This document is the Request for Proposals (RFP) Program of Requirements and Scope of Work for the GRSA 315541 - Rehabilitate Employee Housing federal contract opportunity.

The RFP outlines the detailed requirements and scope of work for rehabilitating employee housing units for the Department of the Interior National Park Service National Office. The key objectives are to repair and upgrade the housing units to meet current safety and habitability standards. This includes tasks such as roof replacements, interior renovations, HVAC system upgrades, and landscaping improvements. The total project is estimated at $7.5 million. Responses to the RFP are due by August 15, 2023, with a contract award planned for October 1, 2023. The contract will be set aside for small businesses. Additional details on pricing, site visits, and required proposal content are provided in the RFP attachments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Great Sand Dunes National Park and Preserve, Colorado

SOLICITATION GRSA 315541

Rehabilitate Park Housing

100% Draft Report

Design-Build Request for Proposal & Program of Requirements

NATIONAL PARK SERVICE (NPS)

DENVER SERVICE CENTER (DSC)

June 21, 2024

Great Sand Dunes National Park & Preserve Rehabilitate Park Housing ii

1. Project Introduction

1.1 Scope

1.2 Project Description

1.3 Schedule

1.4 Location

1.5 NPS Contact Information

2. Project Requirements

2.1 Scope of Work and Project Summary/Requirements

2.2 Definition of Contract Line Items

2.3 Project Enhancements

2.4 Temporary Housing Requirements

2.5 Requirements for Tenant Packout and Storage

2.6 Areas Available for Contractor Use

2.7 Progress Payments

2.8 NPS Project Management and Communication Software

2.9 Project Meetings

2.10 Project Schedule

2.11 Schedule of Values

2.12 Design Requirements

2.13 Environmental and Sustainability Requirements

2.14 Waste Management Requirements and Goals

2.15 Construction Submittals

2.16 Accident Prevention

2.17 Quality Control

2.18 Construction Support

2.19 Construction Coordination

2.20 Digital Images

2.21 Working Hour Restrictions

2.22 Temporary Services

2.23 Access

2.24 Preservation of Adjacent Features

2.25 Interruption to Existing Utilities

2.26 Hauling Restrictions

2.27 Temporary Controls

2.28 Field Engineering

2.29 Project Close-out

2.30 Final Inspection, Beneficial Occupancy & Final Acceptance

2.31 Warranty

3. Performance Requirements

3.1 Design Imperatives

3.2 Sustainability

3.3 Integrated Design Principles

3.4 Building Rehabilitation Requirements by Unit

3.5 Site Work Performance Requirements

3.6 Elements and Products

iii

4. Technical Requirements

5. Supplementary Information

5.1 Civil

5.2 Architecture

5.3 Furniture Plan (Enhancement)

5.4 Mechanical and Plumbing

5.5 Electrical

5.6 Fire Prevention and Life Safety

Appendix A – Conceptual Site Plan Appendix B – Unit Floor Plans Appendix C – Contract Price Schedule Appendix D – Water Chemistry Analysis Appendix E – Energy Use and Load Estimates Appendix F – Fire Flow (Hydrant) Test Appendix G – Soils Investigation Appendix H – Hazardous Materials Assessment Appendix I – GRSA Representative Photos Appendix J – NPS Universal Design Checklist Appendix K – Permit Assessment Form Appendix L – HUD Housing Quality Standards Appendix M – Rodent Proof Construction

Figures

Figure 1: Area Map Figure 2: Temporary Housing Geographical Limits Figure 3: Map, Areas Allowed for Contractor Use Figure 4 : Typical Perimeter Wall Section Figure 5: Typical Perimeter Wall/Fence Section Figure 6: Flood Analysis Results Figure 8: Site Map

Tables

Table 1: Temporary Housing Requirements by Unit Table 2: Perimeter Retaining Wall Sizing Table 3: Septic Tank Sizing Table 4: Floorplans iv

List of Acronyms and Abbreviations ABA Architectural Barriers Act ABAAS Architectural Barriers Act Accessibility Standards ADA Americans with Disabilities Act AE Architect-Engineer AMP Ampere APP Accident Prevention Plan ASTM American Society for Testing and Materials BIM Building Information Modeling CAD Computer-Aided Design CCT Correlated Color Temperature CD Construction Document CFC Chlorofluorocarbon cfm cubic feet per minute CLIN Contract Line Item Number CMR Construction Management Representative CO Contracting Officer COR Contracting Officer’s Representative CPM Critical Path Method CRI Color Rendering Index CQC Construction Quality Control CS Contracting Specialist DB Design-Build DD Design Development DO Directors Order DSC Denver Service Center DWV Domestic Waste and Vent EIFS Exterior Insulation and Finish System EISA Energy Independence and Security Act EPDM Ethylene Propylene Diene Monomer EV Electric Vehicle FAR Federal Acquisition Regulation gal Gallon GFCI Ground-Fault Circuit Interrupter GRSA Great Sand Dunes National Park and Preserve (also Park) GSA General Services Administration GSF Gross Square Footage HDPE High-Density Polyethylene HUD Housing and Urban Development HVAC Heating, Ventilation, and Air Conditioning IAQ Indoor Air Quality ICC International Code Council LED light-emitting diode v

