This document contains an amendment to a solicitation for a boundary survey of a property known as APPA 415-18 Morgan's Mill. Key details include:

  • The National Park Service is seeking a contractor to perform a boundary survey of a 415-acre property to be acquired and managed by the agency.

  • The amendment provides answers to questions submitted by contractors regarding project requirements such as the acceptability of partially completed example projects, use of off-road vehicles, boundary marking obligations, and signage responsibilities.

  • The response deadline is extended to February 13, 2024.

  • The period of performance is expected to run from February 19, 2024 to December 27, 2024.

  • The contracting officer is Luis A. Cibrian and can be contacted at luis_cibrian@nps.gov.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2124Q0049 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PWA

Denver CO 80225 P.O.Box 25287 MS WCP NPS, WASO - WCP Contracting

01/22/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

01/22/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to publish answers to questions submitted by contractors:

See continuation pages.

The due date for quote submission is hereby extended to February 13, 2024 by 3:00 PM

Eastern Time

All other terms and conditions remain the same.

APPA SUBMITTED QUESTIONS and ANSWERS:

Q1: Is it required that the three examples all be completed projects?

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Luis Cibrian

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2124Q0049/0001

A1: It would be preferrable if they were completed projects, and we would like to see examples of filed plats included with submission.

However, any project over 50% completion will be accepted.

Q2: Will the use of a side by side off road vehicle or similar be allowed?

A2: Off road travel is not preferred; however, there may be some administrative use allowed with prior approval from the Chief Ranger for the AT.

Q3: Will the setting of Intermediate On-line

Monuments be required between the subject parcel

415-18 and the existing property parcels 415-07 and 415-13?

A3: The existing Fed boundary probably has intermediary monuments in the ground, and they are to be left in place. The intent is not to set any new monuments along existing Fed boundary unless controlling corner(s) are determined obliterated or lost. If it is determined that intermediary monuments were not previously set, there is no need to establish them during this survey.

Q4: On Page 16 of 23 of the SOW:

Obliteration of Old Line Markings: The signs and posts (if applicable) originally installed along the old Exterior Corridor Boundary must be removed and salvaged for future use. Blazes must be painted over with OSHA approved exterior black or gray enamel provided by the contractor.

References will be painted over but left in place. Monuments and caps will be left in place.

Please confirm that the SOW includes

¿Obliteration of Old Line Markings¿ between the subjectparcel 415-18 and the existing property parcels 415-07 and 415-13?

A4: Obliteration of boundary will occur between existing fed boundary 415-07 and 415-13, and that includes marking over old paint and pulling old boundary signs and posts (includes every type of

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

3 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2124Q0049/0001 boundary marking material). Monuments are to be left in place.

Q5: Statement of Work, Page 6 of 23, Item No. 6

(Other Survey Tasks)

¿All Exterior Corridor Boundary lines will be marked with blazing, paint, and signage. (see

Exhibit B ¿Line Marking and Posting Attachment¿ for more details and specifics)¿

Will NPS Provide the Signs, or will Contractor need to provide the signs for the exterior boundary marking?

A5: The contractor will provide signs and other material needed to complete the project, in coordination with the NPS. See page 5 of 23

(sec. II (c) 5a) and page 9 of 23 (Items to deliver by Contractor).

Q6: Statement of Work, Page 15 of 23, Item 1

(Boundary Signs)

If signs will need to be affixed to Metal Fence

Posts or a Carsonite Post, is there a preferred color for each?

A6: Boundary signs will be affixed to standard green metal fence posts, in the rare event that a

Carsonite post is appropriate, they will be brown.

Q7: Statement of Work, Page 6 of 23, Item No. 6

(Other Survey Tasks)

Will the Exterior Boundary line marking and posting be able to be performed at the same time as the rest of the surveying functions, or will that have to be performed after the property has been transferred to NPS?

A7: Marking the boundary is considered a post-acquisition task and is assumed to be completed once the tract is owned by the United

States, managed by the NPS. However, it is anticipated that NPS will close on this acquisition prior completion of the survey work.

Can be discussed at prework meeting.

Period of Performance: 02/19/2024 to 12/27/2024

Contracting Officer; Luis A Cibrian, Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

4 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140P2124Q0049/0001 luis_cibrian@nps.gov

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)