Amendment_0001_SOW_0001.pdf

PDF 1 MB Posted

Attached to
FRSP DRAINAGE & WATERPROOFING ELLWOOD
Solicitation number
140P4221Q0081
Issued by

View the file

Other files

File Type Posted
Sol_140P4221Q0081_Amd_0003.pdf PDF
Sol_140P4221Q0081_Amd_0002.pdf PDF
Sol_140P4221Q0081_Amd_0001.pdf PDF
VA20210008.pdf PDF
SOW_ELLWOOD_FOUNDATION_WATERPROOFING_INSTALL_DRAINAGE.pdf PDF
Sol_140P4221Q0081.pdf PDF
Experience_Questionnaire.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fredericksburg & Spotsylvania National Military Park (FRSP) National Park Service

Scope of Work

Install Drainage and Waterproofing System at Ellwood Ellwood Manor

36380 Constitution Highway Orange, VA 22960

Project Purpose:

The project will install drainage and waterproof system in basement of Ellwood at the 1798-1804 historic Ellwood Manor. Purpose of the work is to eliminate water infiltration into the basement. The current conditions of the basement foundation walls allow water to enter the basement. The flooding has increasingly gotten worst over this past year, causing irreversible damage to the flooring and wall materials.

The project will provide improved park visitor and employee comfort and safety in the buildings.

Preventing water infiltration into the basement areas of the buildings will significantly reduce the likelihood of flooding, mold/mildew/fungal growth, and associated damage to building components or historical artifacts within the basements.

Work Description/ Scope:

Existing concrete floor in the basement of Ellwood will be saw cut around the perimeter of the building approximately 170 linear feet. Old concrete and dirt will be excavated, and a new trench will be dug for the installation of an interior drainage system in the basement of Ellwood. Contractor will install 170 linear feet of 4inch perforated pipe with Geotech filter fabric around pipe. Pipe will be installed in a 12 to 24-inch-deep trench. Gravel will be placed under perforated pipe and on top to channel water. Contractor will install 170 feet secondary 5inch channel drain in same trench with metal grate at floor level above primary drain and both drains will be daylighted into sump pump crock. A new sump crock will be installed, and perforated pipe and channel drain will be terminated to interior of sump crock. A 1/3 hp AC primary sump pump will be installed with a 1/2 hp battery back- up pump system with batteries, charging system, control box and alarm system in case of primary pump failure. Two new floor drains will also be added and terminate inside sump crock for any A/C or heating pipe drainage that may be needed for building units. Electrical changes such as new circuits, outlets, electric boxes, wiring, breakers, GFCI, metal conduit will be added to complete electrical dedicated circuits to new sump pumps and alarm systems. A Sump pump discharge line will be piped from both pumps to outgoing 4” drain line. All piping for pumps will be schedule 40 PVC pipe, fittings and check valve needed for pump operations.

Contractor will purchase and install a gray waterproof masonry sealant to cover all interior basement walls, floor to ceiling and fill all interior mortar joints vertical and horizontal in the basement at Ellwood with approved sealant and mortar mix from LimeWorks.US site at https://www.limeworks.us All waterproofing and mortar mix will comply with lime products for historic restoration. Concrete floor where drains have been installed will be repaired and poured to a finish close to the original concrete floor. All contractor’s excess material will be removed at job completion of pipes and pumps and basement will be cleaned at contractors’ expense. Contractor will obtain all permits or inspections required by local, City, County, State or Federal agencies needed to perform work before project begins at contractors’ expense. A copy of any permits will be posted at job site and a copy will be given to

CO/COR.

Project Location:

National Park Service Ellwood Manor 36380 Constitution Highway Locust Grove, VA 22508

Execution:

A. Contractor is strongly encouraged to attend a pre-bid site visit.

B. Contractor shall be responsible to field verify all new and existing dimensions, piping, electrical supplies, breakers, switch’s wiring, metal conduit and fittings affecting the installation work of this contract before ordering products.

C. Contractor is responsible for calling Miss Utility and to ensure all utility companies have marked all utilities inside and outside prior to floor removal and digging. Contractor is responsible for any and all damages to companies’ utilities and private utilities damaged during installation of project work. All repairs will be made according to code at contractor’s expense.

D. The contractor shall obtain permits from the town of Orange or any county prior to any on-site work starting. The contractor must abide by all NPS and City building codes for construction.

