This document is an Amendment (Amendment 0002) for Solicitation 140P2025R0036, a National Park Service project to rehabilitate the A.G. Gaston Motel at Birmingham Civil Rights National Monument in Alabama. The amendment extends the proposal due date from July 9, 2025, to July 16, 2025, and incorporates a comprehensive set of questions and answers that provide critical details about the project's scope and requirements.

Key project details include: the project involves rehabilitation of a historic civil rights structure, with complexities such as helical pier installation, potential elevator pit excavation, abatement work, and historic preservation considerations. The contract requires total building commissioning for all systems, potential involvement of an architectural conservator, and specific guidelines around personnel roles (e.g., superintendent must be a dedicated individual separate from safety and quality control roles). The project will require careful coordination with local authorities, adherence to historic preservation standards, and management of technical challenges like matching existing brick and handling infrastructure installations. The solicitation indicates the project is fully funded and will involve comprehensive restoration of the A.G. Gaston Motel.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P2025R0036 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PDS

Denver CO 80225-0287 P.O. Box 25287 1 Denver Federal Center, Building 50 DOI, NPS, DSC Contracting Services

PDS

Denver CO 80225-0287 P.O. Box 25287 1 Denver Federal Center, Building 50 NPS, DSC Contracting Services Div

05/15/20250002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/15/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

BICR 316236 Rehabilitate Civil Rights Structures (A.G. Gaston Motel) at Birmingham Civil

Rights National Monument, Birmingham, Alabama

Amendment 0002 is issued to do the following:

1. Incorporate the questions and answers into the solicitation.

2. To attach the Pre-Proposal Site Visit Sign-In sheet.

3. The proposal due date of July 9, 2025, is extended to July 16, 2025, at 1700 ED.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Cary Atwood

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

140P2025R0036 Amendment 0002

Ques ons and Responses:

1. Sheet C-100. The entire parking lot at the corner of 5th Avenue and 15th Street is shown to be able to be utilized for laydown and storage. This is not what was explained at the walk-thru. Please advise if entire lot can be utilized by the contractor during construction?

Answer: Refer to drawing C100 for staging areas.

2. Please provide soils report to be utilized in conjunction with the Helical Pier installation?

Answer: Structural design loads are shown on S001 and S003. Soil reports “Geotechnical Report.pdf” and “Gaston Motel Shear Wave Survey Report.pdf” were included in the solicitation attachments 4 and 5.

3. Based on very current information regarding this project, the elevator pit excavation could compromise the footing on the external wall. Will additional underpinning for the corner of the building where the excavation for the elevator pit will be required? Has that corner of the building already been underpinned?

Answer: Drawing S101 shows underpinning with helical piles at elevator pit.

4. Equipment to access to the working area of the elevator pit will require at least 50” opening to drive the helical piles. Please provide location where this opening can occur?

Answer: This is Contractor Means & Methods question, but we assume the equipment may need to be reconfigured or disassembled/reassembled to utilize existing openings.

5. Section 07 5400. Please provide manufacturer of existing roof? Walkway Pads are to be by “roofing manufacturer”.

Answer: FiberTite

6. Various Notes. “Blank off vents from inside with insulated panel above ceiling” Please provide specification for insulated panels to blank off vents?

Answer: Will determine after award and during material submittals.

7. Section 09 6500. 2.01 A.1.a & 3. VCT is specified to be Armstrong Excelon SDT 9” x

9”. This produce is 12” x 12”. 9” x 9” tile is not manufactured. Please advise?

Answer: Will determine after award and during material submittals.

8. Based on Drawings AV001-AV502 and specifications 27 40 10 - 42 40 90. There is shown and specified AV infrastructure in the form of back boxes, floor boxes, a credenza and cabling but there are no AV devices that mount to this infrastructure. Additionally there is a performance specification but no AV equipment specified to build a performance specification on or to test on. Is the actual AV equipment in the bid or is it a later bid/ contract or sole sourced to the owner?

Answer: AV equipment is supplied by others and not in this contract.

9. The structural engineer is calling for 15 kips allowable compression and tension. A remedial foundation bracket will only work in compression and does not provide any tension capacity. Can the tension requirement be eliminated?

Answer: No, not during solicitation.

10. The 2 required load test for non-production helical piers. 1 test is for compression and 1 test for tension?

Answer: Test per helical pile manufacturer and standard industry practices.

11. The current bid date falls on the Monday following the July 4th holiday weekend. Would the Government consider extending the bid date to account for the holiday schedule?

