Questions_and_Answers_Draft_0001.pdf

PDF 105 KB Posted

Attached to
MAWA - Conservation of Photography Services
Solicitation number
140P4222Q0067
Issued by

View the file

Other files

File Type Posted
Sol_140P4222Q0067_Amd_0002.pdf PDF
MAWA_(8)_112_0002.jpg JPG image
MAWA_(12)_5891_0002.jpg JPG image
MAWA_(9)_108_0002.jpg JPG image
Descriptive_Inventory_0001.xls XLS spreadsheet
MAWA_(9)_108_0001.pdf PDF
MAWA_(12)_5891_0001.pdf PDF
Sol_140P4222Q0067_Amd_0001.pdf PDF
Updated_Statement_of_Work_0001.pdf PDF
MAWA_(8)_112_0001.pdf PDF
Sol_140P4222Q0067.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 140P4222Q0067 - MAWA Conservation of Photography Services

Questions and Answers

Q1. Can you provide an inventory that describes the materials, with dimensions, and descriptions of items, and any three dimensional components?

A1. Yes, please see attachment, Descriptive Inventory.pdf.

Q2. Can any of the prior surveys or reports be provided to bidders?

A2. See A1.

Q3. Will additional questions be allowed once an inventory is provided?

A3. Yes, final questions are due by 12PM September 2, 2022.

Q4. The SOW calls for treatment of photographs, but the three reference images are of paper and parchment documents.

A4. The three images included with the original SOW are items with additional three dimensional components in need of reproduction. Reference A1, and see attached images, MAWA (8) 112.tif, MAWA

(9) 108.tif, and MAWA (12) 5891.tif for details.

Q5. Is there a preference for digital reconstruction or physical reconstruction of three dimensional components? How many items include additional components in need of reproduction?

A5. Reference A1 and A4. See updated reproduction guidance in the SOW.

Q6. Are there variable or unknown treatment components to the project? If so, how should we construct our bid? Can the requirement be split into multiple line items for known tasks and tasks with unknown variables?

A6. No, this is a Firm Fixed Price requirement. Attached updates to the SOW and Q&A responses should resolve any variables/unknowns and provide sufficient information for a Firm Fixed Price quote.

Q7. Existing frames may not accommodate newly matted reproductions. What should the contractor do if the reproductions cannot fit in the original frames with new matting? What are the options for alternate frames?

A7. Original items will be housed in archival folders, reproductions will be returned to the original frames. Reusing original framing and glazing is a priority. In instances where *****ASK ANGELA*** the matting in the original frames needs to be replaced, select replacement matting of appropriate thickness to fit in existing frames.

Q8. When reframing reproductions, should old glazing be retained or should new UV acrylic be used?

A8. No, neither new UV filtering plexi or new frames are required.

Q9. Please confirm that NPS will provide initial delivery of the artifacts to the contractor. Also please confirm that the contractor is not expected to pack the outgoing artifacts.

A9. Yes, NPS will deliver and pick up the items. However, the contractor is expected to pack the items for transport following treatment and inspection as clarified in the updated SOW.