Contractor must also abide by all OSHA regulations for job site safety and installation.

https://www.limeworks.us/

E. The contractor shall furnish supervision, all labor, materials, tools, and equipment necessary for the excavation around the foundation walls, installation of sealant materials, drainage systems and pump systems for project at Ellwood Manor.

F. All electrical work shall be performed by a license electrician.

G. The contractor shall provide costs itemizing labor and materials for the work and provide services in accordance with the clauses, provisions, governments Description/Specification/Work Statement.

H. Work Quality: The Contractor shall execute this work in an expert manner and direct all personnel with an attitude sensitive to and respectful of the recognized architectural significance of the building and site as well as any archaeological issues during construction.

I. All work will be performed under a single contract.

J. Work Areas: Demolition and construction activities are to be confined to spaces within the limits designated and/or as approved by the Contracting Officer Representative (COR). Access to these and other areas will be as approved by the COR.

K. The Contractor shall be responsible for building security during the duration of this contract. Fire prevention shall be of prime consideration. Contractor must ensure the building has proper heat/cooling and the building envelope continues to be environmentally controlled during construction. The building will remain open as much as possible during construction.

Proposal cost breakdown should include the following items:

A. Contractor shall provide all labor, materials and equipment to perform work listed below:

1. Excavate around foundation walls inside- approximately 170 linear feet.

2. Purchase and install new pumps, piping, electrical and drainage upgrades.

3. Hand dig around all utilities after they have been marked by Miss Utility or by private company.

4. Clean and pressure wash wall surface removing all debris after the installation of new drainage system.

5. Patch holes with approved mortar. A parge coat may need to be applied to make the wall surface flat if any penetrations are needed for new drainage or electrical system upgrades.

6. Install Geotech filter or approved equal - high strength drainage filter fabric.

7. Install flexible perforated plastic drainpipe at the base of the foundation wall on top or beside the footer.

8. All new foundation pipes and new floor drainage pipes shall be separate.

9. Backfill along foundation wall will clean #57 gravel or approved equal.

10. Back fill dirt, compact soil in trench and repour concrete over new drainage and new floor drain. Contractor will be responsible to provide additional clean fill dirt or gravel if needed to bring the level up to finish floor grade.

Contractor’s Use of Premises:

A. Construction Camp: Establishment of a camp for the housing of Contractor’s employees within the park will not be permitted.

B. Scheduling:

1. All work shall be performed during the following hours and days of the week: Monday through Friday, 7:00 A.M. to 4:00 P. M.

2. Work during Federal holidays shall be specially scheduled in regard to the following requirements: The contractor shall provide the COR notice of his intent to work during a Federal holiday; notice shall be provided at least 7 days in advance. The National Park

Service will not provide special compensation rates for work performed by the contractor and crew on such Federal holidays.

C. Ellwood Manor will be open and occupied during construction. Contractor is to maintain safe access for National Park Service personnel throughout the construction phase. If the building needs to be closed, contractor shall provide a construction schedule prior to any on-site work.

D. Parking of Contractor’s and workers’ vehicles not required at the Ellwood Manor shall be in an area approved by the COR. This includes visitors to the construction site.

E. Visitors to the park have year-round access. The Contractor shall maintain safe road conditions for pedestrians during the life of this contract on all park roads used by the Contractor. This will be especially important at the site entrance and on the road to Ellwood Manor.

F. Confine storage of materials to designated areas as directed by the COR.

G. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

1. Provide temporary barriers to protect visitors and other employees from work zone.

2. Do not remove, injure, or destroy trees or other plants while working at Ellwood Manor.

3. Carefully supervise excavating, grading, filling, and other construction while working in or near Ellwood Manor.

4. Provide temporary plywood covers to protect against site slips, trips and falls in exposed trenches or other features which could be a hazard during the course of the work.

H. Existing Utilities: Notify COR and utility companies of proposed locations and times for excavation.

1. Contractor shall be responsible for locating and preventing damage to known or unknown utilities. If damage occurs, repair utility at no additional expense to the Government.

Underground drainage lines are considered to be utility lines and may be encountered within proposed trench routes.

2. If damage occurs to a known or unknown utility, all repairs will be made in accordance to all local codes at contractor’s expense.