LEED Leadership in Energy and Environmental Design NBS National Bureau of Standards NEC National Electrical Code NFPA National Fire Protection Association NPDES National Pollutant Discharge Elimination System NPS National Park Service O&M Operations and Maintenance OSB oriented-strand board OSHA Occupational Safety and Health Administration PDF Portable Document Format PEX Cross-Linked Polyethylene PM Project Manager PS Project Specialist psig Per Square Inch Gauge POR Program of Requirements PVC Poly-vinyl Chloride QA Quality Assurance QC Quality Control QCP Quality Control Plan RFI Request for Information RFP Request for Proposal RM Reference Manual ROW Right-of-way RV Recreational Vehicle SD Schematic Design SF square foot/feet SMACNA Sheet Metal and Air Conditioning Contractor’s National Association STC Sound Transmission Class SWPPP Storm Water Pollution Prevention Plan THP Temporary Housing Plan TIA Time Impact Analysis UFAS Uniform Federal Accessibility Standards UL Underwriters Laboratory VRF Variable Refrigerant Flow WMP Waste Management Plan

AECOM 1

1. Project Introduction Park Acronym/PMIS Number: GRSA 315541

Project Title: Rehabilitate Park Housing, Great Sand Dunes National Park and Preserve (GRSA)

Project Drawings Number: To be provided by National Park Service (NPS) after contract award

1.1 Scope

In accordance with terms and conditions of the Contract, the Design-Build (DB) Contractor shall perform the work of this Request for Proposal & Program of Requirements (RFP/POR) for the NPS as described below.

All Architect-Engineer (AE) services required for this contract shall be executed under the responsible control of licensed Architects and Engineers registered in Colorado. All work of the task order shall be performed in accordance with 2024 International Code Council (ICC) building codes, and 2023 National Fire Protection Association (NFPA) 70 (National Electric Code) and accepted industry standards. All design and construction work of this contract will be performed in accordance with requirements and criteria specified on the NPS Denver Service Center (DSC) DB Workflows website:

• https://www.nps.gov/dscw/index.htm

• Work performed shall comply with applicable laws, regulations, and NPS policies and guidelines found at: https://www.nps.gov/dscw/laws-policies.htm

• DB design requirements are located at: https://www.nps.gov/dscw/designbuild.htm

• Division 1 Specifications Templates, which provide standard NPS construction requirements and which the AE may need to use in the creation of the construction specifications, are located at: https://www.nps.gov/dscw/publicforms.htm#div1

• Design Standards are arranged by discipline and/or specialty:

https://www.nps.gov/dscw/dstandards.htm

• All design deliverables must meet the technical content and submission format requirements set forth at: https://www.nps.gov/dscw/del_designbuild.htm

• NPS Quality Assurance (QA) reviews will be performed on every design submission. An overview of the DSC QA process for reviewing design documents is provided at:

https://www.nps.gov/dscw/qaguideline.htm

In case of conflict between this contract and the DSC DB Workflows website, this contract shall take precedence and shall be used in lieu of conflicting portions.

The AE remains fully responsible for determining if the standards or provisions cited on the DSC DB Workflows website have been revised or updated. Any such conflicts between the website and the identified standard or provisions shall be brought to the attention of the Contracting Officer (CO).

1.2 Project Description

The Great Sand Dunes National Park and Preserve (referred to herein as GRSA or Park) housing supports mission-critical park operations year-round by housing essential staff for park https://www.nps.gov/dscw/index.htm https://www.nps.gov/dscw/laws-policies.htm https://www.nps.gov/dscw/designbuild.htm https://www.nps.gov/dscw/publicforms.htm#div1 https://www.nps.gov/dscw/dstandards.htm https://www.nps.gov/dscw/del_designbuild.htm https://www.nps.gov/dscw/qaguideline.htm

AECOM 2

services. The park-based employee housing units are critical infrastructure to support the operation and function of the park.

This project shall address deferred maintenance to nine existing housing units built in the 1960s through 2000s.

The project includes but is not limited to substructure, shell, interior, services, equipment, and site work, for each unit. ABAAS compliance is required for one unit which shall be converted into an ABA duplex to meet NPS accessibility requirements.

The scope of work for each unit is outlined in Building Rehabilitation Requirements by Unit.

Furthermore, Technical Requirements specifies baseline product performance minimums for the project.

The contractor is required to submit a plan for Temporary Housing Requirements as well as Requirements for Tenant Packout and Storage.

This project shall employ integrated design principles using a collaborative design process. The rehabilitated units shall be designed and constructed to meet or exceed all applicable codes and Federal sustainability requirements.

The DB contractor is to bid competitively based on required base bid contract line items, bid options, as well as National Park Services suggested and/or contractor proposed project enhancements as outlined in the Definition of Contract Line Items.

1.3 Schedule

The DB Contractor is expected to complete full design for hazardous materials, abatement, demolition, site, architecture, mechanical, electrical, plumbing and utilities and complete all construction according to the contract period of performance.

1.3.1 DB Design Development (DD) Documents

DB Contractor shall submit DB Design Development Documents no later than 60 days after contract award. NPS shall complete review and provide comments no later than 21 days after receipt of DB Design Development Documents.

1.3.2 100% Draft DB Construction Documents (CD) Not later than 30 days after receiving DB Design Development review comments from NPS, address and incorporate comments into the 100% Draft DB Construction Documents. NPS completes review and provides comments no later than 15 days after receipt of the 100% Draft DB Construction Documents.

1.3.3 100% Complete DB Construction Documents (CD) Not later than 30 days after receiving 100% Draft DB Construction Documents review comments from NPS, DB Contractor shall address and incorporate comments into the 100% Complete DB Construction Documents. NPS shall complete review and provide comments no later than 15 days after receipt.

AECOM 3

1.3.4 Final Stamped/Signed DB Construction Documents (CD)

Not later than 21 days after receiving NPS review comments, DB Contractor shall submit final stamped/signed DB Construction Documents with responses to NPS review of 100% Complete DB Construction Documents.

