A04_Scope_of_Work_Revision_0002.pdf
PDF 176 KB Posted
- Attached to
- GETT HAZARDOUS TREE REMOVAL Federal contract opportunity
- Solicitation number
- 140P4222R0012
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4222R0012_Amd_0003.pdf | ||
| Pricing_Schedule_0002.xlsx | XLSX spreadsheet | |
| Sol_140P4222R0012_Amd_0002.pdf | ||
| Pricing_Schedule_0001.xlsx | XLSX spreadsheet | |
| Sol_140P4222R0012_Amd_0001.pdf | ||
| Pricing_Schedule.xlsx | XLSX spreadsheet | |
| B03_Wage_Determination.pdf | ||
| Sol_140P4222R0012.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL PARK SERVICE
Gettysburg National Military Park
1195 Baltimore Pike Gettysburg PA 17325
PMIS 189344 Hazard Tree Prevention Project GETT
And other future park tree projects
1.0 OBJECTIVE AND LOCATION
As a result of the Emerald Ash Borer, and normal progression of woodlands, Gettysburg National Military Park has experienced an increase in the number of hazardous trees throughout the park beyond what the park staff can maintain. The intent of this contract is to secure a contractor to remove trees identified by park officials as potentially hazardous.
The trees identified in this contract are on the grounds of Gettysburg National Military Park or Eisenhower National Historic Site in Gettysburg, Pennsylvania.
2.0 GENERAL
A. Trees to be taken down or pruned will be tagged by NPS personnel prior to contractor arrival.
B. Any additional tree or debris removal incidental to felling a tagged tree shall be included in cost of felling the tagged tree.
C. Logs and branches:
a) Chips will be removed unless otherwise directed by the COR.
b) Logs and branches will be removed by the contractor, with the exception of “Witness Tree” wood as identified by the COR.
D. Stumps:
a) Grind all stumps to a depth not to exceed 4” below grade. Stump grindings are to be left on site to preserve any potential archeological resources.
E. Trees that overhang Roads: Branches hanging over roads will be cut back to a height of no less than 13.5 feet above the ground.
F. Trees that overhang Sidewalks and Trails: Branches hanging over sidewalks and trails will be cut back to a height of no less than 10 feet above the ground.
G. All hung tree limbs must be placed on the ground as soon as possible but no later than by the end of each work day.
H. All roads and sidewalks must be left clear of cut stems and branches.
I. Climbing spikes shall not be worn.
J. Vehicles: No vehicles shall be permitted to travel over or park within the area generally defined by the canopy of a tree, except if the tree is to be removed and/or if a bucket truck is the only safe means to treat a tree. The root zone of neighboring trees which are not being treated shall not be traveled over. Load distribution matting may be used.
K. Access to certain areas with large equipment is at the discretion of the Contracting Officer’s (CO)
Representative (COR) or Technical Expert on site.
L. All workers to comply with Federal, State and Local safety requirements.
M. The contractor shall be responsible for ground rehab such as rutting and turf damage.
N. The Contractor shall not permit heavy equipment or vehicles or the stock piling of heavy materials off hard surface roads without the expressed permission of the COR. Limited activity may take place, within the root protection area, with the expressed permission of the COR, only in areas determined to be safe from excessive damage. The root protection area is defined as an area equal to a radius of 1.5 feet for each inch of diameter at breast height (DBH) (i.e. a 10-inch DBH tree will have a root protection area equal to 15 feet from the main trunk in all directions). Any damage resulting from such operations shall be repaired to original condition or to the satisfaction of the COR, at no additional cost to the Government.
O. The Contractor will be held responsible for any damages to, and for maintenance and protection of existing structures and utilities.
P. The Contractor shall preserve and protect all existing vegetation such as trees, shrubs, and grass areas (on or adjacent to trees being removed) which do not reasonably interfere with work. The Contractor shall be responsible for all unauthorized cutting or damage to trees and shrubs, including damage due to careless operation of equipment, stockpiling of materials or tracking of grass and other surfaced areas by equipment. Such damaged areas or materials shall be restored, repaired or replaced by the Contractor at no additional cost to the Government.
