Springfield Armory National Historic Site
Springfield, Massachusetts
Replacement of Failing Fire Suppression System
SPAR – 193601
PROJECT SPECIFICATIONS
Construction Documents
NATIONAL PARK SERVICE
NORTHEAST REGION
February 23, 2018
THIS PAGE
INTENTIONALLY LEFT BLANK
SPAR – 193601 00 0110 - 1
TABLE OF CONTENTS
DIVISION 01 GENERAL REQUIREMENTS
011100 SUMMARY OF WORK
012700 DEFINITION OF CONTRACT LINE ITEMS
013100 PROJECT MANAGEMENT AND COORDINATION
013216 CONSTRUCTION PROGRESS DOCUMENTATION
013233 PHOTO DOCUMENTATION FOR HISTORIC PRESERVATION PROJECTS
013323 SUBMITTAL PROCEDURES
TRANSMITTAL
LIST OF MATERIALS SUBMITTAL
013523 SAFETY REQUIREMENTS
HOT WORK POLICY AND PERMITS
013591 HISTORIC PRESERVATION TREATMENT PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
015719.12 NOISE & ACOUSTICS MANAGEMENT
015930 SECURITY REGULATIONS
016700 PRODUCT REQUIREMENTS
017329 CUTTING AND PATCHING
017340 EXECUTION
RFI FORM
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
017900 DEMONSTRATION AND TRAINING
CLOSEOUT AND OPERATION & MAINTENANCE REQUIREMENTS
CONTRACTOR’S MATERIAL AND TEST CERTIFICATE FOR ABOVEGROUND
PIPING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
078413 PENETRATION FIRESTOPPING
DIVISION 09 - FINISHES
092310 REPAIR OF GYPSUM PLASTERING
092900 GYPSUM BOARD
099100 PAINTING
SPAR – 193601 00 0110 - 2
TABLE OF CONTENTS
DIVISION 21 - FIRE SUPPRESSION
210518 ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING
210800 COMMISSIONING OF FIRE SUPPRESSION
211119 FIRE-DEPARTMENT CONNECTIONS
211313 WET-PIPE SPRINKLER SYSTEMS
211316 DRY-PIPE SPRINKLER SYSTEMS
END OF TABLE OF CONTENTS
SPAR – 193601 011100 - 1
SUMMARY OF WORK
SECTION 011100 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work under other contracts.
3. Use of premises.
4. Government's occupancy requirements.
5. Work Restrictions.
6. Additional Requirements
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The Work involves Building 13, also known as the Main Arsenal at the
Springfield Armory National Historic Site, Springfield, MA.
B. The Work consists of the following:
1. The Work of PMIS No. 193601 – Renovation of Fire Suppression System, Building 13 of the Springfield Armory National Historic Site Includes: Comprehensive and coordinated renovation of the Fire Suppression System at all seven levels of Building 13, also known as the Main Arsenal. The building was constructed in 1850 and is one of the most important and iconic structures making up the Springfield Armory complex, a Federally-designated National Historic Landmark District in 1960. The project requires careful consideration and removal and replacement of existing Fire Suppression System components in historically-significant spaces; dedicated, temperature/humidity-controlled archives; offices, meeting rooms and museum spaces; and dedicated mechanical and conveying systems spaces.
C. Project will be constructed under a single prime contract.
1.3 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the
Work of this Contract with work performed under separate contracts.
B. Future Work: Government will award separate contract(s) for the following additional work to be performed at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract. Coordinate all work of this contract with Work of future work indicated below. Contract Documents for future work will be available to Contractor for coordination.
SPAR – 193601 011100 - 2
SUMMARY OF WORK
1. The Work of PMIS No. 193600 – Replacement of Fire Alarm System, Building 13 of the
Springfield Armory National Historic Site Includes: Comprehensive and coordinated replacement of the Fire Alarm System at all seven levels of Building 13, also known as the Main Arsenal. The building was constructed in 1850 and is one of the most important and iconic structures making up the Springfield Armory complex, a Federally-designated
National Historic Landmark District in 1960. The project requires careful consideration and removal and replacement of existing Fire Alarm System components in historically-significant spaces; dedicated, temperature/humidity-controlled archives; offices, meeting rooms and museum spaces; and dedicated mechanical and conveying systems spaces.