1.3.5 Construction

Construction begins when the Contracting Officer issues Construction Notice to Proceed. DB Contractor shall complete construction and design no later than 24-months (730 days) after receiving design Notice to Proceed.

1.3.6 As-Constructed Drawings

Provide as-constructed drawings not later than 60 days after construction completion.

AECOM 4

1.4 Location

This project is in Southern Colorado at Great Sand Dunes National Park and Preserve. The site is within the park’s housing area in and around on Piñon Circle. The project is in an active housing area for employees and their families that will be occupied by residents for the duration of the project.

Figure 1: Area Map

AECOM 5

1.5 NPS Contact Information

1.5.1 Contractual

Contracting Officer (CO): Jim Waller, 720-701-0223, jameswaller@nps.gov

Contract Specialist (CS): Brian Baugh, 865-560-6125, brianbaugh@contractor.nps.gov

1.5.2 Technical

Project Specialist (PS) and primary Contracting Officer’s Representative (COR): David Longtin, 303-619-3620, David_longtin@nps.gov

Project Manager (PM) and Alternate COR:

Doug Denk, 303-513-4562, doug_denk@nps.gov

AECOM 6

2. Project Requirements

2.1 Scope of Work and Project Summary/Requirements

The NPS Denver Service Center will use a Program of Requirements (POR) method of delivery.

This POR includes minimum project requirements for two distinct project elements: (1) DB design and construction for the rehabilitation of the existing residential buildings and associated site work and features, and (2) DB provision of a temporary housing plan and/or all necessary DB Contractor-provided temporary housing accommodations for displaced tenants and their families. This POR specifies minimum project requirements for items such as cladding, insulation, Architectural Barriers Act (ABA) accessibility, interior finishes, fire protection systems, electrical, mechanical, plumbing, and other requirements as provided herein. This POR also provides a list of project enhancements which the DB Contractor may provide in addition to the base scope and bid options as a way to provide additional value to the Government.

The project consists of the rehabilitation of nine (9) buildings comprising 13 units ranging from studios to 3-bedroom, 2 bath homes to serve the park’s needs for staff recruitment and address programmatic and floorplan deficiencies. An ABAAS analysis determined it was best to convert unit 10 into two separate ABA duplex units to meet NPS accessibility requirements.

The scope will include, but not be limited to:

• Design for unit rehabilitation including but not limited to substructure, shell, interiors, services (plumbing, mechanical, electrical, lighting) site, equipment, and furnishings work

• Implement principles of universal design

• Unit 10 shall be an ABA compliant duplex and adhere to NPS accessibility requirements

• Perform topographical survey as required for installation of site walls.

• Provide and maintain a construction schedule

• Create a plan for tenant pack-out and storage

• Mandatory coordination with supplemental archaeological monitor and park staff

• Implement the Temporary Housing Plan including provision of any/all DB Contractor provided temporary housing accommodations

• Obtain necessary permits

• Abate, mitigate, or encapsulate all hazardous material found during construction

• Create signed and stamped construction drawings and provide as-constructed drawings

2.2 Definition of Contract Line Items

This section explains in general, what is and is not included in a Contract Line Item Number (CLIN), and the limits or cut-off points where one item ends and another begins. If no contract line item exists for a portion of work, include costs in a related item. Refer to section 3.4, Building Rehabilitation Requirements by Unit for project requirements for each unit.

All DB Contractor bids shall be submitted on Attachment C, Contract Price Schedule.

2.2.1 Base Bid Items

Base bid items shall be considered a required scope of work for the DB contractor to perform.

AECOM 7

Design Tasks CONTRACT LINE ITEM 0101 – DESIGN: Design Development. Provide Design Development drawings for all base bid construction items.

CONTRACT LINE ITEM 0102 – DESIGN: 100% Draft Construction Documents. Provide 100% Draft Construction Documents for all base bid construction items.

CONTRACT LINE ITEM 0103 – DESIGN: 100% Complete Construction Documents. Provide 100% Complete Construction Documents for all base bid construction items.

CONTRACT LINE ITEM 0104 – DESIGN: Final Construction Documents. Provide Final Construction Documents for all base bid construction items.

CONTRACT LINE ITEM 0105 – DESIGN: Design Phase Supplemental Services. Provide supplemental services to project design.

Temporary Housing CONTRACT LINE ITEM 0201 – CONSTRUCT: Provide temporary housing as described within for displaced tenants. This CLIN includes the development, submittal and ongoing revision, as necessary, of the Contractor’s Temporary Housing Plan as specified herein.

Site Work CONTRACT LINE ITEM 0301 – CONSTRUCT: Complete construction for civil site work and utilities not directly related to housing units. The following items are included, but not limited to, culvert cleanout and restoration, site drainage work, and erosion control.

Unit #6 CONTRACT LINE ITEM 0601 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #6 for one 3BR/2BA home of approximately 1,500 SF. Refer to Appendix B for floor plan.

Unit #7 CONTRACT LINE ITEM 0701 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #7 for one 3BR/2BA home of approximately 1,500 SF. Refer to Appendix B for floor plan.

Unit #8 CONTRACT LINE ITEM 0801 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #8 for one 3BR/3BA home of approximately 1,500 SF. Refer to Appendix B for floor plan.

Unit #9 CONTRACT LINE ITEM 0901 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #9 for one 3BR/3BA home of approximately 1,500 SF. Refer to Appendix B for floor plan.

AECOM 8

Unit #10 CONTRACT LINE ITEM 1001 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #10 for ABA duplex home of approximately 1,500 SF. Refer to Appendix B for floor plan.