Q. Pneumatic tires are a requirement and pavement protection for vehicles over 10,000gvw is required in sensitive areas (2’ rigid foam with two layers of ¾” plywood) Sensitive areas are defined by Historical value and environmental conditions, underground utilities, paths and walkways.
R. The Contractor will be required to furnish all labor, materials, and equipment for cleanup and restoration of all disturbed areas or features, which have been damaged during the course of this contract.
S. Trees identified as “Witness Trees” are not to be removed from the park except for a chipped debris. Any material larger than the capabilities of the chipper, the COR will identify a location for the contractor to deliver the remaining wood to.
T. Trees cannot be fallen onto protected resources like earthworks, stone walls, and other protected resources. Trees growing out of earthworks will be cut as flush to ground as possible. If necessary, some trees may require limb removal prior to felling to diminish the impact of the tree on the ground surface.
No heavy equipment will be authorized for use on top of any earthwork.
U. The Contractor shall provide, erect, and maintain all necessary barricades, danger signals, detour and other signs, and take all necessary precautions for the protection of the work and safety of the public. All such barricades and signs shall be in accordance with the Manual of Uniform Traffic Control Devices (MUTCD, 2003 Edition, as published by the Federal Highway Administration, U.S. Department of Transportation.
V. Preservation of Cultural Features: Confine all operations to work limits of the project. Prevent damage to cultural features. At Gettysburg National Military Park, the cultural landscape (i.e. the cemetery, fences, lanes, tree lines, building complexes, fields and other features that make up the battlefield) is nationally significant and must be protected. Each feature consists of elements that contribute to its significance.
For example, the width, alignment and materials of farm lanes contribute to their significance and must be protected. The elements that are considered significant to cultural features must be protected if possible and restored if disturbance is unavoidable.
1. Keep all disturbances to cultural features to a minimum. Use the narrowest possible construction corridor when a cultural feature, such as a fence or lane, must be crossed or otherwise disturbed. Restore all disturbed cultural features to their pre-construction condition, replacing fences, sections of lanes, and cultural landscape features in kind, at no additional expense to the Government. Coordinate with the Contracting Officer for disturbances to cultural features.
2. Provide temporary barriers to protect cultural features.
3. Do not fasten ropes, cables or guys to existing cultural features.
3.0 PROFESSIONAL QUALIFICATIONS
A. All work shall be under the on-site direction and supervision of a Board-Certified Master Arborist who possesses verifiable experience and technical competence in tree physiology, identification, diagnosis of disorders, and current tree care and safety practices in accordance with accepted industry standards. The Arborist shall be the primary contact with the Government's COR or Technical Expert on site and shall be responsible for directing work in the field, controlling the quality of work and inspecting all completed work to ensure that contract performance requirements are met.
B. All workers shall, through verifiable related training and on the job experience, be familiar with the technical aspects and hazards of tree maintenance work and equipment used in such operations. All workers shall abide by any code of ethics or professional conduct established by the Tree Care Industry Association and the International Society of Arboriculture
4.0 SCOPE OF WORK
A. Definitions
1) Felling/Removal: the felling of a tree and disposal of any logs, branches and other debris in accordance with requirements set forth in this Scope of Work. Trees shall be felled only when there is an adequate felling area at least equal in radius to the height of the tree.
2) Developed Area: The area up to and including ten feet beyond the outer edge of any structure or group of structures; roadway, or trail, or commonly used, maintained grounds including but not limited to picnic areas and historic settings used for education purposes. Developed Areas are most likely accessible by bucket truck.
3) Storm Damaged Tree: A tree which has been blown over either in full or in part, or that has a significant structural defect, damage or lean as a result of a storm.
4) At-Risk Tree: A dead tree (dead longer than two years) or a live tree with a recognizable and significant structural defect, damage or lean that is in the proximity of a high-use or relatively high-use public area and which presents a risk to people or property.
B. Description of Types
1) Tree Felling or Removal
a) All logs, branches and debris from felled trees within a developed area shall be removed from the developed area. No logs or other parts of a tree at risk shall remain suspended above the ground.
b) Trees that cannot be felled due to proximity of the roadways, buildings, structures, utilities, and/or lack of an adequate felling area shall be topped and/or sectioned.
c) The Contractor is responsible for taking all precautions to ensure that the tree will fall where desired.