3. Interruption of existing utility service to any structure, including the outbuildings, will be permitted only with prior consent of the Contracting Officer.

I. No tobacco products are to be used on site in buildings.

J. The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work.

K. The contractor shall disposal or recycles all construction debris associated with the project.

L. Workmanship shall be warranted for no less than one (1) year from date of substantial completion. Materials shall be warranted in accordance with the manufacturer’s specifications.

M. A pre-construction meeting will be scheduled between the National Park Service and the contractor prior to commencement of work.

Project Conditions:

A. Perform work only when existing and forecasted weather conditions are within the limits established by the manufacturer of the materials and products used.

B. Proceed with installation only when substrate construction and preparation is complete.

Barriers:

A. GENERAL

1. Fences and barrier material may be new or used but shall be suitable for intended safety purpose. Fences and barriers shall be structurally adequate and neat in appearance.

C. FENCING

1. Safety Barrier Fence: Orange plastic fence, minimum height, 4 feet.

Barrier Tape:

A. CAUTION CONSTRUCTION AREA tape will be installed where directed by Contracting Officer Representative (COR) for safe work area.

Protection of the Public:

A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.

B. Erect and maintain barricades, lights, safety cones, danger signals, and warning signs.

C. Adequately barricade and cover any open trench’s or open holes during construction.

D. Protect pedestrian traffic by guardrails, safety tape, cones or fences.

Removal:

A. Completely remove barriers and any equipment and materials no longer needed when work is completed and is approved by CO or COR.

PROJECT SCHEDULES:

PART 1 - GENERAL

1.1 SUMMARY

A. This Section sets forth the administrative requirements for project schedules, including the following: 1. Schedule of Values; 2. Construction Schedule Requirements; 3. Construction Schedule Updates; 4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Government in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's progress payment.

1.2 RELATED REQUIREMENTS

A. The General Requirements, Technical Specifications and Drawings included in this Project Manual, and all other contract documents.

1.3 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources. 1. Critical activities are activities on the critical path.

They must start and finish on the planned early start and finish times. 2. Predecessor Activity: An activity that precedes another activity in the network. 3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Government.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned. 2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity 3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Frag net: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.4 SUBMITTALS

A. Electronic Copies: It is the intent of the Government to limit the number of printed materials.

Email one *.pdf copy of each document to the Government representatives. If an electronic copy cannot be submitted, submit three hardcopies. The Government will return one marked-up copy to the Contractor B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Schedule: After contract award and before the Pre-Construction conference, submit electronic copies of baseline schedule, showing entire schedule for entire construction period.

D. Construction Schedule Updates: Submit estimates of the percent completion of each schedule activity a minimum of seven (7) days prior to each progress payment request. Provide supporting data as necessary.

E. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit electronic copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Frag net), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

1.5 QUALITY ASSURANCE

A. Prior to completing development of the Construction Schedule the Contractor shall review the following with the Government: 1. Software limitations, content and format for reports; 2.

Review delivery dates for Government-furnished products, when applicable; 3. Review schedule for work of separate Government contracts, when applicable; 4. Review time required for review of submittals and re-submittals; 5. Review requirements for tests and inspections by independent testing and inspecting agencies; 6. Review time required for completion and startup procedures;

7. Review time required for obtaining and activating permits;

8. Review and finalize list of construction activities to be included in schedule; 9. Review Government comments, resolve issues and progress on incorporating them; 10. Review procedures for updating schedule;

1.6 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Schedule with the Schedule of Values, list of subcontracts, submittals schedule, progress reports, payment requests, and other required schedules and reports. 1. In developing the Construction Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated. 2. Secure time commitments for performing critical elements of the Work from parties involved. 3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. The total cost of all items on the Schedule of Values shall equal the Contract Price.

B. The Schedule of Values will form the basis for progress payments.

C. Breakdown each lump-sum item shown in the Contractor Bid Form into component work activities used in the schedule, for which progress payments may be requested. 1. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the Construction Schedule submitted under this specification. 2. The total costs for the component work activities shall equal the contract price for that lump-sum item. 3. Include mobilization, general condition costs, overhead and profit in the total dollar value of the component work activities for each lump- sum item and unit price items. a. Do not include mobilization, general condition costs, overhead or profit as a separate item. 4. Unit Prices: Do not break down unit price items. Use only the contract price for unit price items. Include mobilization, general condition costs, overhead and profit in the total dollar value of the unit price items. 5. The Government may request data to verify accuracy of dollar values.

