This document is a Statement of Structural Tests and Special Inspections for the MORU 272051 WWTP Solicitation being conducted by the Department of the Interior National Park Service National Office. The statement identifies various structural tests and inspections required for the construction project, including inspections for steel construction, welding, bolting, concrete work, masonry, wood framing, soils, driven pile foundations, cast-in-place foundations, fabricated items, fire resistance, smoke control, and mass timber sealing. It provides details on required qualifications for inspectors, identifies specific inspection and testing requirements, and notes frequency of periodic inspections. Completion of all required inspections and addressing of any deficiencies discovered are obligations of the construction contractor under the contract.

View the file

Other files

File Type Posted
Amendment_08_Questions_and_Answers_0008.pdf PDF
Sol_140P2023R0125_Amd_0008.pdf PDF
Addendum_Items_20230828_0008.pdf PDF
Addendum_Items_20230828_-_Attachment_00-D004_0008.pdf PDF
Addendum_20230905_0008.pdf PDF
Attachment_00-D004_0007.pdf PDF
Addendum_Items_0007.pdf PDF
Sol_140P2023R0125_Amd_0007.pdf PDF
Questions_and_Answers_for_Solicitation_140P2023R0125_0007.pdf PDF
MORU_CD_Volume_4_0006.pdf PDF
MORU_CD_Volume_1_0006.pdf PDF
MORU_CD_Volume_3_0006.pdf PDF
MORU_CD_Volume_2_0006.pdf PDF
Sol_140P2023R0125_Amd_0006.pdf PDF
MORU_Prebid_Sign_in_Sheet_0006.pdf PDF
Sol_140P2023R0125_Amd_0005.pdf PDF
Amendment_05_Attachment_5_VOLUME_3__South_Bldg__COMPLETE_0005.pdf PDF
Amendment_04_Attachment_12a_Fillable_B08_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD_0004.xlsx XLSX spreadsheet
Amendment_04_Attachment_2a_Specification_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_2_-_6-12-23_0004.pdf PDF
Amendment_04_Attachment_13_Wage_Detemination_0004.pdf PDF
Amendment_04_Attachment_12_Fillable_-_ContractPriceSchedule_23_6_13_CD_0004.xlsx XLSX spreadsheet
Amendment_04_Attachment_4_VOLUME_2__North_Bldg__COMPLETE_0004.pdf PDF
Amendment_04_Attachment_2_Specification_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_1_-_6-12-23_Rev1_0004.pdf PDF
Amendment_04_Attachment_9_Closeout-OperationMaintenance-Requirements_0004.pdf PDF
Amendment_04_Attachment_5_VOLUME_3__South_Bldg__COMPLETE_0004.pdf PDF
Amendment_04_Attachment_10_Bid_Bond__VOL-1-24-16e_0004.pdf PDF
Amendment_04_Attachment_6_VOLUME_4__Series_04-09__COMPLETE_0004.pdf PDF
Amendment_04_Attachment_11_PSP_VOL_1_0004.pdf PDF
Amendment_04_Attachment_8_Geotechnical_Report_0004.pdf PDF
Amendment_04_Attachment_1_SF-1442_and_Clauses_0004.pdf PDF
Amendment_04_Attachment_3_VOLUME_1_Series_00-01__General__Civil_0004.pdf PDF
Amendment_04_Attachment_11a_PSP_VOL_2_0004.pdf PDF
Sol_140P2023R0125_Amd_0004.pdf PDF
Amendment_03_MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_1_-_6-12-23_Rev1_0003.pdf PDF
MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_1_-_6-12-23_Rev1_0003.pdf PDF
MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_2_-_6-12-23_0003.pdf PDF
Amendment_03_MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_2_-_6-12-23_0003.pdf PDF
Sol_140P2023R0125_Amd_0003.pdf PDF
Sol_140P2023R0125_Amd_0002.pdf PDF
Amendment_02_MORU_MAP_0002.pdf PDF
Amendment_02_MORU_WWTP_PREBID_INSTRUCTIONS_0002.pdf PDF
Sol_140P2023R0125_Amd_0001.pdf PDF
B08__WWTP_SOLICITATION_140P2023R0125_7_24_23_0001.pdf PDF
Attachment_2_VOLUME_1_Series_00-01__General__Civil.pdf PDF
Attachment_7_MORUGeotechnical_Report.pdf PDF
Attachment_6_STATEMENT_OF_STRUCTURAL_TESTS_AND_SPECIAL_INSPECTIONS.pdf PDF
Attachment_9a_Bid_Bond__VOL-1-24-16e.pdf PDF
Attachment_3_VOLUME_2__North_Bldg__COMPLETE.pdf PDF
Sol_140P2023R0125.pdf PDF
Attachment_10a_Fillable_-_ContractPriceSchedule_23_6_13_CD.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MORU - 272051 01 45 33B - 1