Answer: Yes, to July 16, 2025

12. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

Answer: The job site superintendent role must be a dedicated individual and separate from the on-site safety and quality control roles. The SSHO and QC manager can be one individual.

13. Are there any phasing requirements?

Answer: NPS has no phasing requirements.

14. If the building remains occupied, how many people will be in the building?

Answer: The building will not be occupied during construction.

15. Are there any temporary heating/cooling requirements?

Answer: No

16. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

Answer: Long lead items should be identified by the Contractor in their proposal. NPS can authorize long lead material purchases after award and before the NTP to minimize impact to period of performance.

17. Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

Answer: Soil reports “Geotechnical Report.pdf” and “Gaston Motel Shear Wave Survey Report.pdf” were included in the solicitation attachments 4 and 5.

18. Please provide bidding quantities for deteriorated underlayment (roofing)/base course

(paving).

Answer: Not available.

19. Please confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system.

Answer: FiberTite is the roofing system and the installer was CSC Roofing.

20. Please provide the contact information for the building fire alarm company.

Answer: TBD after award

21. Please provide the site visit attendee sign-in sheet.

Answer: Attached

22. Please provide photos of the job site and existing conditions.

Answer: Not available

23. Is this project tax exempt?

24. Is abatement (asbestos/lead) part of the base bid scope, or will it be performed under a separate contract?

Answer: ACM and LBP abatement are part of this base bid scope. Refer to Section 01 11 00 – 1, “Summary of Work,” and solicitation attachments 6, 7 and 8 for details

25. Please confirm if the abatement contractor will be provided by the Government or is to be subcontracted by the general contractor.

26. Are temporary protection and air monitoring during abatement to be included by the prime or the abatement contractor?

27. Please confirm whether the HVAC control system is intended to operate as a standalone

VRF controls package (local to the building and equipment), or if it is required to integrate with a third-party Building Management System (BMS) such as JCI, Niagara, Trane, etc. If integration is required, please clarify who is responsible for furnishing and implementing the BMS front-end.

Answer: Standalone system but with the BACNet MSTP interface furnished to interface to a future BMS.

28. Please provide the contact information for the building controls contractor.

Answer: Not available.

29. Please confirm if the fire alarm system is to be fully replaced or modified. If modified, please identify the existing system manufacturer and model.

Answer: New system to be installed under this contract.

30. Are low voltage systems (AV, fire alarm, security) to be installed in conduit or is cable tray/MC cable acceptable?

Answer: Installed in conduit.

31. Are test and balance (TAB) services to be included in the base bid or provided by the

Government?

Answer: TAB is part of the base bid and part of this contract.

32. Are extended warranties for VRF compressors (e.g., 5-year manufacturer) to be included in the base bid?

Answer: Refer to specification 23 80 00 - 2, part 1.06 “Warranty” for warranty period.

33. What are the expected design loads for the helical piles?

Answer: Structural design loads are shown on S001 and S003. Soil reports “Geotechnical Report.pdf” and “Gaston Motel Shear Wave Survey Report.pdf” were included in the solicitation attachments 4 and 5.

34. Is there a bid depth for the helical piles?

Answer: A bid depth was not specified but estimate 35 feet for a basis of design.

35. Are utility tap fees, meter fees, or impact fees the responsibility of the contractor or the Government?

Answer: All fees are the responsibility of the contractor and should be included in this contract.

36. What is the existing thickness of the slab?

Answer: Refer to solicitation attachment 4 for details.

37. Is an SWPPP required?

Answer: Contractor will determine requirements and methods of SWPPP and provide as a Division 1 submittal.

38. Is silt fencing required? If so will wood framing suffice?

Answer: Contractor will determine requirements and methods of SWPPP and provide as a Division 1 submittal.

39. Per note 1 on A211 - please define area for concrete repair (for bidding purposes) due to

1963 bomb blast damage.

Answer: Drawing A211, shows, for reference, the extent of damage and subsequent repairs made in 1963. This contract has no concrete repairs in the basement.

40. What is the thickness of the existing damaged concrete wall?

Answer: See drawing A311, detail 6 for basement wall sections.

41. How far beneath level 1 does this damage extend? Does the entire basement wall on the damaged side need to be replaced?

42. Are there any waterproofing additives to the concrete (such as Xypex) necessary at basement wall repair?

43. Can we shut down 5th avenue to traffic for utility work and roadway patching?

Answer: Coordinate with the City of Birmingham on these requirements.