D. The Contractor and the Government shall agree upon an acceptable Schedule of Values before the first progress payment is processed.

E. For the Contractor’s convenience, the Government will review a Draft Pay Request (Pencil Copy) based on the percentage of completion for each item on the Schedule of Values prior to the Contractor’s submittal to the IPP system. The purpose of this submittal is to ensure the Government is in agreement with the Contractor’s estimate of percentage of completion of each task.

PART 3 - EXECUTION

3.1 CONSTRUCTION SCHEDULE UPDATES

A. Progress Meeting Updates: Provide a two (2) week look-ahead schedule, derived from the currently accepted schedule, before each weekly progress meeting. Utilize the look- ahead schedule to facilitate and take notes on discussions held during the progress meeting.

B. Distribution: Distribute copies of accepted Construction Schedule to Government representatives, Subcontractors, testing and inspecting agencies, and other parties identified by Contractor with a need-to-know schedule responsibility.

C. Construction Schedule Revisions: 1. Required Revisions: If, as a result of the monthly schedule update, it appears the currently accepted Construction Schedule no longer represents the actual prosecution and progress of the work, the Government will request, and the Contractor shall submit, a revision to the Construction Schedule. 2. The Contractor may also request reasonable revisions to the currently accepted Construction Schedule in the event the Contractor's planning for the work is revised. 3. Procedure: If revision to the currently accepted Construction Schedule is contemplated, the Contractor or the Government shall so advise the other in writing at least seven (7) calendar days prior to the next schedule review, describing the revision and reasons for the revision. 4. Accepted revisions will be incorporated into the currently accepted Construction Schedule.

3.2 TIME IMPACT ANALYSIS FOR CONTRACT MODIFICATIONS CHANGES DELAYS AND

CONTRACTOR REQUESTS:

A. Requirements: When contract modifications or changes are initiated, delays are experienced, or the Contractor desires to revise the currently accepted Construction Schedule, the Contractor shall submit to the Government a written time impact analysis illustrating the influence of each modification, change, delay, or Contractor request on the contract time.

B. Time Extensions: Activity delays, which result in projecting a late completion date, shall not automatically mean that an extension of the contract time is warranted or due the Contractor. It is possible that a modification, change, or delay will not affect existing critical path activities or cause non-critical activities to become critical. A modification, change, or delay may result in only absorbing a part of the available total float that may exist within an activity chain of the Schedule, thereby not causing any effect on the contract time. Time extensions will be granted in accordance with the terms of the contract.

C. Extension of the contract time will be granted only to the extent the equitable time adjustments to the activity or activities affected by the modification, change, or delay exceeds the total (positive or zero) float available on a particular activity.

D. Procedure: Each time impact analysis shall be submitted within the time period stated in a request for proposal, or the time period designated under the clauses entitled Changes or Default.

In cases where the Contractor does not submit a written request for extension of time and a time impact analysis within the designated time, it is mutually agreed that the particular modification, change, delay, or Contractor request does not require an extension of the contract time. Upon acceptance, the time impact analysis shall be incorporated into the currently accepted Construction Schedule at the next monthly schedule update.

E. Contract Modifications: For each proposed contract modification and concurrent with its submission, prepare a time-impact analysis using frag nets to demonstrate the effect of the proposed change on the overall Construction Schedule.

SUBMITTAL PROCEDURES:

PART 1 - GENERAL

1.1 SUMMARY

A. This Section sets forth administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

B. The Contractor is responsible for providing all submittals including Preconstruction submittals, submittals required by individual General Requirements (Division 01) and Technical Specification sections and all other submittals required by the contract.

1.2 DEFINITIONS

A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.

B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with the requirements.

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols.

An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

1.3 GENERAL SUBMITTAL PROCEDURES

A. General: Provide submittals required by individual Specification Sections. Types of submittals are indicated in individual specific sections. 1. The Government reserves the right to require submittals in addition to those called for in individual sections.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents. 1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity; 2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination. a. Government reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received. 3. Contractor shall sign the transmittal form for each submittal to indicate that submittal has been thoroughly reviewed for all requirements.