2. The Work of PMIS No. 196751 – Replacement of the Security System, Building 13 of the Springfield Armory National Historic Site Includes: Comprehensive and coordinated replacement of the Security System at all seven levels of Building 13, also known as the
Main Arsenal. The building was constructed in 1850 and is one of the most important and iconic structures making up the Springfield Armory complex, a Federally-designated
National Historic Landmark District in 1960. The project requires careful consideration and removal and replacement of doors, frames, Security System and related battery back-up components in historically-significant spaces; dedicated, temperature/humidity-controlled archives; offices, meeting rooms and museum spaces; and dedicated mechanical and conveying systems spaces.
1.4 USE OF PREMISES
A. General: Contractor shall have limited use of premises for construction operations as indicated on Drawings by the Contract limits.
B. Storage of Materials: Confine storage of materials to storage units outside the building .
C. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of
Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to specific rooms where work is being conducted so as to maintain the operations of the building.
a. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
2. Preservation of Natural Features:
a. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
b. Provide temporary barriers to protect existing trees and plants and root zones.
c. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.
d. Do not fasten ropes, cables, or guys to existing trees.
SPAR – 193601 011100 - 3
SUMMARY OF WORK
e. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
3. Government Occupancy: Allow for Government occupancy of Project site.
4. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times.
Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
D. Use of Existing Building: Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
1.5 GOVERNMENT'S OCCUPANCY REQUIREMENTS
A. Maintain and keep operational fire suppression system, fire detection and alarm system and security system at all times during construction.
B. Full Government Occupancy: Government will occupy site and existing building during entire construction period and the building shall remain fully operational throughout the construction period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Government and authorities having jurisdiction.
C. Government Occupancy of Completed Areas of Construction: Government reserves the right to occupy and to place and install equipment in completed areas of building, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and partial occupancy shall not constitute acceptance of the entire project.
1. Before partial Government occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Government will operate and maintain mechanical and electrical systems serving occupied portions of building.
2. On occupancy, Government will assume responsibility for maintenance and custodial service for occupied portions of building.
SPAR – 193601 011100 - 4
SUMMARY OF WORK
D. Public Use of Site
1. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public. Building portion closures will be permitted, when required, upon specific approval of Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Upon specific approval of Contracting Officer.
2. Early Morning Hours: Upon specific approval of Contracting Officer.
3. Hours for Core Drilling: Specific hours approved by the Contracting Officer.
B. Existing Utilities
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: As permitted and coordinated with the Contracting Officer.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
1.7 ADDITIONAL REQUIREMENTS
A. SPAR Curatorial staff will be present at any and all pre-construction meetings to identify and specify needs. Any and all concerns and issues the selected Contractor will be discussed prior to the start of the project with the COTR and SPAR Curator.
B. If Contractors have questions or exceptions to working near museum collections, the COTR and
SPAR Curator will be advised at time of the walk through in order that questions may be answered and Drawings and Specifications amended as appropriate.
C. Contractor will provide regular and recurring consultation as needed with COTR and SPAR
Curator.
SPAR – 193601 011100 - 5
SUMMARY OF WORK
D. Contractors will be guided by an NPS designee in all situations, and the NPS designee will direct Contractor staff to stop work when the NPS designee feels any situation may impair or threaten to impair the safety and integrity of any object or the historic structure.
E. Whereas much of the museum collection will require protection-in-place, SPAR curatorial staff will identify for the Contractor the location of those objects and possible vulnerabilities. Those objects not contained in a box, crate or storage wrap will be protected by dust covers of polyethylene plastic or rip stop nylon and secured with tape to minimize dust and debris infiltration. The completed protection for all identified items in the area must be approved by the park curator before work commences.
F. Once work in an area containing museum collections has been completed, the contractor shall clean debris and dust, and, under the guidance of the park curator or designee, remove plastic sheeting and tape.
G. The NPS designated representative shall have the authority to stop any action by the Contractor because of potentially damaging or unsafe practice to the archival material or those working on the project.
H. The Contractor can only cite their involvement after the completion of the entire project. This increases the safety of the objects throughout the duration of the project.
I. Contractor shall note the historical significance of the Main Arsenal within which the work shall be performed. Because of the historic nature of this site, all aspects of the work of this contract shall be carried out with an emphasis on preserving and protecting the property.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011100
SPAR – 193601 012700 - 1
DEFINITION OF CONTRACT LINE ITEMS
SECTION 012700 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No.0001: PMIS No. 193601 – Renovation of Fire Suppression System.
1. This item consists of comprehensive and coordinated renovation of Fire Suppression
System at all seven levels of the building.