If a tree cannot be felled safely in one piece, the tree shall be topped and/or sectioned.
d) The Contractor shall take all reasonable precautions to avoid damaging surrounding vegetation, lawn areas, monuments, and utilities (irrigation) and prevent gouging and erosion of soils as a result of tree removal operations.
e) The Contractor shall, on the same day the tree is removed, chip all materials and remove all remaining wood and debris from the park and dispose of legally off site, unless approved otherwise by the COR. Removal from the park and disposal is the responsibility of the contractor.
f) When stump grinding is indicated, the Contractor shall make every effort to minimize any soil disturbance around the stump
2) Takedown of At Risk or Storm Damaged Trees
a) All logs, branches and debris from felled trees within a developed area shall be removed from the developed area. No logs or other parts of a tree at risk shall remain suspended above the ground.
3) Cabling
a) Existing support cables shall be inspected for integrity and replaced or adjusted as necessary to provide continued structural support to the specimen tree and its branches.
b) New cable installation shall conform to ANSI A300 guidelines.
5.0 SAFETY AND ACCIDENT PREVENTION PROGRAM
A. The Contractor shall be responsible for employee and visitor safety on the work site and shall establish an effective accident prevention program and provide a safe environment for all personnel and visitors.
Report to the COR any and all accidents or injuries that occur. Place all required protective barriers and take all necessary measures to assure unauthorized persons do not enter the work site. Assure there are no hazards to park visitors during execution of the work.
B. ACCIDENT PREVENTION PLAN: Before on-site work begins, submit to the COR for acceptance an accident prevention plan containing as a minimum the following information:
A. Name of responsible supervisor to carry out the program.
B. Nearly all trees are located within developed areas containing high densities of pedestrians, vehicles, utilities, and structures; so safety is of the utmost importance.
C. All operations shall be conducted in accordance with ANSI Z133.1-2017 Safety Requirements for Trimming, Repairing, Maintaining and Removing Trees and Cutting Brush and all Federal OSHA, state and local safety requirements.
D. First aid procedures - Provide adequate facilities for the number of employees and the type of construction at the site. Provide adequate training to ensure prompt and efficient first aid.
E. Hazard Assessment - Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to ensure property protection and safety of the public, National Park Service personnel, and Contractor's employees.
F. Training - Assure all employees have adequate initial and continuing training for the tasks that they perform. Also, train and instruct each employee exposed to hazardous materials (explosive, flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury) in safe and approved methods of handling and storage.
G. Emergency Planning - Planning for possible emergency situations including fires, windstorms, lighting storms etc.
H. Housekeeping - Keep project site in a clean, neat, and safe condition at all times.
I. Fire Protection - Maintain adequate and proper fire protection equipment on site at all times.
J. This project is a required safety vest or shirt and hard hat area.
K. The contractor is responsible for all traffic and pedestrian control, including but not limited to signage, and or flagger when working on or adjacent to on roads, or sidewalks. Designated flaggers are required when working over a road and sidewalks
L. The Contractor shall provide a level of public safety, proportionate with exposure, while working at Gettysburg National Military Park
M. The Contractor shall comply in rectifying all unsafe or unhealthy conditions called to his/her attention by the CO or COR.
N. The Contractor shall allow for formal and informal, announced and unannounced, safety inspections at the worksite.
O. All tools and equipment used on any project at Gettysburg National Military Park must meet all OSHA regulations.
P. There will be no smoking in or around any building at Gettysburg National Military Park.
Smoking will be permitted only in designated areas.
Q. Gettysburg National Military Park is a drug and alcohol free workplace.
R. If work is to take place over designated state routes the contractor is responsible for coordination with PENNDOT for any road closures or required permits.
S. If work is to take place over city streets or other property the contractor is responsible for obtaining all permits and road closures.