Unit #14 CONTRACT LINE ITEM 1401 – CONSTRUCT: Partial demolition and construction on Unit #14 for rehabilitation of two 1BR/1BA residential units and one 1BA studio residential unit of approximately 1,600 SF with separate shared laundry room. Refer to Appendix B for floor plan.

Unit #45 CONTRACT LINE ITEM 4501 – CONSTRUCT: Partial demolition and construction on Unit #45 for rehabilitation of two 2BR/2BA duplex units of approximately 1,900 SF. Refer to Appendix B for floor plan.

2.2.2 Bid Options

The DB Contractor shall provide a bid to Denver Service Center and National Park Service for the scope of work requested as a bid option. The work will require approval in order to be performed.

Unit #8 (2x1 bedroom duplex + studio) CONTRACT LINE ITEM 0802 – DESIGN: Design for rehabilitation of residential Unit #8 for one 2 duplex + 1 studio of approximately 1,500 GSF. Refer to Appendix B for floor plan.

CONTRACT LINE ITEM 0803 –CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #8 for one 2 duplex + 1 studio of approximately 1,500 GSF.

Refer to Appendix B for floor plan.

Unit #9 (2x1 bedroom duplex + studio) CONTRACT LINE ITEM 0902 – DESIGN: Design for rehabilitation of residential Unit #9 for one 2 duplex + 1 studio of approximately 1,500 GSF. Refer to Appendix B for floor plan.

CONTRACT LINE ITEM 0903 –CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #9 for one 2 duplex + 1 studio of approximately 1,500 GSF.

Refer to Appendix B for floor plan.

Unit #11 (3 Bedroom, 2 Bath)

CONTRACT LINE ITEM 1101 – DESIGN: Design for rehabilitation of residential Unit #11 for one 3 bedroom, 2 bathroom home of approximately 1,500 GSF. Refer to Appendix B for floor plan.

CONTRACT LINE ITEM 1102 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #11 for one 3 bedroom, 2 bathroom home of approximately 1,500 GSF. Refer to Appendix B for floor plan.

Unit #43 (2 Bedroom, 2 Bath Duplex)

CONTRACT LINE ITEM 4301 – DESIGN: Design for rehabilitation of residential Unit #43 for one 2 bedroom, 2 bathroom duplex of approximately 1,900 GSF. Refer to Appendix B for floor plan.

AECOM 9

CONTRACT LINE ITEM 4302 – CONSTRUCT: Partial demolition and construction for rehabilitation of residential Unit #43 for one 2 bedroom, 2 bathroom duplex of approximately 1,500 GSF. Refer to Appendix B for floor plan.

Unit #45A Water Damage Rehabilitation CONTRACT LINE ITEM 4502 – DESIGN: Design for repair of water damage in duplex housing unit of approximately 1,900 GSF.

CONTRACT LINE ITEM 4503 –CONSTRUCT: Partial demolition and construction for repair of water damage in duplex housing unit of approximately 1,900 GSF. Further description is provided in Section 3.4.A

Metal panel siding to stucco

CONTRACT LINE ITEM 0102 – DESIGN: Design for removal of all metal siding for replacement to stucco at Units 6, 7, 8, 9, 10, and 14. Any sheathing replaced as part of this modification shall have adequate capacity to satisfy lateral demands on housing units per all applicable building codes.

CONTRACT LINE ITEM 0103 – CONTSTRUCT: Demolition of all metal siding and replacement with stucco at Units 6, 7, 8, 9, 10, and 14.

EIFS siding to stucco

CONTRACT LINE ITEM 0104 – DESIGN: Design for removal of all EIFS siding for replacement to stucco at Units 43 and 45. Any sheathing replaced as part of this modification shall have adequate capacity to satisfy lateral demands on housing units per all applicable building codes.

CONTRACT LINE ITEM 0105 – CONTSTRUCT: Demolition of all EIFS siding and replacement with stucco at Units 43 and 45.

2.3 Project Enhancements

The DB Contractor shall not be required to provide bids on any Project Enhancements.

However, for the benefit of the government, the DB Contractor may choose to demonstrate additional value by proposing scope enhancements and/or higher quality products than the minimum standards require. In proposing a Project Enhancement, the DB Contractor shall specify the type, quantity, unit cost, and line-item total cost on the Contract Price Schedule and may attach a brief summary of technical details. The determination of cost-benefit for any proposed Project Enhancement shall be at the sole discretion of the Contracting Officer.

CONTRACT LINE ITEM 9100 – Personal Storage Provide options for personal storage units in lieu of communal storage space.

CONTRACT LINE ITEM 9200 – Interior Sound Attenuation Provide sound attenuation greater than 45 in interior wall partitions in the duplex and triplex units 8, 9, 10, 14 A/B/C.

CONTRACT LINE ITEM 9300 – Concrete Patios Provide concrete patios behind housing units. (Additional Project Enhancements shall be numbered sequentially CLIN 9600, 9700, 9800, etc.)

AECOM 10

CONTRACT LINE ITEM 9400 – Furniture Plan Provide new furniture for housing units. See Appendix B for furniture list.

CONTRACT LINE ITEM 9500 – Project Enhancement Item #5 This consists of proposed additions by the DB Contractor for the benefit of the government.

(Additional Project Enhancements shall be numbered sequentially CLIN 9600, 9700, 9800, etc.)

2.4 Temporary Housing Requirements

The Contractor is required to provide temporary housing as specified herein for all housing occupants displaced by the construction activities of this project. The Contractor is also required to provide all moving and storage services as specified herein for the moving of displaced residents’ household goods and property. The Contractor is not permitted to perform any construction work on occupied buildings (inclusive of multi-unit buildings), with the exception of certain civil site work and septic system work if approved in advance by the Contracting Officer.