C. Electronic Submittals: Submit one (1) electronic copy of each submittal in *.pdf format by email to the Government. Do not upload submittals to third-party or “cloud” services such as “Google Drive”, “Dropbox” or the like. 1. Separate submittals shall be provided for each Specifications section. Do not gang submittals from different specification sections together. 2.

Transmittal Form: All submittals shall be transmitted using National Park Service form CM-16 form. No action will be taken on submittals unless accompanied by the CM-16 transmittal form.

All Government comments and actions will be documented on the Transmittal form and returned to the Contractor. a. Complete the general information at the top of the form; b. Provide all required information based on the submittal type: i. List each separate item in each submittal in the space provided; c. Attach all related documents d. Sign the Transmittal in the contractor section at the bottom of the form. 3. If submittals cannot be submitted electronically deliver three

(3) hardcopies to the Government Representative (or designee). The Government will retain two

(2) copies and return one (1) hardcopy to the Contractor. 4. Physical samples: Provide an electronic CM-16 Transmittal as described above for each type of sample. Deliver the physical sample to the Government Representative (or designee) for processing.

D. Identification: Submittal number or other unique identifier, including revision identifier. 1.

Submittal number shall use a sequential number (e.g., .001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., 001.A).

E. Re-submittals: Make re-submittals using the same process used with the initial submittal. 1.

Note date and content of previous submittal; 2. Note date and content of revision in the title block on the CM-16 and clearly indicate the extent of revision; 3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.

F. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities.

G. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction and review by the Government if requested.

PART 2 - PRODUCTS

2.1 SUBMITTAL LIST

A. The Contractor shall prepare a list of all submittals required by the contract. This Submittals List shall be submitted as a Preconstruction Submittal (see Article 2.2 below). At a minimum the Submittal List shall identify each submittal as Preconstruction, Action or Informational and track dates of submission and dates of approval. The Submittals List shall be reviewed at each Progress Meeting.

B.

2.2 PRECONSTRUCTION SUBMITTALS

A. Preconstruction Submittals shall be provided to the Government a minimum of seven (7) days prior to the Preconstruction Conference. If all Preconstruction Submittals have not been received seven (7) days before to the scheduled Preconstruction Conference date, the conference may be cancelled, Notice to Proceed may not be issued, and the Government may consider other contractual remedies.

B. Preconstruction Submittals include, but may not be limited to, the following: 1. Name, contact information and letter designating Project Manager / Superintendent; 2. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors; 3. Bond Certificates; 4. Insurance Certificates;

C. The Government reserves the right to require Preconstruction Submittals required by the contract whether listed above or not.

2.3 PREMOBILIZATION SUBMITTALS

A. Preconstruction Submittals include, but may not be limited to, the following:. : 1. Project Schedule 2. Schedule of Values; 3. Accident Prevention Plan; 4. A list of Subcontractors for this project; 5. Form 1413 for all subcontractors; 6. Written statements from subcontractors certifying compliance with applicable labor standard clauses; 7. Waste Management Plan; 8. Quality Control Plan; 9. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP); 10.

Historic Preservation Treatment Plan; 11. Qualifications statements and proof of certification required by individual Technical Specifications sections. 12. Name and Contact information for Contractor’s Environmental Coordinator; 13. Submittals List.

2.4 ACTION SUBMITTALS

A. General: 1. Collect information into a single submittal for each specification sections and each type of product, equipment, shop drawing and/or sample. 2. Submittals shall be project specific.

a. Do not submit electronic copies of manufacturers’ full catalogues and/or line(s) of products; b.

Clearly mark each submittal to indicate which products and/or options are being submitted.

B. Product Data: 1. Submit manufacturers’ printed product literature for products and/or equipment as required. If information must be specially prepared for submittal because standard printed data is not suitable for use, submit as Shop Drawings, not as Product Data. 2. Include the following information, as applicable: a. Manufacturer’s product specifications; b. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Government and keep another complete set of instructions at the project site until substantial completion; c. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use; d. Wiring diagrams showing factory-installed wiring, where applicable; e. Printed performance curves, where applicable; f. Operational range diagrams, where applicable; g. Compliance with specified referenced standards. h. Testing by recognized testing agency, where applicable.