C. EMERGENCY INSTRUCTIONS: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
D. ACCIDENT REPORTING: Notify COR immediately in the event of a reportable accident. A reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, property damage by accident in excess of $100, and fires. Within 7 days of a reportable accident, fill out and forward to the Contracting Officer a DI-134 form, which may be obtained from Contracting Officer. The
Contractor shall report all other accidents to the Contracting Officer as soon as possible and assist the Contracting Officer and other officials as required in the investigation of the accident.
E. Safety of visitors is of the utmost importance. The contractor will adequately cordon off each work area.
Work areas, at the discretion of the COR, may be required to be fenced off completely with orange safety fence.
F. HARD HATS AND SAFETY VESTS AND PROTECTIVE EQUIPMENT: All construction areas in Gettysburg National Military Park or Eisenhower National Historic Site are deemed Hard Hat and Safety Vest areas. The hard hat area shall be posted by the Contractor and it is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats, safety vest and other necessary protective equipment at all times.
G. The Contractor shall provide, erect, and maintain all necessary barricades, danger signals, detour and other signs, and take all necessary precautions for the protection of the work and safety of the public.
H. No uncompleted work or debris shall be left on sidewalks traveled way or on roadway shoulders overnight or on weekends that present a hazard to public.
6.0 POLLUTION AND EROSION CONTROL
A. During all operations under this contract, the Contractor shall exercise reasonable measures to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and solid or liquid wastes from the Contractor's operations shall be collected and stored in a sanitary, nuisance-free manner and disposed of in a State-approved sanitary landfill or as approved by the Contracting Officer.
B. Oil from crankcases or gear boxes, equipment waste or spilled or excess fuel shall be placed in containers and removed from the work site and disposed of as approved and required by Federal, State, and Local laws.
7.0 SPECIAL REQUIREMENTS
A. This is an Indefinite Quantity (IQ) type contract. All trees to be cut shall be identified and tagged by
(NPS) personnel and ordered by the contracting officer via the issuance of task orders, on Optional Form 347.
B. It is highly recommended that the Contractor verify all measurements regarding this contract by making a site visit.
C. A site visit has been scheduled with the designated COR, Randall Hill on XX XXX XX at XX:XX am.
The meeting will begin at Gettysburg National Military Park, Maintenance Division 405 Taneytown Rd Gettysburg PA 17325 and then travel to the other parks in the city. Please call Mr. Hill for further details and meeting arrangements at 717-752-9171. Any questions that arise during the site visit prior to proposal submission shall be made in writing and submitted to the Contracting Office via email.
D. The contractor, their employees, equipment, and materials may be subject to search by Law Enforcement when working in secure areas or on any Federal property within the Park.
8.0 SCHEDULE
A. Work is to be performed during the hours of 6am and 5pm, Monday through Friday. No work is to be performed on Saturday or Sunday or on federally recognized holidays (unless otherwise authorized by the Contracting Officer 72 Hours ahead of date of work).
B. Period of Performance shall begin upon issuance of each task order and end ninety (90) days thereafter.
C. Once the contractor begins work on a specific effort (i.e. tree removal), they are expected to be on the job site each workday until that effort is complete, weather permitting
D. Work shall be scheduled and arranged so as not to interfere with normal activities of the park, particularly Ranger-led tours scheduled at various hours of the day at various locations throughout the park or any special tours or visiting groups. Advanced notice will be given to the contractor if a conflict is expected to divert from a prearranged schedule. Any plant debris, personnel or equipment that would interfere with any NPS sponsored or NPS permitted activity or event shall be removed prior to the activity. If, at any time, the COR determines that the work is unsatisfactory or is being conducted in an unsafe manner, the contractor will be notified and shall immediately cease all work activities.
9.0 DELIVERABLES
A. Within five days of award, Contractor shall provide the following;
1) Safety and Accident Prevention Plan
2) Proof of Arborist Certification
3) Proof of employee certification and training
4) Job or Activity Hazard Analysis
5) Proof of current vehicle registration and inspection
10.0 INSPECTION/ACCEPTANCE
A. The NPS reserves the right to conduct any inspection it may deem necessary prior to acceptance and approval of payment, to assure that all work conforms to the Statement of Work and any applicable standards, regulations, or laws.