STATEMENT OF STRUCTURAL TESTS AND SPECIAL INSPECTIONS

Statement of Structural Tests and Special Inspections National Park Service (NPS) - Denver Service Center (DSC) | 6-29-21

For each test marked required, specify the qualifications of inspector. For each test marked periodic, specify the frequency.

Park: Mount Rushmore National Memorial

Project Management Information System (PMIS) Number: 272051

Project Name: Rehab & Expand WWTP

Structural Engineering Firm: HDR, Inc.

This Statement of Structural Tests and Special Inspections is being submitted as required by Chapter 17 of the

2021 International Building Code (IBC-21). It includes the following:

1. Seismic requirements

2. Wind requirements

3. Qualification Requirements for Inspectors and Testing Technicians

4. Listing of Required Structural Tests and Special Inspections

The Construction Contractor’s Quality Control Supervisor will provide copies of all special inspection reports and associated documentation to the Contracting Officer (CO). The Construction Contractor will be required to correct all deficiencies discovered in the Special Inspection and Structural Testing program.

Prepared By: Svein Magnussen (Type or print name)

Signature: ____________________________________________________ Date: 6-13-2023

Stamped by Professional Engineer (PE) or Structural Engineer (SE)

MORU - 272051 01 45 33B - 2

Seismic and Wind Requirements

Seismic Requirements, IBC-21 Section 1704.3

Description of seismic-force-resisting system and designated seismic systems subject to special inspections:

The seismic-force-resisting system for this project varies by building. The North and South building have plywood sheathing on the roof that acts as a diaphragm. The diaphragm shear is transferred to the walls using shear straps. At the North Building, the shear walls are Light-frame (wood) walls sheathed with wood structural panels rated for shear resistance. At the South Building, the shear walls are masonry reinforced shear walls. The Aeration Basin and Clarifier have ordinary reinforced concrete shear walls and are buried mostly beneath grade.

Special Inspections for the wood seismic-force-resisting systems is not required per IBC 1705.13.2 as the structures are in seismic design category B.

Special Inspections for the concrete seismic-force-resisting system is not required per IBC 1705.13.2 as the design spectral response acceleration at short periods, SDS, is less than 0.5.

Wind Requirements, IBC-21 Section 1704.3

Description of wind-force-resisting system and designated wind systems subject to special inspections:

MORU - 272051 01 45 33B - 3

The wind-force-resisting system for this project varies by building. The North and South building have plywood sheathing on the roof that acts as a diaphragm. The diaphragm shear is transferred to the walls using shear straps. At the North Building, the shear walls are Light-frame (wood) walls sheathed with wood structural panels rated for shear resistance. At the South Building, the shear walls are reinforced masonry walls. The Aeration Basin and Clarifier have ordinary reinforced concrete shear walls and are buried mostly beneath grade.

Special Inspections for the wood wind-force-resisting systems is not required per IBC 1705.12.1 as the project is in Exposure B and the wind speed is less than 150 miles per hour.