C. Shop Drawings: Prepare project specific Shop Drawings where required by individual specifications sections and/or article 2.1.A.1 above. Shop Drawings shall be drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data. 1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable: a. Dimensions; b. Identification of products; c. Fabrication and installation drawings; d. Roughing-in and setting diagrams; e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring. f. Shop work and/or manufacturing instructions;; g. Templates and patterns; h. Schedules; i. Notation of coordination requirements; j. Notation of dimensions established by field measurement; k. Relationship to adjoining construction clearly indicated; l. Seal and signature of professional engineer if specified; m. Wiring Diagrams: Differentiate between manufacturer-installed and field installed wiring. 2. Submit one (1) electronic copy of Shop Drawings in *.pdf format to the Government for review and processing. The Government will review the Shop Drawings and provide written comments and/or notations of required corrections. 3. If Shop Drawings are marked “Not Approved” the Contractor shall address all Government comments and notations and resubmit the Shop Drawings to the Government. 4. Resubmittal of Shop Drawings: If all Government comments and notations have not been adequately addressed the Shop Drawings will be returned to the Contractor as many times as necessary to adequately address all Government comments and notations.

D. Contractors Updated Project Schedule: Comply with the requirements specified in section

PROJECT SCHEDULE.

E. Samples: Submit physical samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed. 1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package. 2. Complete the CM-16 Transmittal for processing and documentation of action on submitted samples. If samples are delivered to the site or other specified Government location(s), email an electronic copy of the Transmittal to the Government Representative (or designee). 3. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample; b. Product name and name of manufacturer; c. Color, finish and or model number(s); d. Sample source; e. Number and title of appropriate Specification Section.

4. Number of Samples: Provide three (3) sets of all samples. The Government will retain one (1) set of samples; and return two (2) sets of samples to the Contractor. One set of samples shall remain at the Project Site throughout construction. 5. Disposition: Maintain sets of approved Samples at Project site, available for quality- control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set. 6. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available. a. Submit full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Government will return submittal with options selected. 7. Samples for Verification: Submit full-size units or samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

2.4 SUBSTITUTION AND APPROVED EQUALS SUBMITTALS

A. Submit pursuant to the requirements of section PRODUCT REQUIREMENTS.

B. For each item proposed as an “approved equal,” submit supporting data, including: 1.

Drawings and samples as appropriate. 2. Comparison of the characteristics of the proposed item with that specified. 3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendors. 5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

C. A request for approval constitutes a representation that Contractor: 1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified. 2. Will provide the same warranties for the proposed item as for the item specified.

3. Has determined that the proposed item is compatible with interfacing items. 4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution. 5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

2.5 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by individual Specification Sections. 1. Email electronic copies of Informational Submittals in *.pdf format to the government Representative (or designee). 2. Certificates and Certifications: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity. 3. Informational submittals that do not comply with the requirements specified in the Contract Documents will be rejected and one copy will be returned.

B. Coordination Drawings:

C. Accident Prevention Plan:

D. Schedule of Values:

E. Waste Recycling Plan:

F. Quality Control Plan:

G. Storm Water Pollution Prevention Plan:

H. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.

I. Welding Certificates: Prepare written certification that welding procedures and personnel comply with the requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.

J. Installer Certificates: Prepare written statements on manufacturer’s letterhead certifying that Installer complies with the requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

K. Manufacturer Certificates: Prepare written statements on manufacturer’s letterhead certifying that manufacturer complies with the requirements in the Contract Documents. Include evidence of manufacturing experience where required.

L. Product Certificates: Prepare written statements on manufacturer’s letterhead certifying that product complies with the requirements in the Contract Documents.

M. Material Certificates: Prepare written statements on manufacturer’s letterhead certifying that material complies with the requirements in the Contract Documents.

N. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting test results of material for compliance with the requirements in the Contract Documents.

O. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with the requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

P. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.

Q. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

R. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

S. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency’s standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with the requirements in the Contract Documents.

T. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

U. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

V. Manufacturer’s Instructions: Prepare written or published information that documents manufacturer’s recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturers.

W. Manufacturer’s Field Reports: Prepare written information documenting factory authorized service representative’s tests and inspections. Include the following, as applicable: 1. Statement on condition of substrates and their acceptability for installation of product. 2. Summary of installation procedures being followed, whether they comply with the requirements and, if not, what corrective action was taken. 3. Results of operational and other tests and a statement of whether observed performance complies with the requirements.