Certain existing housing units which are part of this project will be available for use as temporary housing space at certain times as specified herein. In addition, the Contractor is permitted to provide additional temporary housing space via either temporary on-site facilities or off-site facilities, or both. All Contractor provided temporary housing space, either on-site or off-site shall comply with all requirements specified herein.

The Contractor is required to develop a Temporary Housing Plan for NPS review and approval as part of the design phase of this project. The Temporary Housing Plan shall clearly define all temporary housing space to be utilized, shall demonstrate that all temporary housing space meets the contract requirements, and shall provide a detailed schedule and sequencing plan for the moving of all displaced residents into and out of the permanent and temporary housing spaces.

The DB contractor shall construct this project in a manner that minimizes disruption to the park's residents who are temporarily displaced during construction.

The following table shows occupancy by unit to aid the DB contractor in developing a temporary housing plan and schedule.

Table 1: Temporary Housing Requirements by Unit

Unit

Bedrooms

Bathrooms

Required Occupant*

Temporary Housing Period Occupied**

Required Temporary Housing Arrangement

6 3 2 YES Year-round 2-bedroom family unit required

7 3 2 Year-round 2-bedroom family unit required

8 3 1 YES April 1 – October 31 Three 1-bedroom units required

OR

3-bedroom 1 bath unit similar to existing

9 3 1 April 1 – October 31 Three 1-bedroom units required

OR

AECOM 11

3-bedroom 1 bath unit similar to existing

3 1 N/A none

11 3 2 Year-round 2-bedroom family unit required

14A 1 1 Year-round 1-bedroom unit required

14B 1 1 April 1 – October 31 1-bedroom unit required

14C 1 1 April 1 – October 31 1-bedroom unit required

43A 2 2 YES Year-round 2-bedroom family unit required

43B 2 2 Year-round 2-bedroom family unit required

45A

2 2 N/A none

45B 2 2 Year-round 2-bedroom family unit required

*See Temporary Housing Occupancy Requirements section 2.4.1

** This is the date range during which the contractor will have to provide for temporary housing for each unit. For example, any time Unit 7 is under construction, the contractor will have to provide a 2-bedroom family temporary housing unit. If Unit 9 is under construction during the date range shown, the contractor will have to provide three 1-bedroom apartments or a 3-bedroom 1 bath unit similar to existing. If Unit 9 is under construction outside of the date range shown, the Contractor is not required to provide any temporary housing for that unit. No temporary housing is required for Units 10 or 45A since NPS will not assign any tenants to those units during the construction performance period of this contract.

***NPS will not assign any tenants to Unit 10 or Unit 45A during the construction performance period of this project.

2.4.1 Temporary Housing Occupancy Requirements

The Contractor’s Temporary Housing Plan must provide for the required temporary housing arrangements for the required temporary housing periods as indicated in the table above based upon the Contractor’s construction schedule and sequencing. Temporary housing is only required for occupants displaced by construction.

Temporary Housing for Required Occupants (NPS staff such as first responders) must be provided either on-site or within the Temporary Housing Boundary for Required Occupants as depicted in Figure 2: Temporary Housing Geographical Limits.

The Contractor’s Temporary Housing Plan must accommodate two (2) Required Occupants on a year-round basis, each in a 2-bedroom family unit. These required occupants are currently assigned Units 6 and 43A as represented in the above table under Required Occupant.

AECOM 12

The Contractor’s Temporary Housing Plan must accommodate three (3) additional Required Occupants from April 1 to October 31. These seasonal Required Occupants can be in 1-bedroom units or collectively in Units 8 or 9. These occupants are currently housed in Unit 8.

Temporary Housing for Permitted Occupants (NPS staff who are not first responders) must be provided either on-site or within the Temporary Housing Boundary for Permitted Occupants as depicted as depicted geographically in Figure 2.

2.4.2 NPS Owned Temporary Housing Space for Contractor Use

NPS will not assign any tenants to Unit 10 or Unit 45A during the construction performance period of this project, and both of those units will be available for Contractor use as temporary housing space at all times during the construction performance period of this project, at the Contractor’s discretion.

The Contractor may utilize Unit 45A as temporary housing only after rehabilitation of that unit is complete per the requirements of this contract.

The Contractor may utilize Unit 10 as temporary housing either prior to its rehabilitation per the requirements of this contract, after its rehabilitation, or both, at the Contractor’s discretion. Prior to its rehabilitation, Unit 10 can only be occupied by members of the same family or by individuals of the same gender.

The Contractor is also permitted to utilize Units 8, 9, 14B and 14C as temporary housing space during their unoccupied period of November 1 – March 31, but these units must be available for normal occupancy during their occupied period of April 1 – October 31.

For any NPS owned unit utilized by the Contractor as temporary housing space, the Contractor is responsible for performing a full deep clean of the unit after the last temporary occupant has moved out.

2.4.3 NPS Tenant and Rental Policies

NPS will provide tenants with a rental agreement.

The contractor shall not charge tenants rent for temporary housing.

2.4.4 Contractor Provided Temporary Housing Requirements:

2.4.4.1 On-site temporary housing:

Location: The acceptable locations for contractor provided temporary housing are listed in Figure 3 and are numbered as 1. RV Area, 2. Old Road to Corral, 3. Future Road to Additional Housing. See section 2.5 for a detailed description of these areas. Refer to Appendix N for NPS provided utility plans.

Disassembly, Removal and Site Restoration: The Contractor is responsible for removing all temporary buildings from the site and restoring the site to prevent erosion. Temporary utility lines shall be properly stubbed and capped.