Instructions:

1. Under Listing of Required Structural Tests and Special Inspections:

a. Required? - Place an X for all Special Inspections and Tests required for this project.

b. Required Qualifications - Provide qualifications for the special inspector, using the

Qualification Requirements for Inspector and Testing Technicians list below, for all required Structural Tests and Special Inspections.

c. Continuous - If marked with an X, continuous special inspection shall be as defined in Chapter

2, IBC-21.

d. Periodic - If marked with an X, provide the minimum number of tests, i.e. 20% of all field welds, or the amount of work to be inspected (e.g. 10% of all wall surfaces).

2. Attach completed Statement of Structural Tests and Special Inspections to the end of NPS DSC Division 1 Specifications Section 01 40 00 Quality Requirements.

Qualification Requirements for Inspectors and Testing Technicians

PE/SE Structural Engineer – licensed PE or SE specializing in the design of buildings and structures

PE/GE Geotechnical Engineer – licensed PE specializing in soil mechanics and foundations

EIT Engineer-In-Training – graduate engineer who has passed the Fundamentals of engineering examination

American Concrete Institute (ACI) Certification

ACI-CCSI Concrete Construction Special Inspector

ACI-LTT Concrete Laboratory Testing Technician Level 1 or 2

ACI-STT Concrete Strength Testing Technician

MORU - 272051 01 45 33B - 4

ACI-FTT Concrete Field Testing Technician – Grade I

American Society of Non-Destructive Testing (ASNT) Certification

Non-Destructive Testing Technician – Level II or III

American Welding Society (AWS) Certification

AWS-CWI Certified Welding Inspector

Exterior Design Institute (EDI) Certification

EDI-EIFS Certified EIFS inspector

International Code Council (ICC) Certification

ICC-PCSI Prestressed Concrete Special Inspector

ICC-RCSI Reinforced Concrete Special Inspector

ICC-SSI Soils Special Inspector

ICC-SFSI Spray-applied Fireproofing Special Inspector

ICC-SMSI Structural Masonry Special Inspector

ICC-SSBSI Structural Steel and Bolting Special Inspector

ICC-SWSI Structural Welding Special Inspector

National Institute for Certification in Engineering Technologies (NICET) Certification

NICET-CT Concrete Technician – Levels I, II, III and IV

NICET-GET Geotechnical Engineering Technician - Levels I, II, III and IV

NICET-ST Soils Technician - Levels I, II, III and IV

Other

MORU - 272051 01 45 33B - 5

MORU - 272051 01 45 33B - 6

Listing of Required Structural Tests and Special Inspections R e q u ir e d

Structural Test or Special Inspection Required

Qualifications

C o n ti n u o u s

P e ri o d ic Frequency of

Periodic Test or Inspection

Steel Construction (IBC-21 Section 1705.2; American Institute of Steel Construction: AISC 360-16 Chapter N, AISC 341- 16 Chapter J)

Prior to Welding (AISC 360-16 Table N5.4-1)

1. Welder qualification records and continuity records

X

2. Welding procedure specifications (WPS) available

3. Manufacturer certifications for welding consumables available

4. Material identification (type/grade) X

5. Welder identification system X

6. Fit-up of groove welds (including joint geometry)

a. Joint preparation X

b. Dimensions (alignment, root opening, root face, bevel)

c. Cleanliness (condition of steel surfaces) X

d. Tacking (tack weld quality and location) X

e. Backing type and fit (if applicable) X

7. Fit-up of CJP (complete joist penetration) groove welds of HSS (hollow structural sections) T-, Y- and K-joints without backing (including joint geometry)

a. Joint preparation

b. Dimensions (alignment, root opening, root face, bevel)

c. Cleanliness (condition of steel surfaces)

MORU - 272051 01 45 33B - 7

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test or Inspection

d. Tacking (tack weld quality and location)

8. Configuration and finish of access holes X

9. Fit-up of fillet welds

a. Dimensions (alignment, gaps at root) X

b. Cleanliness (condition of steel surfaces) X

c. Tacking (tack weld quality and location) X

10. Check welding equipment X

During Welding (AISC 360-16 Table N5.4-2)