X. Permit Compliance Products: Prepare required information for compliance with permit provisions. Products include written notification of project startup, suspension, and completion of work; photo documentation of site conditions; reports; and drawings.

PART 3 - EXECUTION

3.1 CONTRACTOR’S REVIEW

A. Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.

3.2 GOVERNMENT’S ACTION

A. General: Submittals will be disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval. 1. Any work done or orders for materials or services placed before approval shall be at the Contractor’s own risk.

B. Action Submittals: Government will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM16 Transmittal Form.

The submittal will be marked in one of three ways as defined below: 1. APPROVED: Acceptable with no corrections.

2. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear, and no further review is required. The Contractor shall address all review comments when proceeding with the work. 3. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Government will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

C. Informational Submittals: Government will review each submittal and will either accept or reject it.

D. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

E. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence when the submittal is received by the Government Representative (or designee). When the Government has completed their review and processed the submittal, it will be returned to the Contractor by email. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals. Submittal review times are as follows: 1. Action Submittals a. Initial Review: Allow twenty-one (21) days for initial review of each submittal.

Allow additional time if coordination with subsequent submittals is required. b. Re-submittal Review: Allow fifteen (15) days for review of each re- submittal. 2. Informational submittals a.

Review: Allow fifteen (15) days for review of each submittal.

Example Channel Drain (Secondary Drain Ellwood)

Example Channel Drain (Secondary Drain Ellwood)

Example of sump pump

Example of sump pump tank, pump and battery pump systems.

Example of pump system

Contractor’s Use of Premises:
A. Construction Camp: Establishment of a camp for the housing of Contractor’s employees within the park will not be permitted.
B. Scheduling:
1. All work shall be performed during the following hours and days of the week: Monday through Friday, 7:00 A.M. to 4:00 P. M.
2. Work during Federal holidays shall be specially scheduled in regard to the following requirements: The contractor shall provide the COR notice of his intent to work during a Federal holiday; notice shall be provided at least 7 days in advance. The ...
C. Ellwood Manor will be open and occupied during construction. Contractor is to maintain safe access for National Park Service personnel throughout the construction phase. If the building needs to be closed, contractor shall provide a construction sc...
D. Parking of Contractor’s and workers’ vehicles not required at the Ellwood Manor shall be in an area approved by the COR. This includes visitors to the construction site.
E. Visitors to the park have year-round access. The Contractor shall maintain safe road conditions for pedestrians during the life of this contract on all park roads used by the Contractor. This will be especially important at the site entrance and on...
F. Confine storage of materials to designated areas as directed by the COR.
G. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect visitors and other employees from work zone.
2. Do not remove, injure, or destroy trees or other plants while working at Ellwood Manor.
3. Carefully supervise excavating, grading, filling, and other construction while working in or near Ellwood Manor.
4. Provide temporary plywood covers to protect against site slips, trips and falls in exposed trenches or other features which could be a hazard during the course of the work.
H. Existing Utilities: Notify COR and utility companies of proposed locations and times for excavation.
1. Contractor shall be responsible for locating and preventing damage to known or unknown utilities. If damage occurs, repair utility at no additional expense to the Government. Underground drainage lines are considered to be utility lines and may be ...
2. If damage occurs to a known or unknown utility, all repairs will be made in accordance to all local codes at contractor’s expense.
3. Interruption of existing utility service to any structure, including the outbuildings, will be permitted only with prior consent of the Contracting Officer.
I. No tobacco products are to be used on site in buildings.
J. The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt s...
K. The contractor shall disposal or recycles all construction debris associated with the project.
1. Fences and barrier material may be new or used but shall be suitable for intended safety purpose. Fences and barriers shall be structurally adequate and neat in appearance.
C. FENCING
1. Safety Barrier Fence: Orange plastic fence, minimum height, 4 feet.
Barrier Tape:
A. CAUTION CONSTRUCTION AREA tape will be installed where directed by Contracting Officer Representative (COR) for safe work area.
Protection of the Public:
A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthorized entry.
B. Erect and maintain barricades, lights, safety cones, danger signals, and warning signs.
C. Adequately barricade and cover any open trench’s or open holes during construction.
D. Protect pedestrian traffic by guardrails, safety tape, cones or fences.
Removal:
A. Completely remove barriers and any equipment and materials no longer needed when work is completed and is approved by CO or COR.