QUESTIONS & ANSWERS REGARDING:
SOLICITATION/REQUEST FOR QUOTE NO. 140P3021Q0050
Amendment 0001
PRWI Fuel Island Probe Repair
(AMENDMENT 0001)
QUESTIONS RECEIVED AS OF 8/04/2021:
1. Question: “Contractor shall clean entire underground oil/water separator holding tank and render tank free from all debris and contaminants”. Is this stating that you want the tank itself drained and cleaned? Or is it referring to the containment sumps/spill buckets?
ANSWER:
The project would benefit from a tank cleaning in the tank that the new correct probe will be functioning in. This will ensure the probe functions properly at install. The containment sumps/spill buckets will not need the cleaning.