2. Measurement for payment will be all work within Building 13 and extending ioutsied the building for water main connection.
3. Payment will be made at the contract lump sum price.
END OF SECTION 012700
SPAR – 193601 013100 - 1
PROJECT MANAGEMENT AND COORDINATION
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Construction Coordination.
2. Project meetings.
3. Environmental Coordination.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Pre-installation conferences.
7. Project closeout activities.
8. Commissioning activities.
SPAR – 193601 013100 - 2
PROJECT MANAGEMENT AND COORDINATION
1.3 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base
Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.
b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer for resolution of such conflicts.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those
Sections.
B. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Storm Water Pollution Prevention Plan.
11. Indoor Air Quality (IAQ) Management Plan.
12. Contractors Commissioning Plan.
13. Historic Preservation Treatment Plan.
C. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to
Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued.
SPAR – 193601 013100 - 3
PROJECT MANAGEMENT AND COORDINATION
1.4 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Resolution of comments on required Division 01 documents.
4. Coordination of Subcontractors.
5. Labor law application.
6. Modifications.
7. Payments to Contractor.
8. Payroll reports.
9. Contract time.
10. Liquidated damages.
11. Display of Hotline posters.
12. Notice to proceed.
13. Correspondence procedures.
14. Acceptance/rejection of work.
15. Progress meetings.
16. Submittal procedures.
17. As-constructed drawings/operation and maintenance (O&M) manuals.
18. Saturday, Sunday, holiday and night work.
19. Reference materials.
20. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the
Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
g. Construction Schedule update (provide updated CPM).
h. Status of Project Record Drawings and O&M manuals.
i. Other business relating to work.
SPAR – 193601 013100 - 4
PROJECT MANAGEMENT AND COORDINATION
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 013100
SPAR – 193601 013216 - 1
CONSTRUCTION SCHEDULE
SECTION 013216 – CONSTRUCTION SCHEDULE
PART 1 - GENERAL
1.1 SUMMARY
A. This Section consists of Construction Schedule requirements including but not limited to the following:
1. Schedule of Values
2. Construction Schedule Requirements.
3. Construction Schedule Updates.
4. Time Impact Analysis.
B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The
Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment
1.2 DEFINITIONS
A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.
1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.
2. Predecessor Activity: An activity that precedes another activity in the network.
3. Successor Activity: An activity that follows another activity in the network.
B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.
C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.
D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.
E. Float: The measure of leeway in starting and completing an activity.
1. Float: Float is not for the exclusive use or benefit of either the Government or the
Contractor but is jointly owned.
2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.
SPAR – 193601 013216 - 2
CONSTRUCTION SCHEDULE
3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.
F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.
G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.
1.3 SUBMITTALS
A. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.
B. Construction Schedule: After contract award and before the Pre-Construction conference, submit two copies of initial schedule, large enough to show entire schedule for entire construction period.
1. Submit an electronic copy of schedule, in the software it was created in, on CD-R, and labeled Initial schedule with date.
C. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies and one electronic copy.
D. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit one electronic copy and twopaper copies of a Time Impact Analysis. Each Time
Impact Analysis shall include a Fragmentary Network (Fragnet) demonstrating how the
Contractor proposes to incorporate a modification, change, delay, or Contractor request into the
Construction Schedule.
1.4 QUALITY ASSURANCE
A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:
1. Review software limitations, content and format for reports.
2. Verify availability of qualified personnel needed to develop and update schedule.
3. Discuss constraints, including interim milestones and partial Government occupancy.
4. Review delivery dates for Government-furnished products.
5. Review schedule for work of separate Government contracts.
6. Review time required for review of submittals and re-submittals.
7. Review requirements for tests and inspections by independent testing and inspecting agencies.
8. Review time required for completion and startup procedures.
9. Review and finalize list of construction activities to be included in schedule.
10. Review initial schedule comments, resolve issues and progress on incorporating them
11. Review procedures for updating schedule.
SPAR – 193601 013216 - 3
CONSTRUCTION SCHEDULE
B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate in writing and provide the qualifications of an authorized representative in the Contractor's organization who shall be responsible for coordinating with the Contracting Officer during the preparation and maintenance of the Construction Schedule.
1.5 COORDINATION
A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate contractors.
B. Coordinate Construction Schedule with the Schedule of Values, list of subcontracts, Submittals
Schedule, progress reports, payment requests, and other required schedules and reports.
