This document is an Amendment (0001) to a Request for Proposal (RFP) for removing substandard bridges and culverts at Katahdin Woods and Waters National Monument. The solicitation number is 140P4325R0043, issued by the National Park Service (NPS), NER - NE MABO, located in Boston, MA. The amendment provides responses to two Request for Information (RFI) questions and includes a record of attendance from a pre-bid site visit on 08/11/2025. The project period of performance is from 09/01/2025 to 09/30/2026.

The RFI responses clarify licensing and zoning requirements. The National Park Service has completed all necessary permitting and compliance, and the contractor is only required to maintain valid driver's licenses and SAM.gov registration. Regarding zoning, Maine law restricts in-stream work to the period between July 15th and September 30th. Four construction companies attended the pre-bid site visit: Dunbar Construction, Emery Lee & Sons, TBC Excavation Inc., and Clark Contracting, with their representatives and contact information documented on the attendance sheet.

View the file

Other files for this federal contract opportunity

Other files attached to KAWW - REMOVE BRIDGE AND CULVERTS, newest first.
File Type Posted
B08_Solicitation_Attachment_4_Construction_Contract_Administration.docx DOCX document
Sol_140P4325R0043.pdf PDF
B08_Solicitation_Attachment_1_SOW_Bridge_Removal.pdf PDF
B08_Solicitation_Attachment_3_-_DOL_Wage_Determination_ME20250047.pdf PDF
B08_Solicitation_Attachment_2_SOW_Culvert_Removal.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P4325R0043 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Boston MA 02129-4543

PNN

Building I-1 Charlestown Navy Yard Boston National Historical Park

NPS, NER - NE MABO

08/14/20250001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/01/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Remove Substandard Bridge and Culverts at Katahdin Woods and Waters National Monument

The purpose of this Amendment is to provide a response to RFIs 1-2, and to provide a copy of the record of attendance to the organized pre-bid site visit.

Period of Performance: 09/01/2025 to 09/30/2026

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jason Albright

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Request for Proposal Number 140P4325R0043

Remove Substandard Bridge and Culverts at Katahdin Woods and Waters National Monument Amendment 0001

DESCRIPTION OF AMENDMENT/MODIFICATION

The following are a list of questions and responses for the Solicitation Number 140P4325R0043, Remove Substandard Bridge and Culverts at Katahdin Woods and Waters National Monument.

1) Which licenses, certifications, and permitting will be required from the vendor?

Answer: All permitting and compliance is completed by National Park Service and is complete. It is up to the contractor keep any required drivers licenses valid and up to date. The Government does not believe the state of Maine requires a contractor’s license for this type of excavation and rehabilitation work. The contractor shall maintain registration in SAM.gov.

2) Are there any zoning requirements?

Answer: Maine law only allows in-stream work between July 15th and Sept 30th.