFR 012700

APRIL 4, 2024 DEFINITION OF CONTRACT LINE ITEMS

SECTION 012700 - DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. This section briefly describes requirements under contract line items as listed on CONTRACT PRICE SCHEDULE (Form CPS-1) for Intrusion Detection Alarm Systems for Val Kill Factory & Stone Cottage and Fire and Intrusion System at Top Cottage.

B. Intent of Section is to explain, in general, what is and what is not included in each Contract Line Item, and limits, areas, or cut-off points where one item ends and another begins.

C. If no Contract Line Item exists for a portion of the Work, include the costs in a related item.

1.2 RELATED DOCUMENTS

A. Documents related to the Work of this Section include, but are not limited to:

1. The Federal Acquisition Regulation (FAR)

2. Division 00, with attention directed to:

a. NER NPS CONTRACT PRICE SCHEDULE (Form CPS-1).

b. DIVISION 01 - all General Requirements Sections of this Project Manual

3. Divisions 02 through 33 - all Trade Sections of this Project Manual.

4. Project Drawings.

1.3 LIST OF CONTRACT LINE ITEMS – (BID ITEMS)

A. Contract Line-Item No. 01, Base Bid: Provide intrusion detection and alarm system for Val Kill Factory and Stone Cottage.

1. This item consists of the following:

a. Furnish, install, program, test and demonstrate intrusion alarm and detection system with multiplexed, modular, microprocessor-based controls, main intrusion alarm control center with dual-tech motion detection and alarm management software, initiation devices and notification appliances, daytime barrier transgression alarms that will trigger audible alarm while the intrusion system is disarmed during guided tours. Provide all communication links to perform monitoring, alarm, and control functions.

b. Develop, install, program and test management software and hardware for main alarm system control station, and perform tests for the complete and proper operation of systems involved.

c. Provide separate point address for each initiating device so that device can be identified by exact device location. Exact device location shall be communicated by point address from the intrusion detection and alarm system control station to the central station.

d. Complete Department of Homeland Security Federal Protective Service MegaCenter subscriber form with system information required for MegaCenter monitoring services.

• Intrusion detection system shall be monitored by the U.S. Department of Homeland Security FPS MegaCenter.

• Intrusion detection system shall be fully compatible with the U.S. Department of Homeland Security FPS MegaCenter central monitoring station interface standards.

ELRO & HOFR 012700

APRIL 4, 2024 DEFINITION OF CONTRACT LINE ITEMS

2. Measurement for payment will be percentage complete one line item per scheduled value.

3. Payment will be made at the contract Lump Sum price.

B. Contract Line-Item No. 02, Base Bid: Provide fire detection and alarm system and intrusion detection for Top Cottage, part of the Home of FDR, located a few miles from the installation at Val Kill.

1. This item consists of the following:

a. Furnish, install, program, test and demonstrate fire alarm and detection system with multiplexed, modular, microprocessor-based controls, main fire alarm control center with fire detection and alarm management software, initiation devices and notification appliances, voice evacuation system and communication links to perform monitoring, alarm, and control functions.

b. Develop, install, program and test management software and hardware for main fire detection and alarm system control station, and perform tests for the complete and proper operation of systems involved.

c. Provide separate point address for each initiating device so that device can be identified by exact device location. Exact device location shall be communicated by point address from the fire detection and alarm system control station to the central station.

d. Complete Department of Homeland Security Federal Protective Service MegaCenter subscriber form with system information required for MegaCenter monitoring services.

• Intrusion detection system shall be monitored by the U.S. Department of Homeland Security FPS MegaCenter.

• Intrusion detection system shall be fully compatible with the U.S. Department of Homeland Security FPS MegaCenter central monitoring station interface standards.

2. Measurement for payment will be percentage complete on line item per scheduled value.

3. Payment will be made at the contract Lump Sum price.

PART 2 - PRODUCTS (Intentionally Not Used)

PART 3 - EXECUTION (Intentionally Not Used)

END OF SECTION 012700

ELRO & HOFR 012973 - 1/1

APRIL 4, 2024 SCHEDULE OF VALUES

SECTION 01 29 73 - SCHEDULE OF VALUES

PART 1 – GENERAL

1.1 FORM AND APPROVAL

A. The form for the Schedule of Values shall be AIA Document G703 Continuation Sheet.

B. If objected to by the Designer or the government, revise and resubmit the Schedule of Values to the Designer's and government’s satisfaction prior to submitting an Application for Payment.

1.2 LEVEL OF DETAIL

A. Provide a breakdown of the Contract Sum in sufficient detail to facilitate ongoing evaluation of Applications for Payment and progress measurement and reports. Provide the following minimum detail:

1. Provide cost breakdown for materials, labor and equipment by building (Factory, Stone Cottage and Top Cottage.

B. Round off, line items to the nearest whole dollar with the total equal to the Contract Sum.

1.3 ALLOCATION OF VALUES

1. Site Work: Provide line items for site work including utilities connection.

A. Each Involved Building or Major Structure:

1. Categorize items by major trades or units of work corresponding to the Divisions and Sections of the Specifications.

2. Further subdivide as desired but maintain a distinct and identifiable correspondence to this allocation.

3. Schedule a significant value for closeout activities and deliverables. Include such things as instructions, warranty, testing, training, as-built drawings, device diagrams, photos, documentation, decommissioning of the old system and other parts of the project that follow the installation of the new system.

