Amendment_04_Attachment_6_VOLUME_4__Series_04-09__COMPLETE_0004.pdf

PDF 9 MB Posted

Attached to
MORU 272051 WWTP Solicitation
Solicitation number
140P2023R0125
Issued by

About this file

This solicitation is for wastewater treatment plant upgrades at Mount Rushmore National Memorial in South Dakota. The National Park Service is seeking design and construction services to rehabilitate and expand the existing wastewater treatment plant. Key work includes replacing solids dewatering equipment, upgrading aeration basins and clarifiers, installing new instrumentation and controls, and replacing aging infrastructure. The total project cost is estimated at $9-12 million. The solicitation was issued on June 13, 2023 with proposals due by July 15 and award planned for late 2023. The contract will be a firm-fixed-price design-build contract. The solicitation encourages proposals from small businesses and SDVOSBs.

View the file

Other files

File Type Posted
Amendment_08_Questions_and_Answers_0008.pdf PDF
Sol_140P2023R0125_Amd_0008.pdf PDF
Addendum_Items_20230828_0008.pdf PDF
Addendum_Items_20230828_-_Attachment_00-D004_0008.pdf PDF
Addendum_20230905_0008.pdf PDF
Attachment_00-D004_0007.pdf PDF
Addendum_Items_0007.pdf PDF
Sol_140P2023R0125_Amd_0007.pdf PDF
Questions_and_Answers_for_Solicitation_140P2023R0125_0007.pdf PDF
MORU_CD_Volume_4_0006.pdf PDF
MORU_CD_Volume_1_0006.pdf PDF
MORU_CD_Volume_3_0006.pdf PDF
MORU_CD_Volume_2_0006.pdf PDF
Sol_140P2023R0125_Amd_0006.pdf PDF
MORU_Prebid_Sign_in_Sheet_0006.pdf PDF
Sol_140P2023R0125_Amd_0005.pdf PDF
Amendment_05_Attachment_5_VOLUME_3__South_Bldg__COMPLETE_0005.pdf PDF
Amendment_04_Attachment_12a_Fillable_B08_Solit_PSP_Vol_II_LmtOnSubcontracting_REQD_0004.xlsx XLSX spreadsheet
Amendment_04_Attachment_2a_Specification_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_2_-_6-12-23_0004.pdf PDF
Amendment_04_Attachment_13_Wage_Detemination_0004.pdf PDF
Amendment_04_Attachment_12_Fillable_-_ContractPriceSchedule_23_6_13_CD_0004.xlsx XLSX spreadsheet
Amendment_04_Attachment_4_VOLUME_2__North_Bldg__COMPLETE_0004.pdf PDF
Amendment_04_Attachment_7_STATEMENT_OF_STRUCTURAL_TESTS_AND_SPECIAL_INSPECTIONS_0004.pdf PDF
Amendment_04_Attachment_2_Specification_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_1_-_6-12-23_Rev1_0004.pdf PDF
Amendment_04_Attachment_9_Closeout-OperationMaintenance-Requirements_0004.pdf PDF
Amendment_04_Attachment_5_VOLUME_3__South_Bldg__COMPLETE_0004.pdf PDF
Amendment_04_Attachment_10_Bid_Bond__VOL-1-24-16e_0004.pdf PDF
Amendment_04_Attachment_11_PSP_VOL_1_0004.pdf PDF
Amendment_04_Attachment_8_Geotechnical_Report_0004.pdf PDF
Amendment_04_Attachment_1_SF-1442_and_Clauses_0004.pdf PDF
Amendment_04_Attachment_3_VOLUME_1_Series_00-01__General__Civil_0004.pdf PDF
Amendment_04_Attachment_11a_PSP_VOL_2_0004.pdf PDF
Sol_140P2023R0125_Amd_0004.pdf PDF
Amendment_03_MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_1_-_6-12-23_Rev1_0003.pdf PDF
MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_1_-_6-12-23_Rev1_0003.pdf PDF
MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_2_-_6-12-23_0003.pdf PDF
Amendment_03_MORU_Water_Treatment_Plant_Expansion_Project_Manual_-_Volume_2_-_6-12-23_0003.pdf PDF
Sol_140P2023R0125_Amd_0003.pdf PDF
Sol_140P2023R0125_Amd_0002.pdf PDF
Amendment_02_MORU_MAP_0002.pdf PDF
Amendment_02_MORU_WWTP_PREBID_INSTRUCTIONS_0002.pdf PDF
Sol_140P2023R0125_Amd_0001.pdf PDF
B08__WWTP_SOLICITATION_140P2023R0125_7_24_23_0001.pdf PDF
Attachment_2_VOLUME_1_Series_00-01__General__Civil.pdf PDF
Attachment_7_MORUGeotechnical_Report.pdf PDF
Attachment_6_STATEMENT_OF_STRUCTURAL_TESTS_AND_SPECIAL_INSPECTIONS.pdf PDF
Attachment_9a_Bid_Bond__VOL-1-24-16e.pdf PDF
Attachment_3_VOLUME_2__North_Bldg__COMPLETE.pdf PDF
Sol_140P2023R0125.pdf PDF
Attachment_10a_Fillable_-_ContractPriceSchedule_23_6_13_CD.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OLD

BALDY

MOUNTAIN

TO 385

MOUNT RUSHMORE

SCULPTURES

VISITOR AREA

LEGEND

AMPHITHEATER

WATER RESERVOIR

CONCESSION

BUILDING

ENERGY

CENTER

DORMITORY

INTERPRETIVE

CENTER

MAINTENANCE BUILDING

SCULPTOR'S STUDIO

& RESIDENCE

WASTE WATER

TREATMENT PLANT

WATER PUMPING

& STORAGE AREA

SWITCHBACK

(INACTIVE)

HOUSING

AREA

TO 36

16A

KEYSTONE

TO 16

TO

HAYWARD

THIS PROJECT

MOUNT RUSHMORE NATIONAL MEMORIAL

SCALE OF FEET

400' 0' 800'

100 0 100 200

400'

SCALE OF METERS

WASTEWATER TREATMENT PLANT EXPANSION

MAP LEGEND

PARK BOUNDARY

PAVED ROAD

UNPAVED ROAD

TRAIL

VISITOR CENTER

PARK HEADQUARTERS

PARKING

RESTROOMS

HQ.

V.C.

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

C R e v it L o c a l\ -0

S e ri e s

G e n e ra l_ R ic W e b e r.