1. Control and handling of welding consumables

a. Packaging X

b. Exposure control X

2. No welding over cracked tack welds X

3. Environmental conditions

a. Wind speed within limits X

b. Precipitation and temperature X

4. WPS followed

a. Settings on welding equipment X

b. Travel speed X

c. Selected welding materials X

d. Shielding gas type/flow rate X

e. Preheat applied X

f. Interpass temperature maintained

(minimum/maximum)

MORU - 272051 01 45 33B - 8

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test

g. Proper position (F, V, H, OH) X

h. Intermix of filler metals avoided unless approved (reference: AISC 341-10 Table J6.2)

5. Use of qualified welders X

6. Welding techniques

a. Interpass and final cleaning X

b. Each pass within profile limitations X

c. Each pass meets quality requirements X

7. Placement and installation of headed stud anchors

After Welding (AISC 360-16 Table N5.4-3)

1. Welds cleaned X

2. Size, length and location of welds X

3. Welds meet visual acceptance criteria

a. Crack prohibition X

b. Weld/base-metal fusion X

c. Crater cross section X

d. Weld profiles X

e. Weld size X

f. Undercut X

g. Porosity X

4. Arc strikes X

5. k-area X

MORU - 272051 01 45 33B - 9

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

6. Weld access holes in rolled heavy shapes and built-up heavy shapes

7. Backing removed and weld tabs removed (if required)

8. Repair activities X

9. Document acceptance or rejection of welded joint or member

10. No prohibited welds have been added without the approval of the EOR (Engineer of Record)

11. Placement of reinforcing or contouring fillet welds (if required) (reference: AISC 341-16)

Nondestructive Testing (AISC 360-16 Section N5 and AISC 341-16 Section J6)

1. Risk Category II Structures - Perform Ultrasonic Testing on 10% of CJP groove welds in butt, T-and corner joints subject to transversely applied tension loading, in materials 5/16 inch thick or greater.

2. Risk Category III or IV Structures - Perform Ultrasonic Testing on all CJP groove welds subject to transversely applied tension loading in butt, T- and corner joints, in materials 5/16 inch thick or greater.

3. Access Holes – Perform Magnetic Particle Testing or Liquid Penetrant Testing when the flange thickness exceeds 2 inches for rolled shapes, or when the web thickness exceeds 2 inches for built-up shapes.

4. Welded Joints Subject to Fatigue X

Nondestructive Testing (AISC 341-16 Section J6)

Column Splice and Column to Base Plate PJP Groove Weld (AISC 341-16 Section J6 2b)

1. Perform Ultrasonic Testing on 100% of PJP

(partial-joint-penetration) groove welds in column splices and column to base plate welds

2. CJP Groove weld X

MORU - 272051 01 45 33B - 10

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test or Inspection

3. Lamellar tearing X

4. Beam cope and access hole X

5. Reduced beam section repair X

6. Weld tab removal X

Prior to Bolting (AISC 360-16 Table N5.6-1)

These inspections are not required for snug-tight joints.

1. Manufacturer’s certifications available for fastener materials

2. Fasteners marked in accordance with ASTM requirements

3. Correct fasteners selected for the joint detail

(grade, type, bolt length if threads are to be excluded from shear plane)

4. Correct bolting procedure selected for joint detail

5. Connecting elements, including the appropriate faying surface condition and hole preparation, if specified, meet applicable requirements

6. Pre-installation verification testing by installation personnel observed and documented for fastener assemblies and methods used

7. Protected storage provided for bolts, nuts, washers and other fastener components

During Bolting (AISC 360-16 Table N5.6-2)

These inspections are not required for snug-tight joints.

These inspections are not required for pretensioned joints and slip-critical joints, when the installer is using the turn-of-nut method with matchmarking techniques, the direct-tension-indicator method, or the twist-off-type tension control bolt method.