1. In developing the Construction Schedule, ensure that subcontractor work at all tiers, as well as the prime contractor’s work, is included and coordinated in the Construction
Schedule.
2. Secure time commitments for performing critical elements of the Work from parties involved.
3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.
PART 2 - PRODUCTS
2.1 SCHEDULE OF VALUES
A. Breakdown each lump-sum item into component parts of work for which progress payments may be requested. The total costs for the component parts of work shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.
B. Do not break down unit price items. Use only the contract price for unit price items.
C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.
D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting
Officer before the first progress payment is processed.
2.2 CONSTRUCTION SCHEDULE REQUIREMENTS
A. Construction Schedule: Prepare Construction Schedule using a computerized,, resource-loaded, time-scaled CPM network analysis diagram for the Work.
1. Develop and finalize Construction Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.
SPAR – 193601 013216 - 4
CONSTRUCTION SCHEDULE
a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.
2. Establish procedures for monitoring and updating Construction Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.
3. Use "one workday" as the unit of time. Incorporate nonworking days and government holidays into the schedule.
B. Construction Schedule Preparation: Prepare a list of all activities required to complete the
Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.
1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.
2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.
3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.
4. The Construction Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Schedule shows a coordinated plan of the work.
5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.
6. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.
a. The late finish date shown on the schedule shall be the same date as the last day of the contract period.
b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.
c. The Contractor shall limit use of lead or lag duration’s between schedule activities.
d. Activity Duration: Define activities so no activity is longer than 15 days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.
e. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 days, as separate activities in schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.
f. Submittal Review Time: Include review and re-submittal times indicated.
Coordinate submittal review times in Construction Schedule.
g. Startup and Testing Time: Include not less than 3 days for startup and testing and commissioning activities.
h. Substantial Completion: Allow time for Government administrative procedures necessary for certification of Substantial Completion.
SPAR – 193601 013216 - 5
CONSTRUCTION SCHEDULE
7. Constraints: Include constraints and work restrictions indicated in the Contract
Documents and as follows in schedule, and show how the sequence of the Work is affected.
a. Phasing: Arrange list of activities on schedule by phase.
b. Work under More Than One Contract: Include a separate activity for each contract.
c. Work Restrictions: Show the effect of the following items on the schedule:
1) Coordination with existing construction.
2) Limitations of continued occupancies.
3) Uninterruptible services.
4) Partial occupancy before Substantial Completion.
5) Use of premises restrictions.
6) Provisions for future construction.
7) Seasonal variations.
8) Environmental control.
d. Work Stages: Indicate important stages of construction for each major portion of the Work.
8. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final
Completion.
C. Joint Review, Revision, and Acceptance:
1. Within seven calendar days of receipt of the Contractor's proposed Construction
Schedule, the Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the initial Construction Schedule. Any areas which, in the opinion of the Contracting Officer, conflict with timely completion of the project shall be subject to revision by the Contractor.
2. Within seven calendar days after the joint review between the Contractor and Contracting
Officer, the Contractor shall revise and resubmit the Construction Schedule in accordance with agreements reached during the joint review.
3. In the event the Contractor fails to define any element of work, activity, or logic, and the
Contracting Officer review does not detect this omission or error, such omission or error, when discovered by the Contractor or Contracting Officer, shall be corrected by the
Contractor within seven calendar days and shall not affect the contract time.
4. Upon acceptance of the Construction Schedule by the Contracting Officer, the
Construction Schedule will be used to evaluate the Contractor's monthly applications for payment based upon information developed at the monthly Construction Schedule update meeting.
D. Cost Correlation: In the heading of the schedule, provide a cost correlation line, indicating planned and actual costs. On the line, show dollar volume of the Work performed as of dates used for preparation of payment requests.
1. Contractor shall assign cost to construction activities on the Construction Schedule. Costs shall not be assigned to submittal activities unless specified otherwise but may, with
Contracting Officer’s approval, be assigned to fabrication and delivery activities. Costs
SPAR – 193601 013216 - 6
CONSTRUCTION SCHEDULE
shall be included for testing and commissioning activities, operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training
(if applicable).
2. Each activity cost shall reflect an accurate value based on the Contract Price Schedule.
3. Total cost assigned to activities shall equal the total Contract Price.
E. Computer Software: Prepare schedules using a program that has been developed specifically to manage construction schedules.
1. Software: The software shall be the latest version of Primavera Project Planner, version, Primavera Contractor, version, Microsoft Project, version or approved equal.