rv t

/1

/2

:0 :1

A

M

VOL4

MOUNT RUSHMORE NATIONAL MONUMENT

272051

COVER SHEET VOLUME 4RDW

CLZ / TWM / HHD

06/13/23

RDW

18678704-

FINAL CONSTRUCTION DOCUMENTS

SCHEDULE OF DRAWINGS VOLUME 4

SHEET SUB-SHEET SHEET NAME

177 04-VOL4 COVER SHEET VOLUME 4

178 04-X101 WEST AERATION BASIN (1A/2A) PROCESS DEMOLITION PLANS

179 04-X102 WEST AERATION BASIN (1A/2A) ELECTRICAL DEMOLITION PLAN

180 04-S101 WEST AERATION BASIN (1A/2A) PLAN

181 04-D101 WEST AERATION BASIN (1A/2A) PROCESS PLAN

182 04-E101 WEST AERATION BASIN (1A/2A) POWER AND LIGHTING PLANS

183 05-S101 EAST AERATION BASIN (1B/2B) FOUNDATION PLAN

184 05-S102 EAST AERATION BASIN (1B/2B) UPPER LEVEL FLOOR PLAN

185 05-S301 EAST AERATION BASIN (1B/2B) SECTIONS

186 05-D101 EAST AERATION BASIN (1B/2B) PROCESS PLAN & SECTION

187 05-E101 EAST AERATION BASIN (1B/2B) POWER AND LIGHTING PLAN

188 06-X101 WEST CLARIFIER (#1) ELECTRICAL DEMOLITION PLAN

189 06-D101 WEST CLARIFIER (#1) DEMOLITION & PROCESS PLAN

190 06-E101 WEST CLARIFIER (#1) POWER AND LIGHTING PLAN

191 07-S101 EAST CLARIFIER (#2) FOUNDATION PLAN

192 07-S102 EAST CLARIFIER (#2) UPPER LEVEL FLOOR PLAN

193 07-S301 EAST CLARIFIER (#2) SECTIONS

194 07-D101 EAST CLARIFIER (#2) PROCESS PLAN & SECTIONS

195 07-E101 EAST CLARIFIER (#2) POWER AND LIGHTING PLAN

196 08-X101 WINTER BIOSOLIDS STORAGE DEMOLITION PLAN

197 08-X102 WINTER BIOSOLIDS STORAGE ELECTRICAL PLAN - DEMO

198 08-D101 WINTER BIOSOLIDS STORAGE PROCESS PLAN & SECTIONS

199 08-D501 WINTER BIOSOLIDS STORAGE BUILDING TANK DETAILS

200 08-M101 WINTER BIOSOLIDS STORAGE MECHANICAL PLANS

201 08-E101 WINTER BIOSOLIDS STORAGE POWER AND LIGHTING PLANS

202 08-E102 WINTER BIOSOLIDS LIGHTNING PROTECTION / GROUNDING PLAN

203 08-E601 WINTER BIOSOLIDS ONE-LINE & SCHEDULE

204 08-E602 WINTER BIOSOLIDS MOTOR CONTROL DIAGRAMS

205 09-G001 INSTRUMENTATION P&ID -INSTRUMENTATION LEGEND

206 09-G002 INSTRUMENTATION P&ID -INSTRUMENTATION LEGEND

207 09-Y501 INSTRUMENTATION INSTRUMENT INSTALLATION DETAILS

208 09-Y502 INSTREMENTATION INSTRUMENT INSTALLATION DETAILS

209 09-Y601 INSTRUMENTATION P&ID HEADWORKS

210 09-Y602 INSTRUMENTATION P&ID INFLUENT EQ BASIN & AERATED SLUDGE HOLDING TANK

211 09-Y603 INSTRUMENTATION P&ID - EQUALIZATION BASIN

212 09-Y604 INSTRUMENTATION P&ID - AERATION BASIN 1A / 2A

213 09-Y605 INSTRUMENTATION P&ID - AERATION BASIN 1B / 2B

214 09-Y606 INSTRUMENTATION P&ID - AERATION BLOWERS

215 09-Y607 INSTRUMENTATION P&ID - ARP PUMPS

216 09-Y608 INSTRUMENTATION P&ID - CLARIFIER 1

217 09-Y609 INSTRUMENTATION P&ID - CLARIFIER 2

218 09-Y610 INSTRUMENTATION P&ID - RWAS PUMPS

219 09-Y611 INSTRUMENTATION P&ID - SCUM PIT

220 09-Y612 INSTRUMENTATION P&ID - SAND FILTERS AND REAERATION COLUMN

221 09-Y613 INSTRUMENTATION P&ID - UV TREATMENT AND OUTFALL

222 09-Y614 INSTRUMENTATION P&ID - MICRO-C SYSTEM SHEET 1 OF 2

223 09-Y615 INSTRUMENTATION P&ID - MICRO-C SYSTEM SHEET 2 OF 2

224 09-Y616 INSTRUMENTATION P&ID - CENTRIFUGE FEED PUMPS

225 09-Y617 INSTRUMENTATION P&ID - DEWATERING CENTRIFUGES

226 09-Y618 INSTRUMENTATION P&ID - DEWATERING POLYMER SYSTEM

227 09-Y619 INSTRUMENTATION P&ID - TRUCK LOADOUT

228 09-Y620 INSTRUMENTATION P&ID - FERRIC CHLORIDE SYSTEM

229 09-Y621 INSTRUMENTATION P&ID - SODIUM HYDROXIDE SYSTEM

230 09-Y622 INSTRUMENTATION P&ID - NORTH BUILDING SUMP

231 09-Y623 INSTRUMENTATION P&ID - WINTER SOLIDS BUILDING

232 09-Y624 INSTRUMENTATION P&ID - NORTH BUILDING ALARM SIGNALING SYSTEM

233 09-Y625 INSTRUMENTATION P&ID - SOUTH BUILDING ALARM SIGNALING SYSTEM

234 09-Y626 INSTRUMENTATION P&ID - WINTER SOLIDS BUILDING ALARM SIGNALING SYSTEM

235 09-Y701 INSTRUMENTATION PROCESS CONTROL SYSTEM COMMUNICATIONS DIAGRAM

VOLUME 4

X01

X01

X01

X02

X02

X02

X02 X02

X02

X02

X02

X03

X03

X03 X03

X03

X03 X04

X04 X04

X03 X03

X03 X03

X03 X03

X05 X05

X06

X06

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:3

:1

P

M

X101

MOUNT RUSHMORE NATIONAL MEMORIAL

272051

WEST AERATION BASIN

(1A/2A) PROCESS

DEMOLITION PLANS

CLR

DJG

06/13/23

KSP

18678704-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WEST AERATION BASIN (A1/2A) PROCESS DEMOLITION LOWER PLAN

ASCALE

WEST AERATION BASIN (1A/2A) PROCESS DEMOLITION GRADE PLAN

NOTES:

1. COORDINATE DEMOLITION WITH THE OWNER. THE

TREATMENT SYSTEM SHALL REMAIN IN SERVICE AT

ALL TIMES. REFER TO SECTION 01 31 00 FOR

ADDITIONAL REQUIREMENTS.

2. REMOVE ALL SUPPORTS AND ANCHOR BOLTS.

PATCH THE STRUCTURE AS SPECIFIED IN SECTION

01 73 29.

3. SEE SPECIFICATION SECTION 01 27 00 FOR

DESCRIPTION OF BID OPTIONS.

KEYNOTES

X01 EXCAVATE AND REMOVED BURIED PIPING AND

FITTINGS AND PREPARE REMAINING PIPING FOR NEW

CONNECTION.

X02 REMOVE EXISTING AERATION DIFFUSERS AND

SUBMERGED AERATION PIPING. PREPARE REMAINING

AIR DISTRIBUTION PIPING FOR CONNECTION TO NEW

DIFFUSER SYSTEM.

X03 REMOVE EXISTING MIXERS. PATCH AND PREPARE

AERATION BASIN TO RECIEVE NEW MIXERS.

X04 REMOVE EXISTING WASTEWATER INFLUENT PIPING.

PATCH CONCRETE WALL PENENTRATIONS AND

ANCHOR BOLT LOCATIONS.

X05 RETAIN EXISTING PNEUMATIC AIR FLOW CONTROL

VALVES FOR CONNECTION TO NEW DIFFUSER PIPING.

X06 BID OPTION #2, REHABILITATE DOME COVER AS

SPECIFIED IN SECTION 09 01 91 - REFINISHING

FIBERGLASS DOMES. THE BASE BID EXCLUDES DOME

REHABILITATION WORK.

IC

ICIC

IC

IC IC

IC

ICIC IC IC

IC

IC IC

ICIC

IC IC

IC

IC

IC

IC

IC

IC

J

EXISTING

INSTRUMENT

CABINET

E3 E3

E3

E3

E3

E3

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:0

:0

A M

X102

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WEST AERATION BASIN

(1A/2A) ELECTRICAL

DEMOLITION PLAN

GB

KLG

06/13/23

MTJ

18678704-

100% DRAFT CONSTRUCTION DOCUMENTS

ASCALE

WEST AERATION BASIN (1A/2A) DEMOLITION PLAN

KEYNOTES - DEMOLITION

# DESCRIPTION

E3

1' -0

4'

-9

1'-0" 8" 8" 1'-0"

(F.V.)

5'-6"

(F.V.)

