This is Amendment 0001 to Solicitation 140P2125R0007 for Exhibit Planning & Design Services for Exterior Exhibits at Golden Spike National Park, issued by the National Park Service. The amendment extends the proposal due date and provides responses to nine questions received about the solicitation.
Key details from the Q&A include: The project will involve government-to-government consultation with tribal nations and possible consultation with Chinese-American groups and railroad worker descendants; digital content will be delivered through the NPS mobile app rather than a standalone app; exhibits must follow Wayside Exhibit standards for in-ground installation as there are generally no existing foundations except at the Visitor Center pavilion; work samples may include completed but not yet installed projects; both prime contractors and subcontractors must submit past performance questionnaires; writing samples must show integration with graphic design; and samples of work are limited to 20 pages combined for Factor A (overall project samples) and 20 pages combined for Factor B (writing and Digital UX/AR/VR samples). The period of performance is 12/19/2024 to 05/30/2027.
View the file
Other files for this federal contract opportunity
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2125R0007 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PHF
Harpers Ferry WV 25425 IDC Building 67 Mather Place DOI, NPS, HFC - Acquisition Managem
PWA
Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting
11/27/20240001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
11/13/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Exhibit Planning & Design Services for Exterior Exhibits
Golden Spike National Park
The purpose of this amendment is to respond to questions, received by the date and time specified in the solicitation, in accordance with the attached Description of Amendment consisting of three (3) pages.
Period of Performance: 12/19/2024 to 05/30/2027
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Sheila Spring
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation Number 140P2125R0007 Amendment Number 00001
Description of Amendment/Modification Outdoor Exhibit Planning and Design Services for
Golden Spike National Park
The purpose of this amendment is to extend the proposal due date and respond to questions received by the date and time specified in Solicitation Number 140P2125R00007 – Outdoor Exhibit Planning and Design Services for Big Thicket National Preserve. The government response is provided below each question.
1. General: Will this project incorporate consultation from outside groups?
RESPONSE: Yes, the government will conduct government-to-government consultation with affiliated tribal nations, and may also consult with local Chinese- American groups and other descendants of Transcontinental Railroad workers. The government will be responsible for conducting the consultations, and will provide feedback from these groups as part of the official review and comments from the government.
2. Page 9 of 78: The RFP states that “the contractor shall consider use of digital app-based content delivery.” Shall we assume that the content would be integrated into and delivered through the NPS app? Or should we consider the design of a standalone app for this project?
RESPONSE: Yes, assume that content delivery will be through the NPS app.
3. Page 18 of 78: The RFP notes that exhibits should not require major construction or foundations for support. Are there any current foundations that can be used to anchor new exhibits in the areas outlined under space allocation?
RESPONSE: In general, so, there are not current foundations for anchoring new exhibits. The contractor shall plan for exterior exhibits to be installed following Wayside Exhibit standards for in-ground installation (or in some cases, sled bases). See https://www.nps.gov/subjects/hfc/upload/Wayside-Guide-First-Edition.pdf, Section C.
In select locations, such as the pavilion outside the Visitor Center, existing concrete pads can be attached to for non-Wayside-style exhibits such a raised relief map models, or other structures. New concrete pads and new foundations are not within the scope of this project, and will not be provided by the government.
4. Page 68 of 78: Can the samples of work include exhibit planning and design projects that are completed, but not yet installed? Or must the examples be projects that are completed and installed? Page 72 indicates that “samples shall represent work which is either on-going or has been completed,” but page 68 notes “date of installation” as required information.
RESPONSE: Yes, samples of work may include completed planning & design work that is not yet installed. For “date of installation” please not date of Planning & Design completion, and provide anticipated date of installation, if known.
5. Per 22.3, “The offeror shall complete the included Past Performance Questionnaire for three (3) completed, or substantially completed, projects performed by the prime contractor and proposed subcontractors within the last five (5) years for efforts that are similar in scope, complexity, and nature to this project.” Does each subcontractor need to submit 3-5 past performance questionnaires, or is the prime contractor responsible for providing that information?
RESPONSE: Yes, Past Performance shall be submitted for subcontractors as well.
6. For writing samples described in 21.1, “The sample shall be presented as designed within a graphic layout to demonstrate how the writing is integrated and incorporated with image and design, and including enlargements as necessary to ensure all text is legible.” In contexts where the exhibit writer is not the exhibit designer, will you accept text samples outside of layout? Similarly, if the prime contractor has not engaged with exhibit writing, are they able to submit graphic panels with client-provided interpretation?
RESPONSE: The exhibit writer need not also be the exhibit designer, but during the planning & design process, writing and graphic design should merge and become a single, cohesive, final product. For the writing samples, the government will evaluate the writing in the context of the design. If text samples are provided outside of the graphic layout, this would be a deviation, and shall be noted as such, with justification.
Writing samples should be submitted from the proposed exhibit writer for the GOSP Exhibit project; therefore, samples that were prepared with client-provided interpretive text will not be accepted.
7. In reading through the Evaluation Factors (beginning on Solicitation page 68), are samples of work limited to 20 pages each or combined?
RESPONSE: Samples of work shall be limited to 20 pages combined for Factor A (overall project samples), and 20 pages combined for Factor B (writing and Digital UX/AR/VR samples).
8. In 2.8.5.e. original artwork and illustration is assigned to the Production Budget. Can some custom illustration be included in the Design phase if provided by in-house Design team personnel? With the understanding Rights Usage would be secured and transferred to NPS in the same manner non-illustrative image acquisitions would be handled.
RESPONSE: Yes, custom illustration can be included during the planning & design phase by any means (in-house or subcontracted), as long as this fits within the firm-fixed price of the planning & design contract.
9. 23.1 Volume I – Technical Capability, B. Factor B: Key Personnel Samples, ii. Can the Digital UX/AR/VR Designer assume collaboration with NPS is possible in the form of hosting some digital content on the Golden Spike National Park government website and/or NPS mobile app?
RESPONSE: Yes, digital content shall be hosted on the NPS Mobile App, or the GOSP website. Coordination with the NPS Digital team will be required, and shall be facilitated by the government.