2. The Contractor shall provide to the Contracting Officer a licensed copy of the software used to create the Construction Schedule and a software reference manual. The software and reference manual will be returned to the Contractor at completion of the Contract
PART 3 - EXECUTION
3.1 CONSTRUCTION SCHEDULE UPDATES
A. Progress Meeting Updates: Provide updated schedule information before each weekly progress meeting.
1. Issue updated schedule concurrently with the report of each such meeting. Incorporate revisions into the schedule in a timely manner.
B. Monthly Schedule Updates:
1. General: Update the Construction Schedule on a monthly basis to reflect actual construction progress and activities throughout the entire contract period and until project substantial completion. The status date of each schedule update shall be the 7th day preceding the progress payment request date.
2. Procedure: The Contractor shall meet with the Contracting Officer each month at a
Construction Schedule update meeting to review actual progress made through the status date of the Construction Schedule update, including dates activities were started and/or completed and the percentage of work completed on each activity started and/or completed.
3. Reports: Concurrent with making revisions to schedule, prepare tabulated reports showing the following:
a. Identification of activities that have changed.
b. Changes in early and late start dates.
c. Changes in early and late finish dates.
d. Changes in activity durations in workdays.
e. Changes in the critical path.
f. Changes in total float or slack time.
g. Changes in the Contract Time.
4. As the Work progresses, indicate Actual Completion percentage for each activity.
SPAR – 193601 013216 - 7
CONSTRUCTION SCHEDULE
5. Progress Payments: The monthly updating of the Construction Schedule shall be an integral part of the process upon which progress payments will be made under this contract. If the contractor fails to provide schedule updates or revisions, then a portion of his monthly payment may be retained until such corrections have been made.
C. Distribution: Distribute copies of accepted schedule to Contracting Officer, Contracting
Officers Representative, Construction Management Representative, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.
1. Post copies in Project meeting rooms and temporary field offices.
2. When revisions are made, distribute updated schedules to the same parties and post in the same locations. Delete parties from distribution when they have completed their assigned portion of the Work and are no longer involved in performance of construction activities.
D. Construction Schedule Revisions:
1. Required Revisions: If, as a result of the monthly schedule update, it appears the
Construction Schedule no longer represents the actual prosecution and progress of the work, the Contracting Officer will request, and the Contractor shall submit, a revision to the Construction Schedule. The Contractor may also request reasonable revisions to the
Construction Schedule in the event the Contractor's planning for the work is revised. If the Contractor desires to make changes in the Construction Schedule, the Contractor shall notify the Contracting Officer in writing, stating the reason for the proposed revision.
Accepted revisions will be incorporated into the Construction Schedule at the next monthly schedule update.
2. Procedure: If revision to the Construction Schedule is contemplated, the Contractor or
Contracting Officer shall so advise the other in writing at least seven calendar days prior to the next monthly schedule update meeting, describing the revision and reasons for the revision. Government-requested revisions to the Construction Schedule will be presented in writing to the Contractor, who shall respond in writing within seven calendar days.
3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DLAYS AND
CONTRACTOR REQUESTS:
1. Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the Construction Schedule, the Contractor shall submit to the Contracting Officer a written time impact analysis illustrating the influence of each modification, change, delay, or Contractor request on the contract time.
2. Time Extensions: Activity delays shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the
Construction Schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.
3. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.
SPAR – 193601 013216 - 8
CONSTRUCTION SCHEDULE
4. Procedure: Each time impact analysis shall be submitted within the time period stated in a request for proposal, or the time period designated under the clauses entitled Changes or Default. In cases where the Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, the time impact analysis shall be incorporated into the Construction Schedule at the next monthly schedule update.
5. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using fragnets to demonstrate the effect of the proposed change on the overall Construction Schedule.
END OF SECTION 013216
SPAR – 193601 013233 - 1
PHOTO DOCUMENTATION FOR HISTORIC
PRESERVATION PROJECTS
SECTION 013233 – PHOTO DOCUMENTATION FOR HISTORIC PRESERVATION PROJECTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for the following:
1. Existing Condition images.
2. Periodic construction images.
B. See Division 01 Section "Closeout Procedures" for a complete listing of closeout documents.
C. See Division 01 Section "Demonstration and Training" for submitting videotapes of demonstration of equipment and training of NPS personnel.
1.2 SUBMITTALS
A. Construction Images: Submit images electronically within seven days of taking the image.
Include the following for each:
1. Include Date, time and number (sequentially number all images) in filename.
2. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.