5'-6"

04-S101

2-#5 DIAG EF

#5@ 8 EW EF

EXISTING

WALL

1' -4

#6X18"@ 12 OC

DWL W/ 6" MIN

EMBED INTO

EXISTING WALL

EXISTING

SLAB

SEE PLAN SEE PLAN

OPENING

TYP

ASCALE

1 0 1 2

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WEST AERATION BASIN

(1A/2A) PLAN

GS

SKM

06/13/23

TJH

18678704-

FINAL CONSTRUCTION DOCUMENTS

SCALE A

WEST AERATION BASIN (1A/2A) PLAN1

SCALE A

WALL ELEVATION2

06/13/23

6"-RC

6"-CLI

6"-CLI

6"-CLI

6"-RC

4"-RC/RAS

4"-RC/RAS

SEE 01-C106 FOR

CONTINUATION SEE 01-C106 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

4"-ABI 4"-ABI

PLUG VALVE (TYP)(NC)(NC)

SEE 05-D101 FOR

CONTINUATION

1AX1a

1AX1b

2AX1a

2AX1b

1OX1a 2OX1a

1OX1b 2OX1b

ANOXIC 1

ANOXIC 1

ANOXIC 1

ANOXIC 1

OXIC 1 OXIC 1

OXIC 1 OXIC 1

AERATION BASIN NO. 1A AERATION BASIN NO. 2A

8"-ABI

8"-ABI

SUMERSIBLE

MIXER (TYP)

SEE 05-D101 FOR

CONTINUATION

6"-CLI

04-ABMX-1A1

04-ABMX-1A3

04-ABMX-1A2 04-ABMX-2A2

04-ABMX-2A3

04-ABMX-2A1

6"-RC

4"-LPA

3"-LPA3"-LPA

D01 D01

D03

D02D02

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:3

:1

P

M

D101

MOUNT RUSHMORE NATIONAL MEMORIAL

272051

WEST AERATION BASIN

(1A/2A) PROCESS PLAN

CLR

DJG

06/13/23

KSP

18678704-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WEST AERATION BASIN (1A/2A) PROCESS PLAN

KEYNOTES - PROCESS

# DESCRIPTION

D01 SEE SHEET 00D-002 FOR PROCESS AIR SCHEMATIC AND VALVE

REQUIREMENTS.

D02 PROVIDE PNEUMATIC CONTROL VALVES AS SHOWN ON THE

PROCESS AIR SCHMEATIC (NOT INCLUDED IN PROCESS PLAN

VIEW).

D03 BID OPTION #2, REHABILITATE DOME COVER AS SPECIFIED IN

SECTION 09 01 91 - REFINISHING FIBERGLASS DOMES. THE BASE

BID EXCLUDES DOME REHABILITATION WORK.

NOTES:

1. SEE SPECIFICATION SECTION 01 27 00 FOR DESCRIPTION OF

BID OPTIONS.

IC

IC IC

IC

ICIC IC IC

IC

IC IC

ICIC

IC IC

IC

IC

IC

IC

IC

IC

J

S

RECONNECT

TO EXISTING

CIRCUIT (TYP)

LSHH-134

AV-146C

AIT-147

AE-147A

AIT-146

AE-146B

AIT-137

AIT-136

AE-136B

AE-137A

AV-136C

AIT-138

AIT-148

AE-138A AE-148B

AE-148A

AE-138B

AV-146A

AV-146BAV-136B

AV-136A

AE-146AAE-136A

EXISTING NEMA 4X

INSTRUMENT CABINET

04-ABMX-1A2 04-ABMX-2A2

04-ABMX-2A304-ABMX-1A3

04-ABMX-1A1 04-ABMX-2A1

00-E502 DISCONNECTS FOR

MIXERS, MOUNT ON

RACK TYP OF 10

LSHH-144

E04

S2 S2

S2 S2

E01

E02 E02

E02E02

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:0

:0

A M

E101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WEST AERATION BASIN

(1A/2A) POWER AND

LIGHTING PLANS

GB

KLG

06/13/23

MTJ

18678704-

100% DRAFT CONSTRUCTION DOCUMENTS

ASCALE

WEST AERATION BASIN (1A/2A) POWER PLAN

ASCALE

WEST AERATION BASIN (1A/2A) LIGHTING PLAN

KEYNOTES - ELECTRICAL

# DESCRIPTION

E01 VERIFY LIGHTING CONTROL SWITCHES AT EACH ENTRANCE TO THE

AERATION BASION ARE IN GOOD CONDITION AND REPLACE SWITCHES

IF REQUIRED. CIRCUIT LIGHTING TO EXISTING SWITCHES.

E02 REPLACE EXISTING LUMINAIRE WITH STANCHION MOUNT. PROVIDE 1

1/2" CONDUIT FOR SUPPORT.

E04 EXISTING NEMA 4X PULL BOX.

GENERAL NOTES

1. SEE AREA CLASSIFICATION AND ELECTRICAL EQUIPMENT INSTALLATION

SCHEDULE ON SHEET 00-E607.

1'-0"1'-6" 5'-6" 1'-0" 5'-6" 1'-0" 5'-6" 1'-0" 5'-6" 1'-6"1'-0"

-0

7'

-0

1' -0

1'

-6

8' -0

1'

-0

9' -9

1'

-0

'-0

1'

-6

1' -0

1'-6" CONCRETE BASE

SEE SHEET NOTE 1

TOC EL 4975.003'

-6

1'-0"

1'-0"

1'-6"

1'-6"

1'-0"

1'-0"

1'-0"

1'-0"

1' -6

1' -0

1' -0

1'

-0

1' -0

1' -0

1' -0

1' -6

1' -0

1' -0

05-S301

05-S301

05-S301

05-S301

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST AERATION BASIN

(1B/2B) FOUNDATION PLAN

GS

SKM

06/13/23

TJH

18678705-

FINAL CONSTRUCTION DOCUMENTSASCALE

AERATION BASIN FOUNDATION PLAN

GENERAL NOTES:

1. SEE SHEET 00-S001 FOR GENERAL STRUCTURAL NOTES.

2. FOR TYPICAL STRUCTURAL DETAILS, SEE SHEETS 00-S

SERIES SHEETS.

3. COORDINATE ALL WALL AND SLAB PENETRATIONS WITH

ELECTRICAL AND PROCESS DRAWINGS.

SHEET NOTES:

1. 1'-6" CONCRETE BASE SLAB WITH #8@9 EW T&B W/ 90 DEG HK

EE. NORTH/SOUTH BARS ARE INNER BARS. OVER A 2'-0"

THICK FREE DRAINING GRANULAR BEDDING.

7' -0

5'

-0

9' -9

4'

-0

5' -0

6"

1' -0

12'-4" 3'-4" 12'-4"

1'-0" 6"

10'-6" 4"

3'-4" 4"

10'-6" 6"

1'-0"

PRE-FABRICATED

DOME BY DOME

MANUFACTURER

1'-0" CONCRETE SLAB

SEE SHEET NOTE 2

TOC EL 4993.00

1' -0

6"

05-S301

1'-0" 8" 8" 1'-0"

8" 1'-0" 1'-0" 8"

1'-0" 8" 8" 1'-0"

WALL OPENING BELOW,

TYP

TOC

EL 4993.00

TOC

EL 4993.00

GUARDRAIL,

SEE NOTE 3

TOW

EL 4995.00

05-S301

05-S301

05-S301

SIM

05-S301

05-S301

SIM

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S102

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST AERATION BASIN

(1B/2B) UPPER LEVEL

FLOOR PLAN

GS

SKM

06/13/23

TJH

18678705-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

AERATION BASIN UPPER LEVEL FLOOR PLAN

GENERAL NOTES:

1. SEE SHEET 00-S001 FOR GENERAL STRUCTURAL NOTES.

2. FOR TYPICAL STRUCTURAL DETAILS, SEE SHEETS 00-S

SERIES SHEETS.

SHEET NOTES:

1. PRE-FABRICATED DOME ON AERATION BASIN TO BE

ATTACHED TO AERATION BASIN BY DOME MANUFACTURER.

2. 1'-0" CONCRETE SLAB WITH #5@12 EW T&B. NORTH/SOUTH

BARS ARE INNER BARS.