MORU - 272051 01 45 33B - 11

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

1. Fastener assemblies, of suitable condition, placed in all holes and washers (if required) are positioned as required

2. Joint brought to the snug-tight condition prior to the pretensioning operation

3. Fastener component not turned by the wrench prevented from rotating

4. Fasteners are pretensioned in accordance with the RCSC (Resource Council on Structural Connections) Specification, progressing systematically from the most rigid point toward the free edges

After Bolting (AISC 360-16 Table N5.6-2)

Document acceptance or rejection of bolted connections.

Other Inspection Tasks (AISC 360-16 Section N5.7)

1. Verify compliance of fabricated steel with the details shown on the approved shop drawings.

2. Verify compliance of the erected steel frame with the details shown on the approved erection drawings, including braces, stiffeners, member locations and joint details.

3. Anchor rods and other embedments support structural steel

a. Verify the diameter, grade, type and length of the anchor rod or embedded item.

b. Verify the extent or depth of embedment into the concrete.

4. RBS (reduce beam section) requirements, if applicable (AISC 341-16)

a. Contour and finish X

b. Dimensional tolerances X

5. Protected zone - no holes and unapproved attachments made by fabricator or erector, as applicable. (AISC 341-16)

MORU - 272051 01 45 33B - 12

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

6. H-piles - Protected zone - no holes and unapproved attachments made by the responsible contractor, as applicable. (AISC 341-16)

Cold-formed Steel Deck (IBC-21 1705.2.2)

1. Special inspections in accordance with QA/QC- 2017 Standard for Quality control (QC) and Quality assurance (QA) for Installation of Steel Deck

Open-Web steel Joists and Joist Girders (IBC- 21 Table 1705.2.3)

1. Installation of open-web steel joists and joist girders.

a. End connections - welding or bolted X

b. Bridging - horizontal or diagonal

1. Standard bridging X

2. Bridging that differs from the SJI (Steel

Joist Institute) specifications listed in Section 2207.1.

Inspection of Composite Structures Prior to Concrete Placement (AISC 341-16 Table J9.1)

1. Material identification of reinforcing steel

(Type/Grade)

2. Determination of carbon equivalent for reinforcing steel other than ASTM A706

3. Proper reinforcing steel size, spacing and orientation

4. Reinforcing steel has not been rebent in the field

5. Reinforcing steel has been tied and supported as required

6. Required reinforcing steel clearances have been provided

7. Composite member has required size X

MORU - 272051 01 45 33B - 13

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Inspection of Composite Structures During Concrete Placement (AISC 341-16 Table J9.2)

1. Concrete: Material identification (mix design, compressive strength, maximum large aggregate size, maximum slump)

2. Limits on water added at the truck or pump X

3. Proper placement techniques to limit segregation

Inspection of Composite Structures During Concrete Placement (AISC 341-16 Table J9.2)

1. Achievement of minimum specified concrete compressive

Cold-formed Steel Trusses Spanning 60-feet or Greater (IBC-21 Section 1705.2.4)

1. Verify temporary installation restraint/bracing installed in accordance with the approved shop drawings.

2. Verify permanent individual truss member restraint/bracing installed in accordance with the approved shop drawings.

Concrete Construction (IBC-21 Section 1705.3)

1. Inspect reinforcing steel, including prestressing tendons, and placement.

ACI-CCSI

X Once per Pour

2. Inspection of reinforcing steel welding

a. Verify weldability of reinforcing bars other than ASTM A706.

b. Inspect single pass fillet welds, maximum

5/16 inch.

c. Inspect all other welds. X

X 3. Inspection of anchors cast in concrete. ACI-CCSI X Once per Pour

4. Inspection of anchors post-installed in hardened concrete members.

MORU - 272051 01 45 33B - 14

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test or Inspection

X

a. Adhesive anchors installed in horizontally or upwardly inclined orientations to resist sustained tension load

ACI-CCSI

b. Mechanical anchors and adhesive anchors not defined in 4 a

X 5. Verify use of approved design mix. ACI-CCSI X Once per Pour

6. Prior to placement fabricate specimens for strength tests, perform slump and air content tests, and determine the temperature of the concrete.

