This document is an amendment to a solicitation for a federal contract opportunity. The key details are:

The purpose of Amendment 0002 is to: 1) incorporate a revised Offeror Sheet, 2) provide answers to questions received, 3) change the Period of Performance to 120 days after contract award, 4) require offers to be valid for a minimum of 90 days, 5) incorporate an updated SCA Wage Determination, and 6) extend the quote submission due date to September 12, 2024 at 10:00 am Mountain Time.

The federal contract opportunity is for the design, erection, assembly, and installation of OSHA-compliant scaffolding at Sections 1 and 2 of the La Fortaleza Wall at the San Juan National Historic Site. The Contracting Officer is David Clark, and the solicitation number is 140P2124Q0242. Interested parties must be registered in SAM and submit their quote via email to the Contracting Officer by the due date. The contract will be awarded by the Department of the Interior, National Park Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2124Q0242 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

WA2

Frederick MD 21704 4801A Urbana Pike DOI, NPS, Historic Pres Trng Ctr

PWA

Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting

09/04/20240002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/22/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of Amendment 0002 is to:

1. Incorporate revised Offeror Sheet. Offerors are hereby instructed to submit the attached

Offeror Sheet with their quote. Using the previous version will be deemed non-compliant with the solicitation.

2. Provide answers to questions received.

3. Period of Performance had been changed to 120 days after contract award.

4. Submitted offers must be valid for a minimum of 90 days from the provided response date.

5. Incorporate updated SCA Wage Determination as Attachment 2, dated 07-22-2024.

6. Quote submission due date has been extended to September 12, 2024 at 10:00 am Mountain

Time (12:00 pm Eastern Time).

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

David Clark

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2124Q0242/0002

All other terms and conditions remain unchanged.

FOB: Destination

Change Item 00010 to read as follows(amount shown is the obligated amount):

00010 Scaffold Assembly, Rental, and Disassembly

Product/Service Code: 5440

Product/Service Description: SCAFFOLDING

EQUIPMENT AND CONCRETE FORMS

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Combined Synopsis/Solicitation

Document No.

140P2124Q0242, Amendment 2

Document Title La Fortaleza Wall Scaffolding, San Juan NHS

INSTRUCTIONS TO OFFERORS:

Quotes must be in accordance with and in the order detailed in this section. Failure to submit quotes according to the instructions provided within the solicitation may result in the respondent’s quote not being considered for award.

Interested parties must be registered in the System for Award Management or SAM at time an offer or quotation is submitted.

The offerors must submit a quote to the Contracting Officer, David Clark via email at david_clark@nps.gov no later than 10:00 am Mountain Time (12:00 pm Atlantic Time), on September 12, 2024.

Submitted offers must be valid for a minimum of 90 days from the provided response date.

Offers must submit the following information requested in a) – d) below:

a) Checklist for quote submittal:

This page of the solicitation completed as the first page in the package ☐ All amendments acknowledged using one of the methods set forth in Box 11 of the SF-30 ☐ Completed Provisions (including 52.204-24, 52.204-26, and others as applicable) ☐

b) Provide a project narrative that demonstrates how the company will successfully meet the needs of the statement of work (limit to two pages) ☐

c) Price Schedule and Schedule Confirmation:

Fill in the Price Schedule below for a breakdown of costs and confirm schedule ☐

Offeror Confirmation Offeror Signature (digital or wet signature is acceptable)

Offeror confirms all work will be completed on or before 120 days after contract award.

d) Contractor Core Data:

Offerors Company Name: ____________________________ Offerors POC: ______________________________________

Offerors Unique Entity Identifier (UEI): __________________ Offerors Phone/Email: ________________________________

Description Quantity Unit Total

Labor (Includes Phase 1 & Phase 2 Erecting and Dismantling, IAW SOW)

Installation 1 Lump Sum $

Removal 1 Lump Sum $

Rental Fees/Material

Description Quantity Unit Total

Materials/Rental 91 Days $

Grand Total $

# Questions Answers

1 Can we get a forklift down to the wall? Yes.

Is the tree so fully grown that we have to cut down branches while scaffolding the wall? Are we allowed to cut the branches?

Contractors will not be allowed to cut branches. Any vegetation removal to the large "historic/legacy tree" will need to be completed via the NPS or Government of PR.

Can we hire a crane to get at the edge of the wall to lower down the scaffolding to the base of the wall?

There will be no access for a crane at the site.

Do we need any background checks or security clearance to work on the Fortaleza wall?

Background checks may be required. Contractor will be required to abide by the regulations stated in the contract clause 52.222‐3 Convict Labor.

5 When is the presumed start date for this project?

Pending funding availablity. Contractor will be expected to start and complete work within 120 days after contract award.

How often does this scaffold need to be inspected during the job period?

Contractor should have an OSHA certified specialst sign‐off that the scaffolding is up to code after its erected. NPS will inspect daily and notify contractor if adjustments are required.

7 Will this be a Light, Medium, or Heavy Duty Scaffold. Heavy duty scaffolding.

Are we able to keep all of our scaffolding at the bottom of the wall/ will it be a fenced area?

The work area will be fenced off and scaffolding will stay on site. On site storage (staging) will be limited to el paseo but shall occur during POP. No early staging.

Do we need Debris netting? Would they rather have it shrink wrapped for weather control and dust control?

Debris netting yes, shrink wrapped no.

10 Can we tie the scaffold into the wall itself? This can occur with on‐site approval from NPS and territory.

11 How close does the scaffold have to be to the wall for work use?

The scaffold needs to be within 16‐18 inches from the wall. We will be removing vegetation, power washing, and making masonry repairs.

La Fortaleza Wall Scaffolding (SAJU)

140P2124Q0242

9/4/2024

File details come from the government source that posted it. Updated .