2.4.4.2 Off-site temporary housing:

Location: Refer to Figure 2, Temporary Housing Geographical Limits.

AECOM 13

2.4.5 Requirements Common to All Contractor Provided Temporary Housing:

2.4.5.1 Implementation

The D-B Contractor is required to provide safe and acceptable-quality accommodations to GRSA residents who are displaced during the construction project.

When the D- Contractor has identified a temporary housing unit, they will schedule an inspection with the Owner’s Construction Management Representative (CMR). The Contractor and CMR will walk through the unit together, and the CMR will evaluate the acceptability of the unit based on the acceptability requirements listed below. The Contracting Officer (CO) or designated representative will make the final determination of whether a unit is acceptable, based on this report. The CO may waive certain criteria if it is in the best interest of the Government. The Contractor may not move displaced tenants into a housing unit prior to written approval of the CO. A separate inspection of a housing unit and a subsequent CO approval will be required each time the Contractor wishes to move a new tenant into a unit.

The D-B Contractor is responsible for maintaining the temporary housing units so that they continue to satisfy the acceptability criteria for the duration of the occupation. Written correction requests will be submitted to the CO, who will immediately notify the Contractor. Any correction must be completed in a reasonable time frame, as determined by the CO, based on the severity of the condition, the time needed to acquire materials and other considerations.

These same criteria, approval requirements and maintenance requirements apply to all temporary housing units, whether they are rental units (apartments, single-family homes, etc.), Contractor-owned facilities, located on or off GRSA property or other temporary housing arrangements.

The Contractor will be responsible for covering all costs associated with the temporary housing not included in the bulleted list below. Examples of costs the Contractor are responsible for include but are not limited to rent, water, wastewater and garbage collection.

Temp housing costs the Contractor is not responsible for:

• Electricity

• Gas

• Telecommunications (phone, Wi-Fi, etc.)

• Cable TV or streaming services.

2.4.5.2 Performance Requirements and Acceptability Criteria

This section includes 13 performance criteria which define whether a temporary housing unit is acceptable.

The contractor shall provide temporary housing that is of a quality in accordance with the U.S.

Department of Housing and Urban Development (HUD) Housing Quality Standards. HUD Housing Quality Standards includes but is not limited to the following performance requirements:

• Sanitary facilities;

• Food preparation and refuse disposal;

• Space and security;

AECOM 14

• Thermal environment;

• Illumination and electricity;

• Structure and materials;

• Interior air quality;

• Water supply;

• Lead-based paint;

• Access;

• Site and neighborhood;

• Sanitary condition; and

• Smoke Detectors

See Appendix M, HUD Housing Quality Standards, for housing requirements which include but are not limited to performance requirements as well as the following acceptability criteria which have been added to or modified in some instances by National Park Services.

1. Sanitary Facilities: The dwelling unit must include sanitary facilities within the unit. The sanitary facilities must be in proper operating condition and adequate for personal cleanliness and disposal of human waste. The sanitary facilities must be usable in privacy.

The number of bathrooms must equal or exceed the number listed in Table 2.

Acceptability Criteria:

• The bathroom must be located in a separate room and have a flush toilet in proper operating condition.

• The unit must have a fixed basin (lavatory) with a sink trap and hot and cold running water in proper operating condition.

• The unit must have a shower or tub with hot and cold running water in proper operating condition.

• The facilities must utilize an approved public or private disposal system, including a locally approved septic system.

2. Food Preparation and Refuse Disposal: The dwelling unit must have suitable space and equipment to store, prepare, and serve food in a sanitary manner.

Acceptability Criteria:

• The dwelling unit must have an oven, a stove or range and a microwave oven.

• The dwelling unit must have a refrigerator of appropriate size for the family.

• All required equipment must be in proper operating condition.

• The dwelling unit must have a kitchen sink in proper operating condition, with a sink trap and hot and cold running water. The sink must drain into an approved public or private system.

• The dwelling unit must have space for storage, preparation, and serving of food.

• Facilities and services for the sanitary disposal of food waste and refuse, including temporary storage facilities (i.e., a trash can), are required.

3. Space and Security: The dwelling unit must provide adequate space and security for the family.

Acceptability Criteria:

• At a minimum, the dwelling unit must have a living room and a kitchen.

• Housing arrangements that require multiple bedrooms as specified in Table 2 shall have shared living spaces.

AECOM 15

• The number of bedrooms must equal or exceed the number listed in Table 2.

• Dwelling unit windows that are accessible from the outside must be lockable.

• Exterior doors to the unit must be lockable.

4. Thermal Environment: The dwelling unit must be able to provide a thermal environment that is healthy for the human body.

Acceptability Criteria:

• There must be a safe system for heating the dwelling unit, such as electric baseboard, radiator, or forced air systems. In order to ensure a healthy living environment appropriate for the climate the system must be able to provide adequate heat either directly or indirectly to each room.

• The heating and/or air conditioning system must be in proper operating condition.

• The dwelling unit must not contain unvented room heaters that burn gas, oil, or kerosene.

• Electric heaters are acceptable.

• A “healthy living environment” means that the unit must be able to maintain a temperature range of 68 to 78 degrees, regardless of outside air temperature.

5. Illumination and Electricity: Each room must have adequate natural or artificial illumination to permit normal indoor activities and to support the health and safety of occupants. The dwelling unit must have sufficient electrical sources so occupants can use essential electrical appliances. Electrical fixtures and wiring must not pose a fire hazard.

Acceptability Criteria:

• There must be at least one window in both the living room and each sleeping room.

• The kitchen area and the bathroom must have a permanent ceiling or wall-mounted fixture in proper operating condition.