7. Inspect concrete and shotcrete placement for proper application techniques.

8. Inspect for maintenance of specified curing temperature and techniques.

ACI-CCSI

X Once per Pour

9. Inspection of prestressed concrete:

a. Application of prestressing forces X

b. Grouting of bonded prestressing tendons in the seismic-force-resisting system.

X 10. Erection of precast structural members X

11. For precast concrete diaphragm connections or reinforcement at joints classified as moderate or high deformability elements (MDE or HDE) in structures assigned to Seismic Design Category C, D, E, or F, inspect such connections and reinforcement in the field for:

a. Installation of the embedded parts X

b. Completion of the continuity of reinforcement across joints

c. Completion of connections in the field X

12. Inspect installation tolerances of precast concrete diaphragm connections for compliance with ACI 550.5 (American Concrete Institute).

13. Verification of in-situ concrete strength, prior to stressing of tendons in post-tensioned concrete

MORU - 272051 01 45 33B - 15

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test or Inspection and prior to removal of shores and forms from beams and structural slabs.

X

14. Inspection formwork for shape, location and dimensions of the concrete member being formed.

ACI-CCSI

X

Once per Pour

Masonry Construction (IBC-21 Section 1705.4)

1. Inspect masonry construction in accordance with IBC-21 Section 1705.4 and TMS 602-13 (The Masonry Society)/ACI 530.1-13 Article 1.6.

ICC-SMSI

Once

Level A Quality Assurance

Tests: None.

Inspection: Verify compliance with the approved submittal and project specifications.

Level B Quality Assurance

Tests:

X

1. Verify slump flow and Visual Stability Index (VSI) as delivered to the project site in accordance with TMS 602-13/ACI 530.1-13 Specification Article 1.5B.1.b.3 for self-consolidating grout.

2. Verify f’m and f’aac in accordance with TMS 602-13/ACI 530.1-13 Specification Article 1.4B prior to construction, except where specifically exempted.

Inspection:

1. Verify compliance with the approved submittals and project specifications.

ICC-SMSI

X Once

2. At the start of masonry construction, verify:

X a. Proportions of site-prepared mortar. ICC-SMSI X Once

X b. Construction of mortar joints. ICC-SMSI X Once

X

c. Grade and size of prestressing tendons and anchorages.

MORU - 272051 01 45 33B - 16

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

d. Location of reinforcement, connectors, prestressing tendons and anchorages.

e. Prestressing technique. X

f. Properties of thin-bed mortar for AAC (autoclaved aerated concrete) masonry.

(Continuous inspection is required for the first 5000 square feet of AAC masonry.

Periodic inspection is required after the first 5000 square feet of AAC masonry.)

X X

3. Prior to grouting, verify:

X a. Grout space is clean. ICC-SMSI X Once

X

b. Grade, type and size of reinforcement and anchor bolts, and prestressing tendons and anchorages.

ICC-SMSI

X

Once

X

c. Placement of reinforcing and connectors, and prestressing tendons and anchorages.

ICC-SMSI

X Once

X

d. Proportions of site-prepared grout and prestressing grout for bonded tendons.

ICC-SMSI

X Once

X e. Construction of mortar joints. ICC-SMSI X Once

4. During masonry construction, verify:

X a. Size and location of structural members. ICC-SMSI X Once

X

b. Type, size and location of anchors, including other details of anchorage of masonry to structural members, frames, or other construction.

ICC-SMSI

X

Once

X c. Welding of reinforcement. ICC-SMSI X

X

d. Preparation, construction and protection of masonry during cold weather (temperature below 40 degrees Fahrenheit) or hot weather (temperature above 90 degrees Fahrenheit).

ICC-SMSI

e. Application and measurement of prestressing force.