3. Submit digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
B. Closeout: Submit a complete set of digital image electronic files as a Project Record Document.
Submit on either a Compact Disc (CD) or Digital Video Disc (DVD).
1. Provide an index as a separate file on the Disc. List each image as a file name with number, date, and time. Include description and or vantage point image was taken.
2. Submit images that have the same aspect ratio as the sensor, un-cropped.
PART 2 - PRODUCTS
2.1 FORMAT REQUIREMENTS
A. Media: CD-R Archival Gold or DVD-R Archival Gold
B. Media Labels: Archival CD/DVD labeling markers, archival labels, or direct print CD
C. Images: Provide RGB color images as original-capture Tagged Image file format (.tiff) or raw converted to .tiff. Minimum sensor size of 6 mega pixels, and at an image resolution of not less than 1024 by 768 pixels.
SPAR – 193601 013233 - 2
PHOTO DOCUMENTATION FOR HISTORIC
PRESERVATION PROJECTS
PART 3 - EXECUTION
3.1 CONSTRUCTION IMAGES
A. General: Take digital images using the maximum range of depth of field, and that are in focus, to clearly show the Work. Images with blurry or out-of-focus areas will not be accepted.
1. Maintain index with each set of Construction images that identifies the number, date, time, and description for each.
2. Maintain one set of images on Disc in the field office at the Project site, available at all times for reference.
B. Existing Condition Images: Before starting construction, take color digital images of Project site and surrounding properties, including existing items to remain during construction, from different vantage points, as directed by Contracting Officer.
1. Flag construction limits before recording construction images.
2. Take eight separate images to show existing conditions adjacent to property before starting the Work.
3. Take eight separate images of existing buildings either on or adjoining property to accurately record physical conditions at start of construction.
C. Periodic Construction Images: Take 12 color, digital images weekly, with timing each month adjusted to coincide with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last images were taken.
D. Additional Images: Contracting Officer may issue requests for additional images, in addition to periodic Construction images specified.
1. Three days notice will be given, where feasible.
2. In emergency situations, take additional images within 24 hours of request.
3. Circumstances that could require additional images include, but are not limited to, the following:
a. Immediate follow-up when on-site events result in construction damage or losses.
b. Images to be taken at fabrication locations away from Project site.
c. Substantial Completion of a major phase or component of the Work.
d. Extra record images at time of final acceptance.
END OF SECTION 013233
SPAR – 193601 013323 - 1
SUBMITTAL PROCEDURES
SECTION 013323 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop
Drawings, Product Data, Samples, and other submittals.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Government’s responsive action.
B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.
1.3 GENERAL SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with contract documents.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.
a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
B. Submittal List: A submittal list has been attached to the end of this specification section for your convenience. The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The terms and conditions of the contract still require you to satisfy the requirements of the individual specification sections regardless of what is shown on the submittal list.
C. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on Contracting Officer’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.
1. Action submittals
a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.
SPAR – 193601 013323 - 2
b. Re-submittal Review: Allow 30 days for review of each re-submittal.
2. Informational submittals
a. Review: Allow 10 days for review of each submittal.
D. Approved Equals:
1. For each item proposed as an "approved equal," submit supporting data, including:
a. Drawings and samples as appropriate.
b. Comparison of the characteristics of the proposed item with that specified.
c. Changes required in other elements of the work because of the substitution.
d. Name, address, and telephone number of vendor.
e. Manufacturer's literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.
2. A request for approval constitutes a representation that Contractor:
a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.
b. Will provide the same warranties for the proposed item as for the item specified.
c. Has determined that the proposed item is compatible with interfacing items.
d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.
e. Waives all claims for additional expenses that may be incurred as a result of the substitution
E. Additional Copies: Unless additional copies are required for final submittal, and unless
Contracting Officer observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
F. Transmittal: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Architect will return submittals, without review, received from sources other than Contractor.
1. Transmittal Form: All material submittals shall be transmitted using National Park
Service form CM-16. (A copy of the form is included at the end of this section.) No action will be taken on a material submittal item unless accompanied by the transmittal form.
2. Documents required in division 1 are to be delivered under separate cover letter. Do not use the CM-16 Transmittal form for these documents.
G. Identification: Place a permanent label 1 by 4 inches on each submittal for identification.
1. Include the following information on label for processing and recording action taken:
a. Project name, Park, PMIS number, Contract number.
b. Date.
SPAR – 193601 013323 - 3
c. Submittal number or other…