B. If Quantity Allowances associated with Unit Prices are stipulated, provide a line item for each.

C. If Lump Sum Allowances are stipulated, provide a line item for each.

1.4 CHANGE PROPOSALS INCORPORATED INTO APPROVED MODIFICATIONS (CHANGE ORDERS)

A. Prior to written approval of a Modification which incorporates the Change Proposal, do not show in any respect on the Schedule of Values a Change Proposal intended to modify the Contract sum, regardless of the Change Proposal’s approval status.

B. After a Change Order which modifies the Contract Sum is approved and signed by the CO:

C. Provide a single line item for each fully executed Change Order with identification by Modification Number.

D. Maintain these line items through the balance of the Project.

PART 2 – PRODUCTS – (Not Used)

PART 3 – EXECUTION – (Not Used)

END OF SECTION 01 29 73

ELRO & HOFR 01 31 00

April 2024 PROJECT MANAGEMENT AND COORDINATION

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. The subjects of this Section includes the following:

1. Definitions

2. Informational Submittals.

3. General Coordination Procedures

4. Coordination of Drawings

5. Requests for Information (RFI’s)

6. Project meetings.

B. Related Requirements:

1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

1.2 DEFINITIONS

A. RFI: Request from Offeror or Contractor seeking information from the government required for clarifications of the Contract Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Schedule of Values: Prepare a schedule of values breaking down the total contract price into discrete line-items that represent payable portions of the project work. Distribute general conditions, overhead & profit and mobilization/demobilization among the individual line items. Schedule a single line-item for closeout document delivery, commissioning and training.

B. Materials and Equipment:

1. The contractor shall submit a complete list of all materials and equipment to be incorporated in the work. Unless a specific time limit for this submittal is established within the provisions of these specifications, this shall be done with such promptness as not to cause delay to the work.

2. All materials and equipment shall be new and within one year of manufacture. No rebuilt, refurbished, remanufactured, or used equipment and materials shall be installed under this project.

3. All project materials shall be furnished in accordance with the Buy American Act, FAR Clause 52.225-9. Requests for waivers per this clause should be submitted with the bid documents.

C. Subcontractor List: Provide with the Proposal a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

D. Record drawings

1. The contractor shall maintain at the site a complete, precise, accurate, dimensioned record of actual locations of the work, including concealed and embedded work, size and type of equipment, and every change or deviation from original subcontract drawings. The contractor shall keep this record legible and correct weekly as the job progresses on black or blue line prints. The contractor shall keep record drawings available for inspection at all times. Record drawings will be inspected before approval of requests for payment.

2. It shall be the responsibility of the contractor to submit to the project manager within ten (10) days after final inspection, one (1) complete marked-up set of subcontract drawings fully illustrating all revisions made by all the crafts in the course of the work. This shall include all field changes, adjustments, variances, substitutions and deletions, whether covered by change order or not.

Underground utility installations must be located precisely as constructed on the marked-up drawings.

1.4 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities, and activities of other contractors, to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-Installation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

1.5 COORDINATION DRAWINGS

A. Coordination Drawings, General: Prepare coordination drawings according to requirements in individual Sections, where installation is not completely shown on Shop Drawings, where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.

1. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of Governmental, structural, civil, mechanical, and electrical systems. Show where existing channels, holes or conduit will allow penetration through walls, ceilings or floors.

b. Indicate dimensions shown on the Drawings. Specifically note dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to Government indicating proposed resolution of such conflicts. Minor dimension changes and difficult installations will not be considered changes to the Contract.

c. Provide clear indications of where existing building fabric may be disrupted by drilling or cutting. Do not cut, drill or otherwise disturb building fabric without consent of the COR.

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

2. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, door floor closers, slab depressions for floor finishes, curbs and housekeeping pads, and similar items.

3. Review: Government will review coordination drawings to confirm that the Work is being coordinated, but not for the details of the coordination, which are Contractor's responsibility.

1.6 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Government will return RFIs submitted to Government by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Contracting Officer, Contracting Officer’s Representative and any other designated government representative.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's solution(s) impacts the Contract Time or the

Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

C. RFI Forms: Form bound in Project Manual or Software-generated form with substantially the same content as indicated above, acceptable to Government.

D. Government's Action: Government will review each RFI, determine action required, and respond. Allow ten (10) working days for Government's response for each RFI. RFIs received by Government after 1:00 p.m. will be considered as received the following working day.

1. The following RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for coordination information already indicated in the Contract Documents.

d. Requests for adjustments in the Contract Time or the Contract Sum.

e. Requests for interpretation of Government's actions on submittals.

f. Incomplete RFIs or inaccurately prepared RFIs.

2. Government's action may include a request for additional information, in which case Government's time for response will date from time of receipt of additional information.

3. Government's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract

Sum, notify Government in writing within ten (10) days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log with each RFI. Include the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Government.

4. RFI number including RFIs that were dropped and not submitted.

5. RFI description.

6. Date the RFI was submitted.

7. Date Government's response was received.

F. On receipt of Government's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Government within seven (7) calendar days if Contractor disagrees with response.

1. Identification of related Contract Modification.

1.7 PROJECT MEETINGS

A. General: Contractor shall attend and participate in the types of meetings and conferences described below.

All meetings shall be at the Project site unless otherwise indicated elsewhere in the Contract Documents.

Contractor shall perform the following duties:

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Date and time of each meeting must be agreed to by the Contracting Officers Representative (COR).

2. Agenda: Review the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Record…