3. SEE SPECIFICATION 05 52 46 FOR GUARDRAIL REQUIREMENTS.

KEYNOTES:

1 REMOVABLE RAILING SECTION

SEE PLANSEE PLAN

GRADE

SEE CIVIL

SEE PLAN

#5@8 EW EF

#7@8 EW EF

3" C

LR

#7@8 DOWELS EF

SLAB REINFORCING,

SEE PLAN

SEE PLAN

ROUGHENED CJ

W/ 6" PVC WS

(MIN)

2'-0"

FREE DRAINING

GRANULAR MATERIAL,

SEE SHEET NOTE 1,

SHEET 05-S101

FIBERGLASS DOME,

ATTACHMENT TO CONCRETE

BY DOME MANUFACTURER

LAP

LAP

LAP

TOC WALL

EL = SEE PLAN

MAIN LEVEL

EL = SEE PLAN

TOC SLAB

EL = SEE PLAN

4'-0"

S E

E P

LA

N

EQ EQ

REINFORCING,

SEE PLAN

NOTE 1

SEE PLAN

#6@8 EW EF

NOTES:

1. TOP SLAB NOT PRESENT AT SIM CONDITION.

3" C

LR

FREE DRAINING

GRANULAR MATERIAL,

SEE SHEET NOTE 1,

SHEET 05-S101

#6@8 DOWELS EF

SLAB REINFORCING,

SEE PLAN

LAP

LAP

TOC SLAB

EL = SEE PLAN

MAIN LEVEL

EL = SEE PLAN

GUARDRAIL, SEE

SPECIFICATION 05 52 46

#5@8 EW EFSEE PLAN

GRADE

SEE CIVIL

#7@8 EW EF

SEE PLAN

SLAB REINFORCING,

SEE PLAN

6" PVC WS

3" C

LR

#7@8 DOWELS EF

SEE PLAN

(MIN)

2'-0"

FREE DRAINING

GRANULAR MATERIAL,

SEE SHEET NOTE 1,

SHEET 05-S101

S E

E P

LA

N

FIBERGLASS DOME,

ATTACHMENT TO CONCRETE

BY DOME MANUFACTURER

LAP

LAP

#5@12 W/STD

HK AT END

LAP

LAP

TOC WALL

EL = SEE PLAN

MAIN LEVEL

EL = SEE PLAN

TOC SLAB

EL = SEE PLAN

8"

SEE PLANSEE PLANSEE PLANSEE PLANSEE PLAN

S E

E P

LA

N

8"

4-#8 EW

FREE DRAINING GRANULAR

MATERIAL, SEE SHEET NOTE 1,

SHEET 05-S101

REINF TO MATCH

SLAB REINF IN SIZE

& SPACING

LAPREINFORCING,

SEE PLAN

#6@8 DOWELS

#6@8 EW EF

1' -4

REINFORCING,

SEE PLAN

S E

E P

LA

N

SEE PLAN

PLAN

SEE

#5@8 EW EF

#6@8 EW EF

#7@8 EW EF

2-#5 DIAG EF

SEE PLANSEE PLAN

#5@12 W/STD HK AT END

LAP BSCALE

ASCALE

1 0 1 2

SCALE OF FEET

2 0 2 4

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S301

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST AERATION BASIN

(1B/2B) SECTIONS

GS

SKM

06/13/23

TJH

18678705-

FINAL CONSTRUCTION DOCUMENTS

SCALE A

WALL SECTION1

SCALE A

WALL SECTION2

SCALE A

WALL SECTION3

SCALE B

SECTION4

SCALE B

SECTION5

SEE 01-C106 FOR

CONTINUATION

SEE 07-D101 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

6"-RC

6"-CLI

6"-CLI

6"-CLI

6"-RC

4"-RC/RAS

4"-RC/RAS

4"-ABI

D101

PLUG VALVE (TYP)

1'-0"

1'-0"

1'-0" 1'-0"

8"

1OX1c

OXIC 1

AERATION BASIN NO. 1B AERATION BASIN NO. 2B

1OX1d

OXIC 1

1OX1e

OXIC 1

1AX2

ANOXIC 1

1OX2

OXIC 2

2OX1c

OXIC 1

2OX1d

OXIC 1

2OX1e

OXIC 1

2AX2

ANOXIC 1

2OX2

OXIC 2

8"-ABI

8"-ABI

SEE 04-D101 FOR

CONTINUATION

SEE 04-D101 FOR

CONTINUATION

05-ABMX-2B1

05-ABMX-2B5

05-ABMX-2B4

05-ABMX-2B2

05-ABMX-2B305-ABMX-1B3

05-ABMX-1B205-ABMX-1B4

05-ABMX-1B5

05-ABMX-1B1

SUMERSIBLE

MIXER (TYP)

4"-LPA

D01

TOC SLAB

4975.00

TOC WALL

4995.00

6"-CLI

6"-RC

CL 4985.50

8"-ABI

CL 4991.35

4"-ABI

CL 4987.50

4"-RC/RAS

CL 4985.50

4"-RC/RAS

CL 4985.50

PLUG VALVE (TYP)

8"-ABI

CL 4986.25

3"-LPA 3"-LPA

4"-LPA

3"-LPA

CL 4987.50

6"-CLI

CL 4986.92

6"-CLI

6"-CLI

CL 4986.50

CL 4985.39

EL 4988.17(AT TEE)

(AT TEE)

(AT BEND)

D02

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:3

:2

P

M

D101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST AERATION BASIN

(1B/2B) PROCESS PLAN &

SECTION

CLR

DJG

06/13/23

KSP

18678705-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

PROPOSED AERATION BASIN PROCESS PLAN

SCALE AD101

SECTION2

KEYNOTES - PROCESS

# DESCRIPTION

D01 SEE SHEET 00-D002 FOR PROCESS AIR SCHEMATIC AND

VALVING REQUIREMENTS.

D02 NEW DOME COVER AS SPECIFIED IN SECTION 46 13 01 -

FIBERGLASS COVERS - DOME TYPE.

IC

IC IC

IC

ICIC IC IC

IC

IC IC

ICIC

IC IC

IC

IC

IC

IC

IC

IC

S

AIT-236

AIT-238 AIT-248

AIT-246

AIT-247

AIT-237

LSHH-234 LSHH-244

AE-237A

AE-236B

AV-236C

AV-246C

AE-247A

AE-246B

AV-246B

AV-246A

AE-248B

AE-248AAE-238A

AV-236A

AV-236B

AE-236A AE-246A

AE-238B

MOUNT MIXER

DECONTACTOR TO

GUARDRAIL,

DETAIL

4/00E502 (TYP)

05-ABMX-1B3

05-ABMX-1B4

05-ABMX-1B2 05-ABMX-2B2

05-ABMX-2B4

05-ABMX-1B5

05-ABMX-1B1 05-ABMX-2B1

05-ABMX-2B5

05-ABMX-2B3

INSTRUMENT CABINET

MOUNT ON RACK

DISCONNECTS FOR

MIXERS, MOUNT ON

TYP OF 10

00-E502

S2 S2

S2 S2

E01 E01

E01 E01

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:5

A M

E101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST AERATION BASIN

(1B/2B) POWER AND

LIGHTING PLAN

GB

KLG

06/13/23

MTJ

18678705-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

EAST AERATION BASIN (1B/2B) BASIN POWER PLAN

ASCALE

EAST AERATION BASIN (1B/2B) BASIN LIGHTING PLAN

KEYNOTES - ELECTRICAL

# DESCRIPTION

E01 PROVIDE 1 1/2" CONDUIT FOR SUPPORT OF STANCHION MOUNT

LUMINAIRE.

GENERAL NOTES

1. SEE AREA CLASSIFICATION AND ELECTRICAL EQUIPMENT INSTALLATION

SCHEDULE ON SHEET 00-E607.

187 235

J

IC IC

IC

IC

IC

IC

X01

X02

X03

LSHL-310

LSHH-310

LSHL-194

LSHH-194

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:5

:5

A

M

X101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WEST CLARIFIER (#1)

ELECTRICAL DEMOLITION

PLAN

GB

KLG

06/13/23

MTJ

18678706-

FINAL CONSTRUCTION DOCUMENTS

1/4" = 1'-0"

WEST CLARIFIER (#1) DEMOLITION PLAN

KEYNOTES - DEMOLITION

# DESCRIPTION

X01 REMOVE CONTROL PANEL, CABLE AND

CONDUIT TO REMAIN AND BE

RECONNECTED.

X02 REMOVE ELECTRICAL CONNECTION TO

MECHAINSM.

X03 REMOVE INSTRUMENTS, CABLE TO

REMAIN AND BE RECONNECTED.

6"-CLI

4"-CLI

6"-SCM

6"-FTI

4"-RAS/WAS

SEE 01-C106 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

06-CLAR-1

D01

D01

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:3

:5

P

M

D101

MOUNT RUSHMORE NATIONAL MEMORIAL

272051

WEST CLARIFIER (#1)

DEMOLITION & PROCESS

PLAN

CLR

DJG

06/13/23

KSP

18678706-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

EXISTING FINAL CLARIFIER PROCESS PLAN

ASCALE

EXISTING FINAL CLARIFIER DEMOLITION PLAN

KEYNOTES - PROCESS

# DESCRIPTION

D01 BID OPTION #2, REHABILITATE DOME COVER AS SPECIFIED IN

SECTION 09 01 91 - REFINISHING FIBERGLASS DOMES. THE BASE

BID EXCLUDES DOME REHABILITATION WORK.

