Sol_140P4221Q0070_Amd_0001.pdf

PDF 91 KB Posted

Attached to
FLNI SHELTER CONCRETE FACADE AND ROOFING REPAIRS
Solicitation number
140P4221Q0070
Issued by

View the file

Other files

File Type Posted
Quote_Form.xlsx XLSX spreadsheet
Sol_140P4221Q0070.pdf PDF
References_Worksheet.doc DOC document
DB_Wage_Rates.pdf PDF
SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P4221Q0070 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Philadelphia PA 19107 1234 Market Street, 20th Floor

PNC

South/Philadelphia MABO Northeast Regional Contracting National Park Service

DOI, NPS, NERO & NER SOUTH MABO

08/10/20210001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/29/2021

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment is to provide the answers to three questions which were posed during the site visit held on 8/26/2021:

Q1. Is there a vapor barrier between the concrete façade and the roof.

A1. Per the as-constructed drawings, which is what we have to go off of. No one at the

Memorial was on-staff or involved in the original construction.

Q2. Is the roof plywood tapered?

A2. Per the as-constructed drawings, which is what we have to go off of. No one at the

Memorial was on-staff or involved in the original construction.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Jody Auerbach

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P4221Q0070/0001

Q3. Why can you not just use a traditional design, regular gutter, etc?

A3. We are trying to maintain the architect¿s original design and uniformity throughout the memorial.

This procurement is a Total Small Business Set

Aside under NAICS Code 238110.

The estimated construction cost range for this project is between $25K and $100K.

Offerors must have a DUNS Number, an active registration in the System for Award Management

(SAM) (http://www.sam.gov) and have completed their Online Representations and Certifications in SAM in order to be eligible for award.

The firm receiving the contract award will be responsible for providing a Bid Bond upon contract execution.

Any questions regarding this Solicitation must be submitted in writing to Denny Braccia, Contract

Specialist, at denny_braccia@nps.gov. Questions must be received no later than five (5) business days prior to the due date for responses.

All remaining terms and conditions are unchanged.

Period of Performance: 09/01/2021 to 12/31/2021