• The kitchen must have at least one electrical outlet in proper operating condition.

• The living room and each sleeping space must have at least two electrical outlets in proper operating condition.

6. Structure and Materials: The dwelling unit must be structurally sound. The structure must not present any threat to the health and safety of the occupants and must protect the occupants from the environment.

Acceptability Criteria:

• Ceilings, walls, and floors must not have any serious defects such as severe bulging or leaning, large holes, loose surface materials, severe buckling, missing parts, or other serious damage.

• The roof must be structurally sound and weather-proof.

• The foundation and exterior wall structure and surface must not have any serious defects such as serious leaning, buckling, sagging, large holes, or defects that may result in air infiltration or vermin infestation.

• The condition and equipment of interior and exterior stairs, halls, porches, and walkways must not present the danger of tripping and falling.

• Elevators must be working safely.

7. Interior Air Quality: The dwelling unit must be free of air pollutant levels that threaten the health of the occupants.

AECOM 16

Acceptability Criteria:

• The dwelling unit must be free from dangerous air pollution levels from carbon monoxide, sewer gas, fuel gas, dust, and other harmful pollutants.

• There must be adequate air circulation in the dwelling unit.

• Bathroom areas must have one openable window or other adequate ventilation.

• Any sleeping room must have at least one window. If the window was designed to be opened, it must be in proper working order.

• All windows relied upon for ventilation must be equipped with an insect screen in working order.

8. Water Supply: The water supply must be free of contamination.

Acceptability Criteria:

• The dwelling unit must be served by an approved public or private water supply that is sanitary and free from contamination.

9. Lead-Based Paint: The Lead-Based Paint Poisoning Prevention Act as amended (42 U.S.C. 4821 - 4846) and the Residential Lead-Based Paint Hazard Reduction Act of 1992 and implementing regulations 24 CFR Part 35 Subparts A, B, M, and R apply to these temporary housing criteria.

Acceptability Criteria:

• The requirements apply to dwelling units built prior to 1978 that are occupied or can be occupied by families with children under six years of age, excluding zero-bedroom dwellings.

• During initial and annual inspections of pre-1978 units that are occupied or will be occupied by families with children under 6 years of age, a Contractor-provided inspector must conduct a visual assessment for deteriorated paint surfaces, and provide a certified report on the inspection findings. The Contractor must stabilize deteriorated surfaces in accordance with the findings of the report. Applicable areas include painted surfaces within the dwelling unit, exterior painted surfaces associated with the dwelling unit, and common areas of the building through which residents must pass to gain access to the unit and areas frequented by resident children under six years of age, including play areas.

10. Access: Use and maintenance of the unit must be possible without unauthorized use of other private properties. The building must provide an alternate means of exit in case of fire.

The building must have safe vehicular access and adequate dedicated vehicle parking spaces (minimum one parking space per bedroom).

Acceptability Criteria:

• The unit must have private access to the interior of the dwelling unit.

• The building and parking spaces must be accessible by standard two-wheel-drive, low clearance passenger car on properly maintained roadways and driveways.

• In case of fire, the building must contain an alternate means of exit such as fire stairs, or windows, including use of a ladder for windows above the second floor.

11. Site and Neighborhood: The site and neighborhood must be reasonably free from disturbing noises and reverberations or other dangers to the health, safety, and general welfare of the occupants.

AECOM 17

Acceptability Criteria:

• The site and neighborhood may not be subject to serious adverse natural or manmade environmental conditions, such as dangerous walks or steps, instability, flooding, poor drainage, septic tank back-ups or sewer hazards, mudslides, excessive snow or ice build-up, abnormal air pollution, smoke or dust, excessive noise, vibration, or vehicular traffic, excessive accumulations of trash, vermin, or rodent infestation, or fire hazards.

12. Sanitary Condition: The dwelling unit and its equipment must be in sanitary condition.

Acceptability Criteria:

• The dwelling unit and its equipment must be free of vermin and rodent infestation.

13. Smoke Detectors: On each level of the dwelling unit including basements but excluding spaces and unfinished attics at least one battery-operated or hard-wired smoke detector in proper operating condition must be present. Smoke detectors must be installed in accordance with and meet the requirements of the National Fire Protection Association Standards (NFPA) 74 or its successor standards.

Acceptability Criteria:

• The Contractor must certify that the location of smoke detectors conforms with local and/or State Fire Marshall’s requirements, that smoke detectors are located and installed in accordance with NFPA Standards, and that all smoke detectors must be in operating condition.

In addition to the above Housing Quality Standards, the following are temporary housing requirements of NPS:

1. Telecommunications: The unit shall have at least one service connection to a commercial internet service provider in working order suitable for use by the tenants, at their discretion, to purchase commercial internet services.

a. Acceptability Criteria - the unit has at least one service connection to a commercial internet service provider in working order.

2. Furnishings: Temporary housing shall have furnished accommodations equipped with amenities that are comparable to current tenant provisions in the units such as bed, storage, living and dining area seating, and basic kitchen appliances for meal preparations such as microwave, stove, sink, refrigerator, and freezer.

3. Management and Maintenance:

a. Responsibilities: The contractor shall be responsible for managing the temporary housing facilities, including maintenance, cleaning, and security arrangements. Any necessary repairs or maintenance work shall be promptly addressed to uphold living standards.

b. Supervision: Designated personnel shall oversee the day-to-day operations of the housing facilities, ensuring compliance with safety regulations and addressing any concerns raised by occupants promptly.

c. Communication: Clear communication channels shall be established to facilitate feedback and address any issues or complaints regarding the housing facilities.