NOTES:

1. SEE SPECIFICATION SECTION 01 27 00 FOR DESCRIPTION OF

BID OPTIONS.

IC IC

IC

IC

IC

IC

J

S

E01

E02

E03

06-CLAR-1

LSHH-310

LSHL-310

LCP2-17NSHH-155

NSH-155

LE-155

LSHH-194

LSHL-194

LIT-155

E02

06-CLAR-1

S2 E04

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:0

:4

A M

E101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WEST CLARIFIER (#1)

POWER AND LIGHTING

PLAN

GB

KLG

06/13/23

MTJ

18678706-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WEST CLARIFIER (#1) POWER PLAN

ASCALE

WEST CLARIFIER (#1) LIGHTING PLAN

GENERAL NOTES

1. SEE AREA CLASSIFICATION AND ELECTRICAL EQUIPMENT INSTALLATION

SCHEDULE ON SHEET 00-E607.

KEYNOTES - ELECTRICAL

# DESCRIPTION

E01 REPLACE EXISTING CONTROL PANEL,

RE-USE EXISTING CONDUITS. CP

06-CLAR-1.

E02 EXISTING 8X8 NEMA 4X.

E03 MOUNT TO GUARDRAIL.

E04 REPLACE EXISTING LUMINAIRE WITH

STANCHION MOUNT. PROVIDE 1 1/2"

CONDUIT FOR SUPPORT.

R

2' -2

R 10'-0

1'-2" THICK MAT SLAB WITH

#6 RADIAL BARS 14" OC

MAX TOP & BOTTOM

OUTER BARS

#6 @ 14 CIRCUMFERENTIAL

TOP & BOT INNER BARS, TYP

STAGGER 2X LAP SPLICE

LENGTH AS SHOWN IN

SCHEDULE. STAGGER LAPS

MIN 3'-0"

1'-0" 1'-2"

07-S301

07-S301

KCJ WITH WS IN WALL

AT THIRD POINTS

KCJ WITH WS

MAX

1'-2"

MAX

1'-2"

R 3'-8"

ASCALE

1 0 1 2

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST CLARIFIER (#2)

FOUNDATION PLAN

ARA

SKM

06/13/23

TJH

18678707-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

CLARIFIER FOUNDATION PLAN

GENERAL NOTES:

1. SEE SHEET 00-S001 FOR GENERAL STRUCTURAL NOTES.

2. FOR TYPICAL STRUCTURAL DETAILS, SEE SHEETS 00-S

SERIES SHEETS.

SHEET NOTES:

1. PROVIDE 6" PVC WATERSTOPS IN ALL CONSTRUCTION JOINTS

IN ALL SLABS, WALL TO SLAB JOINTS, AND WALL

CONSTRUCTION OR CONTROL JOINTS FOR ALL BELOW GRADE

EXTERIOR WALLS AND WATER CONTAINING STRUCTURES

UNLESS NOTED OTHERWISE.

2. COORDINATE AND VERIFY ALL DIMENSIONS AND LOCATIONS

OF SUPPORTS WITH ACTUAL CLARIFIER EQUIPMENT

FURNISHED.

3. PROVIDE 24" GRANULAR FILL BENEATH CLARIFIER SLAB.

R 11 '-2

1'-2" 1'-0" 6"

CONCRETE

STAIRS

TOC TOPPING

TOC TOPPING

07-S301

EFFLUENT

PIPING

TOCEL 4987.89

TOCEL 4988.59

TOC

4989.22

KCJ WITH WS IN WALL

AT THIRD POINTS

KCJ IN LAUNDER WALL

AND SLAB AT THIRD

POINTS

1'-1 7/8"

MECHANISM SUPPLIER TO

DESIGN AND FURNISH

SCUM BOX SUPPORT

FRAME PER SPEC 46 43 24.

HANDRAIL PER

SPEC 05 52 46.

WALKWAY PER

SPEC 46 43 24.

ASCALE

1 0 1 2

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S102

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST CLARIFIER (#2) UPPER

LEVEL FLOOR PLAN

ARA

SKM

06/13/23

TJH

18678707-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

CLARIFIER UPPER LEVEL FLOOR PLAN

GENERAL NOTES:

1. SEE SHEET 00-S001 FOR GENERAL STRUCTURAL NOTES.

2. FOR TYPICAL STRUCTURAL DETAILS, SEE SHEETS 00-S

SERIES SHEETS.

SHEET NOTES:

1. PROVIDE 6" PVC WATERSTOPS IN ALL CONSTRUCTION JOINTS

IN ALL SLABS, WALL TO SLAB JOINTS, AND WALL

CONSTRUCTION OR CONTROL JOINTS FOR ALL BELOW GRADE

EXTERIOR WALLS AND WATER CONTAINING STRUCTURES

UNLESS NOTED OTHERWISE.

2. FIBERGLASS DOME TO BE ANCHORED TO CLARIFIER WALL BY

DOME MANUFACTURER.

3. COORDINATE STRUCTURAL WITH ACTUAL CLARIFIER

EQUIPMENT SUPPLIED.

4. STAIR HEIGHT TO BE DETERMINED BY EQUIPMENT PROVIDED,

USE 7" RISERS, 11" TREAD.

5. SEE SPECIFICATION 05 52 46 FOR WALKWAY GUARDRAIL

REQUIREMENTS.

SEE PLAN

3" C

LR

SEE PLAN

2" CONCRETE

TOPPING

RADIAL BARS, SEE

PLAN

ROUGHENED CJ

W/ 6" PVC WS

LAP TYP

#6 @ 12 DOWELS EF

#6 @ 12 EW EF

CONCRETE

TOPPING VARIES,

SEE PLAN

ROUGHENED CJ

3-#5 EQ SPACED

TOP & BOT

#4 @ 12

3-#5 HORIZ STAGGER

LAPS MIN 6'-0"

#5 @ 12 TOP & BOT W/

MATCHING DOWEL AND

MECHANICAL SPLICE @

CONTRACTOR OPTION

GRADE,

SEE CIVIL

SEE PLAN

CONNECTION OF FIBERGLASS

DOME TO CLARIFIER WALL BY

DOME MANUFACTURER.

TOC

EL 4975.12

TOC

EL 4975.29

TOC

EL 4993.12

FIBERGLASS DOME

FRAME DOME AROUND WALKWAY

SUPPORT AND MECHANISM

ATTACHMENT AS REQUIRED

FREE DRAINING

GRANULAR MATERIAL,

SEE SHEET NOTE 3,

SHEET 07-S101

2'-0" (MIN)

SEE PLAN

ATTACHMENT OF CLARIFIER

MECHANISM TO EXTERIOR WALL

BY MECHANISM MANUFACTURER.

TOC

4987.72

TOC

SEE PLAN

2"

CIRCUMFERENTIAL

BARS, SEE PLAN

TOC FILL

(MIN)

2'-0" 3'-0" 1'-0" 3'-0"

1'-0"

1' -2

#5 @ 12 EW

FREE DRAINING

GRANULAR MATERIAL,

SEE SHEET NOTE 3,

SHEET 07-S101

#5 @ 12 EW T&B

NOTE:

COORDINATE ANGLE OF CENTRAL COLUMN OPENING WITH MECHANISM SUPPLIED.

4" RAS/WAS PIPE,

SEE PROCESS

-2

MECHANISM DRIVE

SHAFT SUPPORT

BRACKET AND

BEARING

7'-0" DIAMETER

#5 @ 12 EW T&B

TOC

EL 4972.12

TOC

4974.37

KCJ

4-#5 BARS

EACH WAY

CENTERED

AT OPENING

SLAB REINF

SEE PLAN

"90°

6"

1/ 2"

PROVIDE 7/16" WIDE X 1 1/2"

LONG SLOTS FOR WEIR

ELEVATION ADJUSTMENT.

DETAIL OF

WEIR PLATE

2" 3"

1/

2" 3"

7/8"

7/8"

1' -0

/2

1/

2"

1/ 2"

(PROJ.)