44. Are we responsible for replacing the dumpster pad, apron, walls, and gates?

Answer: If you damage these during construction then yes you will be responsible to repair or replace.

45. Please provide details for the dumpster concrete to be replaced.

46. Is there any permitting required for road work on 5th Ave?

Answer: Coordinate with the City of Birmingham on these requirements.

47. We are concerned the proposed elevator pit excavation may compromise the adjacent exterior wall footing. Please confirm if underpinning is required or if details will be provided. Additionally, our helical pile equipment (minimum unit: MT-100) requires a 50” minimum clear opening. Please confirm sufficient access will be available at the elevator pit location.

Answer: Drawing S101 shows underpinning with helical piles at elevator pit. This is Contractor Means & Methods question, but we assume the equipment may need to be reconfigured or disassembled/reassembled to utilize existing openings.

48. Is there a specific geotechnical engineer of record that must review or approve helical pile submittals and load test results?

Answer: The Engineer of Record will review submittals under Title III services.

49. What is the allowable total settlement and differential settlement criteria for the elevator foundation or helical piles?

50. Are there any restrictions on working hours or noise due to the historic nature of the building or proximity to public access areas?

Answer: Work outside of normal working times must be pre-approved by CO. Activities that generate higher than normal noise levels will be addressed on a case by case basis.

51. Is an architectural conservator required for any components of historic fabric demolition or protection?

Answer: Yes, on a case by case basis.

52. Will existing historic finishes or features removed during demolition need to be salvaged and reinstalled Answer: Yes, on a case by case basis.

53. Please confirm whether a jobsite trailer is required for this project. If so, are there specific location, size, or utility connection constraints the Government would like the contractor to consider?

Answer: This contract will provide a jobsite trailer with utilities for the exclusive use of the Gov’t CMR for the entire construction period of performance. The CMR trailer will have one office, small conference room and restroom. Any other jobsite trailers are at the discretion of the contractor.

54. Is there a designated lay down or staging area for materials and equipment?

Answer: Refer to drawing C100 for staging areas.

55. Is on-site parking available for workers and subcontractors? If limited, are permits required or will alternate parking need to be arranged by the contractor?

Answer: Alternate parking may be required under this contract and will be arranged by the contractor.

56. Are there site access restrictions or daily security check-in requirements?

Answer: Will be determined after award.

57. Please confirm if building commissioning is required. If so, what systems are included, and who is the commissioning agent (CxA)?

Answer: Total building commissioning will be required for all systems. The CxA agent will be determined after award but will most likely be from NPS and the A/E with support from the contractor. See specification 22 05 93 and 01 91 14.

58. Is attic stock (spare parts, filters, paint, etc.) required, and if so, what quantities or types?

Answer: No but will require a list of recommended items to be stocked as spare parts.

59. Will any NPS cultural resource monitor or historic preservation officer be required to oversee work at specific phases (e.g., demolition, restoration)?

Answer: The NPS CMR will monitor all phases of work and will involve others as required.

60. Can any of the On Site Key Personnel have dual roles? (Ex. QC/Safety, Site

Super/Safety) Answer: The job site superintendent role must be a dedicated individual and separate from the on-site safety and quality control roles. The SSHO and QC manager can be one individual.

61. Is there currently an A/E firm under contract for this project?

Answer: Yes, the Engineer of Record is under a Title III services contract.

62. Is this project tax exempt?

63. Will NPS extend the date offers due to give contractors sufficient time to fully review all contract documents and RFIs?

Answer: Yes, to July 16, 2025.

64. Can you confirm if there is a Total Building Commissioning Requirement on this project?

Answer: Total building commissioning will be required for all systems. The CxA agent will be determined after award but will most likely be from NPS and the A/E with support from the contractor. See specification 22 05 93 and 01 91 14.

65. Has this project been fully funded?

Answer: Yes

66. After review of the specs for the security alarm and surveillance cameras specifics. It doesn’t seem to list any recommended manufacturers. Are there any specific manufacturers that we are to use on these items?

Answer: Acquisition guidelines prevent Brand Name (Or Equal) and require salient characteristics instead.

67. Will we have the ability to use the back gate that has keypad access?

Answer: The back gate is owned by the City and requires coordination. NPS will investigate this option after award but the City may not allow use.

68. Typically on federal projects there are no permitting or inspection requirements from local authorities. Can you confirm if that is this case as well on this project?

Answer: The AHJ is the Federal Government but connections to City Utilities will require City permits, fees and inspections which is the responsibility of the contractor.