Regular inspections and feedback sessions may be conducted to assess satisfaction levels and make necessary improvements.

Project Duration and Handover:

AECOM 18

1. Duration: The temporary housing facilities shall be available for the duration of the construction project, with provisions for extension if required due to unforeseen circumstances or project delays.

Handover Procedure: Upon completion of the project, the contractor shall ensure the orderly vacating of the housing facilities and return them to their original condition. Any damages or discrepancies shall be documented and rectified before the handover process.

AECOM 19

Figure 2: Temporary Housing Geographical Limits

AECOM 20

2.5 Requirements for Tenant Packout and Storage

As part of the scope of work, the Contractor shall provide a moving plan to NPS to pack, move, store, and unpack tenant personal belongings and NPS furniture before and after unit renovation. The moving plan must include but is not limited to:

1. Notification and Scheduling:

a. The tenant shall be informed of the upcoming remodel and therefore the need to schedule the professional pack out of personal items 10 days before the move date and 5 days before the unpacking date.

b. The packing and unpacking of tenant items shall be limited to the hours of 8 a.m. to 6 p.m. with the tenant present.

2. Documentation and Inventory:

a. A detailed inventory shall be created for all items being moved.

b. Photographs shall be taken of items to document their pre-move condition.

3. Packing:

a. Materials: Use industry standard packing materials such as bubble wrap, packing tape, moving blankets, sturdy boxes, and labeling materials.

b. Labeling: Clearly label all boxes with the tenant’s name, the contents, and handling instructions for fragile items.

4. Moving Items:

a. Careful Handling: Items are to be handled with care to avoid damage.

b. Transportation: Items shall be safely transported to the designated storage area, whether on site or off site.

5. Storage:

a. Separately contained storage shall be provided to each tenant. Multiple tenants or household belongings shall not be grouped together in a storage unit.

b. Ensure the tenant can access their items, if needed, during the renovation period.

c. On-Site Storage: If storing items on site, ensure the storage area is secure, dry, and free from hazards (e.g., water damage, pests).

d. Off-Site Storage: If using an off-site storage facility, choose a reputable provider with secure, climate-controlled units.

The Contractor is responsible for any damages incurred during the moving and storage process.

Unit renovations shall not occur until the tenant is fully packed out of the unit. Tenants may move back to the unit after the renovation is completed and their personal belongings are delivered and unpacked.

AECOM 21

2.6 Areas Available for Contractor Use

Figure 3: Map, Areas Allowed for Contractor Use

AECOM 22

Project Duration and Handover:

The map in Figure 3 represents NPS approved areas available for contractor use. The following are descriptions of each area represented numerically in the map.

1. RV area: This small RV site is located at the heart of the park’s residential, maintenance and administrative area. There are four RV pads, each measuring approximately 15’ wide by 40’ long, and each of them has access to water, sewer and power. Two of the spaces will be made available to the contractor free of charge. A third site will cost approximately $415 per month, and can be used for contractor housing, if desired. The fourth site will be reserved for park use. Any trailer used for housing is limited to 25’ in length, maximum.

There will be no charge for utilities. The site is surrounded by trees that must not be damaged by contractor activities; also, grading and excavation are prohibited. The site may be useful as a “local” staging area for smaller items or to locate a job or CMR trailer, due to its proximity to the project and the availability of utilities.

1. Old road to corral: This area is located on an old roadbed serving the corrals. The old roadbed itself is fairly level, but the terrain on either side of it is sloped and is covered with trees. Tree removal is not allowed in this contractor use area. The road would have to be re-graded for contractor use and topsoiled by the contractor at the end of the project. There is a drainage swale at the northern end of the road, where it joins the in-use road to the corrals. The contractor would be required to properly pass the drainage under the road if they desire through traffic. The approximate length of this road is 525 feet. The site has access to a 6-in water main that could be tapped to supply potable water. An underground electric line also runs adjacent to the site and could be used for temporary power. The park reserves the right to have the contractor remove temporary utility extensions, culverts, or other temporary improvements at the contractor’s expense after the project is finished. The site could be made useful as a staging area or for locating a job office or CMR trailer, but it would have to be serviced by a portable toilet due to the lack of wastewater service. There would be no fee for the use of this area.

2. Future road to additional housing: This area is just beyond the paved road serving Unit

45. The area is somewhat steep and is covered with trees. Tree removal is allowed along this alignment, but the development plan must be approved by the Contracting Officer prior to ground disturbance or tree removal. The area may have to be re-graded and topsoiled at the contractor’s expense after contractor use, at the park’s discretion. The approximate length of this road is 500 feet. The site has good access to a 6-in water main that could be tapped to supply potable water. An underground electric line also runs adjacent to the road and could be used for temporary power. The park reserves the right to have the contractor re-grade and topsoil the road, and/or to remove temp utility extensions at their own expense after the project is finished. The site could be made useful as a staging area or for locating a job office or CMR trailer. The site could also be used to accommodate one or more mobile housing units for temporary staff housing if a septic system meeting all applicable regulations is installed. The park would consider allowing the contractor to leave the site grading and utility improvements in place if they are beneficial to the park. There would be no fee for the use of this area.

3. No. 4 – Maintenance boneyard: A gravel road extending south of the park’s Maintenance facility leads to a storage “boneyard.” The park has agreed to provide an area measuring 60’ x 40’ for contractor use. The area is ready for use; grading or tree removal are not needed and in fact are not allowed. There is no electricity or water at this site. This area is appropriate for use as a staging area. It is not appropriate for use as a CMR trailer or for temporary housing. There would be no fee for the use of this area.

AECOM 23

Construction Camp Establishment of a camp for housing…