1 1/2"

ADJUST 132 - 5/8" X 10" HOOK ANCHOR

BOLTS WITH 1-H.N. & 1-C.W.

EA. (2-BOLTS PER SUPPT.)

45° CHAMFER FOR

MASTIC SEAL

5/8" X 1 3/4" CTS'K. FLAT HEAD

BOLTS WITH 1-H.N. & 1-C.W. EA.

3/4" X 2" M. BOLT WITH

1-H.N. & 2-C.W. EA.

SECTION AT WEIR

3"

DETAIL OF SCUM

BAFFLE JOINT

136 - 5/8"⌀ X 10" LG.

HOOK ANCHOR BOLTS

WITH 1-H.N. EA.

1/

2"

1/ 2"

SQ.

WASHER

1 3/4" PROJ.

BUTT PL.

5/ 8"

5/ 8"

1/

4" A

D

JU

S T

3"

V NOTCH WEIR

EL 4989.30

ASCALE

SCALE OF FEET

0 1 2 3

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-S

.r v t

-J u n -2

S301

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST CLARIFIER (#2)

SECTIONS

ARA

SKM

06/13/23

TJH

18678707-

FINAL CONSTRUCTION DOCUMENTS

SCALE A

CLARIFIER WALL SECTION1

SCALE A

CENTRAL COLUMN SECTION2

SCALE A

SECTION3

SEE 05-D101 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

SEE 01-C106 FOR

CONTINUATION

6"-CLI

4"-CLI

6"-SCM

4"-RAS/WAS

6"-FTI

D101

D101

07-CLAR-2

D101

TOC BOTTOM

4975.00

TOC CHANNEL

4987.50

MAIN LEVEL

4993.00

4"-RAS/WAS

CL 4972.37

6"-SCM

CL 4985.00

6"-FTI

CL 4988.04

07-CLAR-2

(AT WALL)

(AT WALL)

(AT WALL)

D01

TOC BOTTOM

4975.00

TOC CHANNEL

4987.50

MAIN LEVEL

4993.00

6"-CLI

CL 4985.50

4"-CLI

CL 4985.50 6"-SCM

CL 4985.00

07-CLAR-2

(AT WALL)

D01

TOC CHANNEL

4987.50

6"-SCM

CL 4985.00

(AT WALL)

BSCALE

ASCALE

2 0 2 64

SCALE OF FEET

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:3

:5

P

M

D101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST CLARIFIER (#2)

PROCESS PLAN &

SECTIONS

CLR

DJG

06/13/23

KSP

18678707-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

PROPOSED FINAL CLARIFIER PROCESS PLAN

SCALE AD101

SECTION2

SCALE AD101

SECTION3

SCALE BD101

SECTION4

KEYNOTES - PROCESS

# DESCRIPTION

D01 NEW DOME COVER AS SPECIFIED IN

SECTION 46 13 01 - FIBERGLASS COVERS -

DOME TYPE.

IC

IC

IC

J

S

NSHH-255

NSH-255

MCC-1

PLC-1

02-LP-1:37

E01

E02

E03

07-CLAR-2

LE-255

LIT-255

LSHH-294

LSHL-294

CP 07-CLAR-2

S2 E04

02-LP-1:38

E05

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:5

A M

E101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

EAST CLARIFIER (#2)

POWER AND LIGHTING

PLAN

GB

KLG

06/13/23

MTJ

18678707-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

EAST CLARIFIER (#2) POWER PLAN

ASCALE

EAST CLARIFIER (#2) LIGHTING PLAN

GENERAL NOTES

1. SEE AREA CLASSIFICATION AND ELECTRICAL EQUIPMENT INSTALLATION

SCHEDULE ON SHEET 00-E607.

KEYNOTES - ELECTRICAL

# DESCRIPTION

E01 DETAIL 04/00-E502.

E02 NEMA 4X PULLBOX, MOUNT TO

CLARIFIER WALL.

E03 MOUNT TO GUARDRAIL.

E04 MOUNT 1 1/4" CONUIT FOR STANCHION

MOUNT LIGHT TO GUARDRAIL.

E05 NEMA 4X PULLBOX.

X01

X01

X02

X02

X03

X04 X04

X05

A

X101

B

X101

C

X101

X03

X02X02

X02X02 X03

X01

X05

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:4

:3

P

M

X101 272051

WINTER BIOSOLIDS

STORAGE DEMOLITION

PLAN

CLR

DJG

06/13/23

KSP

18678708-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WINTER BIOSOLIDS STORAGE FLOOR PLAN

GENERAL NOTES

1. CONTRACTOR TO TAKE SPECIAL CARE WHEN REMOVING

FEATURES ON THIS SHEET SO TO NOT DAMAGE THE EXISTING

STRUCTURE.

2. SEQUENCE WORK SO THAT WINTER SOLIDS DEWATERING

EQUIPMENT CAN BE UTILIZED DURING TIME PERIOD THAT

DEWATERING EQUIPMENT LOCATED IN THE SOUTH BUILDING IS

OUT OF SERVICE.

NO SCALE

PHOTOGRAPHA

NO SCALE

PHOTOGRAPHB

NO SCALE

PHOTOGRAPHC

X101

X101

X101

KEYNOTES - DEMOLITION

# DESCRIPTION

X01 REMOVE EXISTING EQUIPMENT PAD. USING A SAW, CUT PAD LOOSE

FROM EXISTING SLAB. DRILL OUT END OF ANY EXPOSED REBAR 1-1/2"

DEEP AND FILL WITH NON-SHRINK EPOXY GROUT.

X02 DEMOLISH AND DISPOSE OF BAG FILTER EQUIPMENT.

X03 DEMOLISH AND DISPOSE OF EXISTING SOLIDS HOLDING TANK.

X04 DEMOLISH AND DISPOSE OF ALL EXPOSED PIPING. CUT DRAIN LINES

FLUSH WITH FLOOR AND CAP OR PLUG UNUSED PIPING BELOW

FLOOR LEVEL SO AS NOT TO INTERFERE WITH NEW SOLIDS HOLDING

TANKS.

X05 DEMOLISH AND DISPOSED OF BAG FILTER COAGULANT TANK AND

ALL ASSOCIATED ELECTRICAL AND CONTROL CIRCUITS.

IC

J

T

P B

C B

INCOMING FEEDER

CONDUITS AND

JUNCTION BOX

TO REMAIN

INCOMING

CONTROLS

TO REMAIN

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:0

A M

X102

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WINTER BIOSOLIDS

STORAGE ELECTRICAL

PLAN - DEMO

GB

KLG

06/13/23

MTJ

18678708-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WINTER BIOSOLIDS STORAGE ELECTRICAL PLAN - DEMO

GENERAL NOTES

1. DEMO ALL ELECTRICAL CONDUITS, WIRE AND EQUIPMENT BACK TO

SOURCE.

4"-WAS

4"-WAS

4"-DR

BIOSOLIDS TANK-1

BIO SOLIDS TANK-2

SEE 01-C103 FOR

CONITUATION

SEE 01-C103 FOR

CONITUATION

SEE 01-C103 FOR

CONITUATION

D101

D101

PLUG

VALVE

(TYP)

2 1/2"-WAS

WINTER SOLIDS

PUMP-1

WINTER SOLIDS

PUMP-2

08-WBT-1

08-WBT-2

4"-WAS

08-WSP-1

08-WSP-2

4"-WAS

4"-WAS

4"-WAS

FF

5004.00

CEILING

5012.504"-WAS

CL 5008.75

4"-WAS

CL 5001.00

BIO SOLIDS

TANK-2

PLUG

VALVE (TYP)

BIO SOLIDS

TANK-1

4"-WAS

4"-WAS

CL 5009.83

WINTER SOLIDS

PUMP-2

WINTER SOLIDS

PUMP-1

08-WBT-2 08-WBT-1

08-WSP-108-WSP-2

FF

5004.00

CEILING

5012.504"-WAS

CL 5008.75

BIO SOLIDS TANK-1

PLUG VALVE

(TYP)

4"-WAS

CL 5009.83

4"-WAS

CL 5007.67

WINTER BIOSOLIDS

PUMP-1

08-WBT-1

08-WSP-1

4"-WAS

CL 5005.00

4"-WAS

CL 5001.00

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:4

:2

P

M

D101

MOUNT RUSHMORE NATIONAL MEMORIAL

272051

WINTER BIOSOLIDS

STORAGE PROCESS PLAN &

SECTIONS

CLR

DJG

06/13/23

KSP

18678708-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WINTER BIOSOLIDS STORAGE FLOOR PLAN