69. Elevator Pit Excavation and Access: Please confirm whether additional underpinning is required at the corner of the building where the elevator pit excavation may compromise the existing footing on the external wall. Is there any structural detail or guidance available for shoring or underpinning in this area?

Answer: Drawing S101 shows underpinning with helical piles at elevator pit.

70. Can the design team clarify the access requirements and allowances for the elevator pit work area? Specifically, will we be permitted to create a minimum 50” wide opening to allow equipment access (e.g., an MT-100 for driving helical piles)?

Answer: This is Contractor Means & Methods question, but we assume the equipment may need to be reconfigured or disassembled/reassembled to utilize existing openings.

71. Clarification on Glazing Scope: Could you please confirm the full extent of the glazing scope for this project? Based on our review, it appears that the only glass work indicated is:

One window referenced on Sheet X102, Note 6, and shown in Detail 3 on Sheet

A411, and Potential interior door lites.

Answer: Bidder needs to confirm full scope of work.

72. Are there any additional glazing elements or window replacements included in the scope that we may have missed?

Answer: Bidder needs to confirm full scope of work.

73. Please confirm whether a Machine Room-Less (MRL) traction elevator is required for this two-stop system. Based on industry recommendations and the short travel distance, we understand that MRL traction elevators often involve proprietary components, which limit service options and increase long-term maintenance costs. Would a traditional non-proprietary hydraulic elevator be an acceptable alternative for this application? A hydraulic system would be more practical, cost-effective, and easier to maintain over the life of the elevator for a two-stop configuration.

Answer: We will not entertain substitutions during the solicitation phase. Price as currently shown in the solicitation.

74. Will the Birmingham local hire ordinance be in effect for this project?

Answer: No, this ordinance is for City funded projects.

75. The specification mentions "The reports “Report of Subsurface Exploratory and Preliminary Geotechnical Engineering Evaluation,” March 31, 2023, prepared by NOVA is available. The report “Report of In-Situ Shear Wave Study,” March 14, 2024, prepared by NOVA. Is it possible to obtain copies of these reports.

Answer: Documents were included in the solicitation attachments 4 and 5.

76. At the site visit I believe the DSC personnel made mention that ALL of the abatement work had been completed on this project. Can you confirm if ALL abatement work has actually been completed?

77. On sheet A201 there is Note 2 to patch and repair hole in brick wall. Where does this occur. I don’t see note 2 on the sheet.

Answer: Note 2 is contained on A201, detail 1 Elevation – North.

78. Also, on A201 Note 3 calls for the removal of the duct (louver) and patch hole in wall.

There are also places in the Lobby / Reception area that calls for new brick to match existing. Both of these areas would require new brick to match existing. The existing brick is a Roman size and is no longer available. Please provide a manufacturer that can and is willing to make this brick to match the existing?

Answer: Will be determined during material submittal phase.

79. Can a utility brick sawn to the correct height and stained to match the existing as closely as possible? Is this an acceptable repair if no brick can be found to match the existing?

Answer: Will be determined during material submittal phase.

80. Solicitation, Section H states that the On-Site Quality Control Manager and the On-Site Safety Manager may be filled by the same qualified individual. May the Superintendent also serve the Quality Control and Safety roles, or must the Superintendent be a separate individual?

Answer: The job site superintendent role must be a dedicated individual and separate from the on-site safety and quality control roles.

81. I was looking through the specs for the A.G. Gaston Motel for the security alarm and surveillance cameras and can't find any specifics. Are there any specific manufacturers that we are to use on these items?

Answer: The security equipment is not part of this contract but will be supplied and installed by the Park/Regional security staff. This contract only furnishes and installs the infrastructure (raceways, conduit, wire, network cables) to support the owner supplied equipment. The security drawings in the SC set are diagrammatic and only show a typical security system architecture with typical connectivity requirements so that our contractor knows where to install raceways and cables.

82. During the pre-bid site visit, some general questions were raised about ACM and LBP abatement previously performed by the City of Birmingham.an a utility brick sawn to the correct height and stained to match the existing as closely as possible? Is this an acceptable repair if no brick can be found to match the existing?

Answer: NPS does not have documentation of this work, but our understanding is that much of the ACM and LBP was removed prior to NPS acquiring ownership of the facility. During design, NPS and our final design A/E conducted a pre-renovation ACM and LBP assessment, which identified some remaining materials that will require abatement under this contract. Refer to Section 01 11 00 – 1, “Summary of Work,” and Section 01 11 00 – 4, “Additional Reports,” Part B for details