MORU - 272051 01 45 33B - 17

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

f. Placement of grout and prestressing grout for bonded tendons is in compliance.

g. Placement of AAC masonry units and construction of thin-bed mortar joints.

(Continuous inspection is required for the first 5000 square feet of AAC masonry.

Periodic inspection is required after the first 5000 square feet of AAC masonry.)

X X

5. Observe preparation of grout specimens, mortar specimens and/or prisms.

ICC-SMSI

X Once

Level C Quality Assurance

Tests:

X

1. Verify f’m and f’aac in accordance with TMS 602-13/ACI 530.1-13/ASCE 6-13 Specification Article 1.4B prior to construction, and for every 5000 square feet during construction.

2. Verify proportions of materials in premixed or pre-blended mortar, prestressing grout, and grout other than self-consolidating grout as delivered to the project site.

3. Verify slump flow and Visual Stability Index (VSI) as delivered to the project site in accordance with TMS 602-13/ACI 530.1- 13/ASCE 6-13 Specification Article 1.5B.1.b.3 for self-consolidating grout.

Inspection:

1. Verify compliance with the approved submittals and project specifications.

ICC-SMSI

X

2. Verify:

a. Proportions of site-prepared mortar, grout and prestressing grout for bonded tendons.

b. Grade, type and size of reinforcement and anchor bolts, and prestressing tendons and anchorages.

c. Placement of masonry units and construction of mortar joints.

ICC-SMSI

MORU - 272051 01 45 33B - 18

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

d. Placement of reinforcement, connectors and prestressing tendons and anchorages.

X e. Grout space prior to grouting. ICC-SMSI X

f. Placement of grout and prestressing grout for bonded tendons.

X g. Size and location of structural elements. ICC-SMSI X Once

h. Type, size and location of anchors, including other details of anchorage of masonry to structural members, frames or other construction.

i. Welding of reinforcement. X

j. Preparation, construction and protection of masonry during cold weather (temperature below 40 degrees Fahrenheit) or hot weather (temperature above 90 degrees Fahrenheit).

ICC-SMSI

k. Application and measurement of prestressing force.

l. Placement of AAC masonry units and construction of thin-bed mortar joints.

m. Properties of thin-bed mortar for AAC masonry.

3. Observe preparation of grout specimens, mortar specimens and/or prisms.

Wood Construction (IBC-21 Section 1705.5)

1. Inspect prefabricated wood structural elements in accordance with Section 1704.2.5.

PE/SE

X Once

2. High load diaphragms:

a. Verify sheathing grade and thickness. X

b. Verify nominal size of framing members at adjoining panel edges.

c. Verify nail or staple diameter and length. X

MORU - 272051 01 45 33B - 19

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test

d. Verify number of fastener lines. X

e. Verify spacing between fasteners in each line and at panel edges.

3. Shearwalls:

X a. Verify sheathing grade and thickness. PE/SE X Once

X

b. Verify nominal size of framing members at adjoining panel edges.

PE/SE

X Once

X c. Verify nail or staple diameter and length. PE/SE X Once

X d. Verify number of fastener lines. PE/SE X Once

X

e. Verify spacing between fasteners in each line and at panel edges.

PE/SE

X

X f. Location and size of holdowns. PE/SE X Once

4. Verify nailing, bolting, anchoring and fastening of:

X a. Drag struts and collectors. PE/SE X Once

X b. Braces. PE/SE X Once

X c. Hold-downs. PE/SE X Once

5. Metal-plate-connected wood trusses spanning

60 feet or greater:

a. Verify temporary installation restraint/bracing installed in accordance with the approved shop drawings.

PE/SE

X

Once

X

b. Verify permanent individual truss member restraint/bracing installed in accordance with the approved shop drawings.

