B09_Amdmnt_0002_-_Q_A_0002.pdf
PDF 408 KB Posted
- Attached to
- GATE - REPLACE A/C UNITS AT SAHO BLDG 20 Federal contract opportunity
- Solicitation number
- 140P4522R0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_AMDMNT_0004_-_SOW_0004.pdf | ||
| Sol_140P4522R0001_Amd_0004.pdf | ||
| thumbnail_IMG_0851_0003.jpg | JPG image | |
| thumbnail_IMG_0850_0003.jpg | JPG image | |
| thumbnail_IMG_0857_0003.jpeg | JPEG file | |
| thumbnail_IMG_0853_0003.jpg | JPG image | |
| thumbnail_IMG_0854_0003.jpg | JPG image | |
| thumbnail_IMG_0852_0003.jpg | JPG image | |
| IMG_0856_0003.jpeg | JPEG file | |
| IMG_0855_0003.jpeg | JPEG file | |
| thumbnail_IMG_0859_0003.jpeg | JPEG file | |
| thumbnail_IMG_0858_0003.jpeg | JPEG file | |
| Sol_140P4522R0001_Amd_0003.pdf | ||
| Sol_140P4522R0001_Amd_0002.pdf | ||
| Sol_140P4522R0001_Amd_0001.pdf | ||
| A04_SOW_AC_Replacement_B20.pdf | ||
| Standard_Form_24_-_Bid_Bond.pdf | ||
| B08_Construction_Clauses_Under_SAT.pdf | ||
| _R0001_-_References_Worksheet.pdf | ||
| Sol_140P4522R0001.pdf | ||
| Standard_Form_25A_-_Payment_Bond.pdf | ||
| B03_NJ20210037__10-22-2021.pdf |
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 140P4522R0001 – SAHO Bldg. 20 A/C Units Amendment No. 0002
Q & A
1. Would your agency consider an alternate bid where the oil-fired boiler and the associated hot water coil is dismantled and removed. Two (2) new 2-ton Heat Pumps with a 7 KW auxiliary heating kit would be installed to provide all heating and cooling needs of the building? This approach is consistent with the Governments transition to Clean Energy.
Answer: The Park does not want to go with a Heat Pump.
2. The existing supply ductwork does not contain a Flex Connector to isolate the Fan Coil from the ductwork. Should a Flex Connectors be included in the scope of work?
Answer: Yes. All work shall be completed by code and the installation shall be completed as per the manufacturer.
3. Should new condensate pumps be included in the scope of work?
Answer: Yes, new condensation pumps should be included for both units.
4. Would we want the condensers raised a bit to make sure they are out of the flood plane?
Answer: The condensers does not need to be raised. Just placed on a new Pad.