SCALE AD101

SECTION2

SCALE AD101

SECTION1

270°

315°

0°

45°

90°

135°

180°

225°

PLAN - BIOSOLIDS

STORAGE TANK (7'-2" ⌀ X 6'-5 1/2") - WBT-1

ITEM

DESCRIPTION

VERTICAL DISTANCE FROM

BASE OF TANK TO

CENTERLINE OF ITEM

1 6 IN DIA VENT CONNECTION NA - TOP ENTRY

2 4 IN DIA FILL CONNECTION SIDE - 4-3"

3 36 IN DIA TOP ACCESS FLANGE NA - TOP ENTRY

2 IN DIA OVERFLOW SIDE - 4'-3"

1 IN DIA DRAIN CONNECTION SIDE - 0'-6"

4 IN DIA PUMP SUCTION CONNECTION SIDE - 0'-6"

NADOME TOP-FLAT BOTTOM CONFIGURATION

2 IN ULTRA SONIC SENSOR NA - TOP ENTRY

270°

315°

0°

45°

90°

135°

180°

225°

PLAN - BIOSOLIDS

STORAGE TANK (7'-2" ⌀ X 6'-5 1/2") - WBT-2

ITEM

DESCRIPTION

VERTICAL DISTANCE FROM

BASE OF TANK TO

CENTERLINE OF ITEM

1 6 IN DIA VENT CONNECTION NA - TOP ENTRY

2 4 IN DIA FILL CONNECTION SIDE - 4-3"

3 36 IN DIA TOP ACCESS FLANGE NA - TOP ENTRY

2 IN DIA OVERFLOW SIDE - 4'-3"

1 IN DIA DRAIN CONNECTION SIDE - 0'-6"

4 IN DIA PUMP SUCTION CONNECTION SIDE - 0'-6"

NADOME TOP-FLAT BOTTOM CONFIGURATION

2 IN ULTRA SONIC SENSOR NA - TOP ENTRY

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-D

.r v t

/9

/2

:4

:2

P

M

D501

MOUNT RUSHMORE NATIONAL MEMORIAL

272051

WINTER BIOSOLIDS

STORAGE BUILDING TANK

DETAILS

CLR

DJG

06/13/23

KSP

18678708-

FINAL CONSTRUCTION DOCUMENTS

NO SCALE

BIOSOLIDS STORAGE TANK PLAN1

NO SCALE

BIOSOLIDS STORAGE TANK PLAN2

T

T

ΔP

Δ P

T 08-EF-1

08-MAU-1

x8 x1

12x12

12x12

G

-8 x

R1-12x8

R1-12x8

(435 CFM)

M1

A

M101

B

M101

EQUIPMENT PAD, SEE

STRUCTURAL DETAILS

1" LP PIPING UP

FROM BELOW GRADE.

SEE CIVIL PLANS FOR

CONTINUATIOM.

REGULATOR, DOWNSTREAM

PRESSURE 0.5"WC

SHUT-OFF VALVE

3/4"-NG

X1

X3

X2

FF

5004.00

CEILING

5012.50 x1

08-MAU-1

R1-12x8

EQUIPMENT PAD

FF

5004.00

CEILING

5012.50

8x12

12x12

08-EF-1

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M

O R

U W a s te w a te r R e h a b a n d E x p a n s io n

/1

-0

-M

P .r v t

/9

/2

:1

:1

P M

M101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WINTER BIOSOLIDS

STORAGE MECHANICAL

PLANS

DJD

DJD

06/13/23

AJC

18678708-

100% DRAFT CONSTRUCTION DOCUMENTS

ASCALE

WINTER BIOSOLIDS STORAGE MECHANICAL PLAN

ASCALE

WINTER BIOSOLIDS STORAGE MECHANICAL DEMOLITION PLAN

SCALE AM101

SECTION AT 08-MAU-1A

SCALE AM101

SECTION AT 08-EF-1B

KEYNOTES - MECHANICAL

# DESCRIPTION

M1 TERMINATE OPEN END DUCT WITH BIRDSCREEN 12” AFF, MOUNT VOLUME

DAMPER IN VERTICAL 48” AFF AND BALANCE TO THE INDICATED CFM.

X1 DEMOLISH EXHAUST FAN IN VERTICAL, DUCTWORK, LOUVERS AND

CONTROLS.

X2 DEMOLISH INTAKE LOUVER AND DAMPER.

X3 DEMOLISH UNIT HEATER AND CONTROLS.

IC

IC

IC

J

IC

IC

IC

J

J

T

B

E

E

-M A

U

-108-LP-1:1

+48"

GFCI

08-LP-1:1

08-LP-1:1

+48"

GFCI

MS 08-SP-1

MS 08-SP-2

08-LP-1

08-BP-1

WP

GFCI

WET

08-SP-2

08-SP-1

PGB

LIT-380

LIT-375

PSH-298

PSH-299

+48"

GFCI

08-EF-1

08-WBT-2

08-WBT-1

08-BP-1

INCOMING FEEDER

CONDUITS AND

JUNCTION BOX

INCOMING

CONTROLS CONDUIT

AND JUNCTION BOX

08-LP-1:3

08-FS-1

08-FS-2

08-BVAP-103-INV-1:6

AFD 08-WSP-1

AFD 08-WSP-2

E02 E03

E04

AIT-681, ASH-681

ASHH-681, AE-681

XS-681.

08-LP-1:2

P3

P3E P3E

P3E

P3

GO/NO GO

LIGHT SYSTEM

03-INV-1:6 03-INV-1:6

03-INV-1:6

W2

03-INV-1:6

03-INV-1:6

E02 E02

E02

E02

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OF

A u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:2

A M

E101

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WINTER BIOSOLIDS

STORAGE POWER AND

LIGHTING PLANS

GB

KLG

06/13/23

MTJ

18678708-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WINTER BIOSOLIDS STORAGE POWER PLAN

ASCALE

WINTER BIOSOLIDS STORAGE LIGHTING PLAN

GENERAL NOTES

1. SEE AREA CLASSIFICATION AND ELECTRICAL EQUIPMENT INSTALLATION

SCHEDULE ON SHEET 00-E607.

KEYNOTES - ELECTRICAL

# DESCRIPTION

E02 CIRCUIT EMERGENCY LIGHTING

FIXTURES AND 08-BVAP-1 TO 03-INV-1 IN

THE SOUTH BUILDING. PROVIDE

DISCONNECT SWITCH WITH SIGN

READING "EMERGENCY LIGHTING

CIRCUIT DISCONNECT SWTICH. DO NOT

TURN OFF EXCEPT FOR MAINTENANCE".

PROVIDE #4 CONDUCTORS FROM

03-INV-1 TO SWTICH AND THEN

TRANSITION TO #12 CONDUCTORS

INSIDE OF BUILDING.

E03 PROVIDE PULL BOX FOR DISCRETE

SIGNALS TO 03-PLC-2 FIELD LOCATE AND

SIZE PER NEC REQUIREMENTS FOR THE

CONDUIT CONFIGURATION.

E04 PROVIDE PULL BOX FOR ANALOG

SIGNALS TO 03-PLC-2. FIELD LOCATE

AND SIZE PER NEC REQUIREMENTS FOR

THE CONDUIT CONFIGURATION.

#4/0 AWG, TYP.

REFER TO SECTION

26 41 13 (TYP)

ASCALE

SCALE OF FEET

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:0

A M

E102

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WINTER BIOSOLIDS

LIGHTNING PROTECTION /

GROUNDING PLAN

GB

KLG

06/13/23

MTJ

18678708-

FINAL CONSTRUCTION DOCUMENTS

ASCALE

WINTER BIOSOLIDS LIGHTNING

PROTECTION / GROUNDING PLAN

GENERAL NOTES

1. SEE AREA CLASSIFICATION AND ELECTRICAL EQUIPMENT INSTALLATION

SCHEDULE ON SHEET 00-E607.

2. REFER TO SECTION 26 41 13 FOR ADDITIONAL LIGHTING PROTECTION

SYSTEM DESIGN AND INSTALLATION REQUIREMENTS.