PE/SE

X

Once

Soils (IBC-21 Section 1705.6)

1. Verify materials below shallow foundations are adequate to achieve the required bearing capacity.

NICET-ST

MORU - 272051 01 45 33B - 20

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

Periodic Test or Inspection

X

2. Verify excavations are extended to proper depth and have reached proper material.

NICET-ST

X Once

X

3. Perform classification and testing of compacted fill materials.

NICET-ST

X Once

X

4. During fill placement, verify use of proper materials and procedure in accordance with the provisions of the approved geotechnical report.

Verify densities and lift thicknesses during placement and compaction of compacted fill.

NICET-ST

5. Prior to placement of compacted fill, inspect subgrade and verify that site has been prepared properly.

NICET-ST

X

Once

Driven Deep Foundation Elements (IBC-21 Section 1705.7)

1. Verify element materials, sizes and lengths. X

2. Determine capacities of test elements and conduct additional load tests when required.

Refer to project specifications.

3. Inspect driving operations and maintain complete and accurate records for each element.

4. Verify element locations and plumbness. X

a. Verify type and size of hammer. X

b. Record number of blows per foot of penetration.

c. Determine required penetration to achieve specified capacity.

d. Record pile tip and butt elevations. X

e. Document any damage to any foundation

5. For steel piling, perform additional inspection in accordance with Section 1705.2 and AISC 341- 16, Table J10.1.

MORU - 272051 01 45 33B - 21

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

6. For concrete elements and concrete-filled elements, perform additional inspections in accordance with Section 1705.3.

7. For specialty elements, perform additional inspections as required in the project specifications.

Cast-in-Place Deep Foundation (IBC-21 Section 1705.8)

1. Inspect drilling operations and maintain complete and accurate records for each

2. Verify element locations and plumbness. X

a. Verify element diameter. X

b. Verify bell diameter (if applicable). X

c. Verify element lengths. X

d. Verify embedment depth into bedrock (if applicable).

e. Verify adequate end-bearing strata capacity. X

f. Record concrete or grout volumes. X

3. For concrete elements, perform additional inspections in accordance with Section 1705.3.

Helical Piles (IBC-21 Section 1705.10)

1. Verify pile locations. X

a. Verify installation equipment used. X

b. Verify pile dimensions. X

c. Verify tip elevations. X

d. Verify final depth. X

e. Verify final installation torque. X

MORU - 272051 01 45 33B - 22

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

f. Other data as required by the project specifications.

Fabricated Items (IBC-21 Section 1705.11)

1. Inspect fabricated items in accordance with

Section 1704.2.5.

PE/SE

X Once

Wind Resistance (IBC-21 Section 1705.12)

1. Provide inspections when required by Section

1705.12.

Seismic Resistance (IBC-21 Section 1705.13)

1. Provide inspections when required by Section

1705.13.

Testing and Qualification for Seismic Resistance (IBC-21 Section 1705.14)

1. Test and qualify seismic resistance in accordance with IBC-21 Section 1705.14 and the project specifications.

Sprayed Fire-Resistant Materials (IBC-21 Section 1705.15)

1. Inspect sprayed fire-resistant materials in accordance with IBC-21 Section 1705.15 and the project specifications.

Mastic and Intumescent Fire- Resistant Coatings (IBC-21 Section 1705.16)

1. Perform inspections in accordance with AWCI

12-B (Association of the Wall and Ceiling Industry) and IBC-21 Section 1705.16.

Exterior Insulation and Finish Systems (EIFS) (IBC-21 Section 1705.17)

MORU - 272051 01 45 33B - 23

R e q u ir e

Qualifications

C o n ti n u o ri o d ic Frequency of

1. Perform inspections in accordance with project specifications and IBC-21 Section 1705.17.

Fire-Resistant Penetrations and Joints (IBC-21 Section 1705.18)

1. Perform inspections in accordance with project specifications and IBC-21 Section 1705.18.

Smoke Control (IBC-21 Section 1705.19)

1. Perform testing in accordance with project specifications and IBC-21 Section 1705.19.

Sealing of Mass Timber

(IBC-21 Section 1705.20)

1. Perform testing in accordance with project specifications and IBC-21 Section 1705.20.