5 5 4 4

30KVA ,3PH

480:208Y/120V

08-LP-1

120/208V

3PH,

4W

-C

D

AFD

-C

D

AFD

0.5

BRANCH PANEL 08-BP-1 100A, 480, 3 PHASE, 3W, 22KAIC, NEMA 4X

100 A 3P

F R

O M

3-

M C

C -1

A T

S O

U T

H B

U

IL

D

IN

G

20A 3P

W

IN

T E

R S

O

LI

D S

P

U M

P

-W S

P -2

3#

,1 #1

2G , 3

/4 "C

20A 3P

3#

,1 #1

2G , 3

/4 "C

S U

M P

P U

M P

-S

P P

-1

20A 3P

W

IN

T E

R S

O

LI

D

P

U M

P

-W S

P -1

S U

M P

P U

M P

-S

P P

-2

3#

,1 #1

2G , 3

/4 "C

20A 3P

3#6, 1#10G, 1"C

45A 3P

30 A 3P

3#

,1 #1

2G , 3

/4 "C

3#1, 1#8G, 1 1/2"C 3#

, 1

#1 2G

, 3 /4

"C

15AF

M A

K E

U P

A

IR

U N

IT

-M A

U -1

20A 3P

MFR CABLE, 3/4"C MFR CABLE, 3/4"C

IC IC

#6 BARE,

1/2"C

4#1, 1#6G, 2"C

E01

SPD

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:0

A M

E601

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WINTER BIOSOLIDS

ONE-LINE & SCHEDULE

GB

KLG

06/13/23

MTJ

18678708-

FINAL CONSTRUCTION DOCUMENTS

Notes:

TOTAL ESTIMATED DEMAND + SPARE: 3 A

SPARE AMPERAGE: 20.00%

TOTAL ESTIMATED DEMAND 3 A

TOTAL CONNECTED: 3 A

REC 720 VA 100.00% 720 VA TOTAL ESTIMATED DEMAND: 925 VA

LTS 90 VA 125.00% 113 VA TOTAL CONNECTED LOAD: 902 VA

HVAC 92 VA 100.00% 92 VA

LOAD CLASSIFICATION CONNECTED LOAD DEMAND FACTOR ESTIMATED DEMAND

PANEL TOTALS

TOTAL AMPS: 8 A 6 A 0 A

TOTAL LOAD: 810 VA 592 VA 0 VA

29 30 27 28 25 26 23 24 21 22 19 20 17 18 15 16 13 14

11 SPARE -- 20 A 1 0.0 12

9 SPARE -- 20 A 1 0.0 10

7 SPARE -- 20 A 1 0.0 0.0 1 15 A -- SPARE 8

5 SPARE -- 20 A 1 0.0 0.0 1 15 A -- SPARE 6

3 08-EF-1 HVAC 20 A 1 92.4 500.0 1 20 A Power 08-BVAP-1 4

1 REC REC 20 A 1 720.0 90.0 1 20 A LTS LIGHTING 2

CKT CIRCUIT DESCRIPTION CLASS TRIP P A B C P TRIP CLASS CIRCUIT DESCRIPTION CKT

Service Entrance Label: No 200% Neutral: No Enclosure: NEMA 4X Integral SPD: No MCB Rating: 100 A Mounting: WALL Wires: 4 Mains Rating: 100 A

Supply From: Phases: 3 Mains Type: MCB Location: WINTER BIOSOLIDS STORAGE BLDG Volts: 208Y/120 A.I.C. Rating:

Branch Panel: 08-LP-1

KEYNOTES - ELECTRICAL

# DESCRIPTION

E01 FUSE SIZE BASED ON BASIS OF DESIGN

EQUIPMENT RATINGS. COORDINATE

FUSE SIZES FOR THE ACTUAL SUPPLIED

EQUIPMENT IN ACCORDANCE WITH NEC

REQUIREMENTS. REFER TO APPROVED

EQUIPMENT SHOP DRAWINGS

FOREQUIPMENT RATINGS. TYPICAL ALL

EQUIPMENT SHOWN WITH WITH FUSED

DISCONNECT SWITCHES.

CPT

ON REMOTE

OFF

W

R

A

A

CR3CR4 CR2

AUTO MANUAL

CR1

CR2

CR3

CR4

CR2

CR5

MCP

HP

XO

Ø A

Ø B

Ø C

G N

D

480:120V

FUFU

FU

RUN

AFD

24V+

INPUT 1

INPUT 4

CR1OX

RUN COMMAND

CR2 PRESSURE SIGNAL

CR4 FAULT SIGNAL

CR3 RUNNING SIGNAL

PLC

OUTPUT 1

OUTPUT 2

INPUT 2

INPUT 3

PRESSURE

AFD INPUT/OUTPUT CONTROL

INPUT 1 REMOTE MOTOR START/STOP COMMAND CONTACT CLOSED - RUN COMMAND ISSUED

INPUT 2 INHIBIT CONTACT CLOSED - MOTOR IS PERMITTED TO RUN

CONTACT OPEN - TRIP/INHIBIT MOTOR RUN REGARDLESS OF CONTROL SOURCE

I/O FUNCTION CONTROL/STAUS DESCRIPTION

INPUT 4 AUTOMATIC/MANUAL COMMAND

CONTACT CLOSED - AUTOMATIC MODE

CONTACT OPEN - MANUAL MODE

INPUT 3 RESET CONTACT CLOSED - RESET THE AFD

RESET

POWER INDICATOR

RUN INDICATOR

FAULT INDICATOR

PRESSURE INDICATOR

MOTOR RUNNING

TO PLC

MOTOR FAULT

TO PLC

PRESSURE

SIGNAL TO PLC

CR5 AUTO/MANUAL COMMAND

OUTPUT 2 FAULT AFD HAS ISSUED A FAULT

OUTPUT 1 RUN AFD IS RUNNING BASED ON MOTOR CURRENT

SWITCH

AUX

AUTO MODE

SPEED SIGNAL

FROM

03-PLC-2

4-20mA

INPUT

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFA

u to d e s k D o c s /1

M O

R U

W a s te w a te r R e h a b a n d

E x p a n s io n

/1

-0

-E

.r v t

/9

/2

:1

:0

A M

E602

MOUNT RUSHMORE NATIONAL MEMORIAL

10298966

WINTER BIOSOLIDS MOTOR

CONTROL DIAGRAMS

GB

KLG

06/13/23

MTJ

18678708-

FINAL CONSTRUCTION DOCUMENTS

MOTOR CONTROL DIAGRAM 08-CD1

08-WSP-1

08-WSP-2

GENERAL NOTES

1. CONTROL DIAGRAMS ARE SHOWN FOR FUNCTIONAL PURPOSES.

PROVIDE COMPONENTS/INTERLOCKS NECESSARY FOR A COMPLETE

AND FUNCTIONING SYSTEM AS OUTLINED IN SECTION 40 61 96 -

PROCESS CONTROL DESCRIPTIONS.

2. ▲ DENOTES FIELD DEVICE.

XXX

ACKNOWLEDGE

EMERGENCY STOP

FAILURE

FORWARD-OFF-REVERSE

FORWARD-REVERSE

FAST-SLOW

HAND-AUTO

HAND-OFF-AUTO

HAND-OFF-REMOTE

LEAD-LAG

LEAD-LAG-STANDBY

LOCAL-OFF-REMOTE

LOCAL-REMOTE

LEAD-STANDBY

MANUAL-AUTO

OPEN-AUTO-CLOSE

OPEN-CLOSE

ON-OFF

OPEN-STOP-CLOSE

RUN-JOG

RUN-JOG-REVERSE

SILENCE

START-STOP

START

STOP

ACK

ES

FAIL

FOR

FR

FS

HA

HOA

HOR

LL

LLS

LOR

LR

LS

MA

OAC

OC

OO

OSC

RJ

RJR

SIL

SS

STR

STP

GENERAL NOTES:

1. THIS IS A STANDARD INSTRUMENTATION SYMBOLOGY AND

ABBREVIATIONS SHEET. LISTING OF SYMBOLS AND

ABBREVIATIONS DOES NOT IMPLY ALL SYMBOLS AND

ABBREVIATIONS HAVE BEEN USED ON THIS PROJECT.

2. SEE PROCESS, MECHANICAL AND PLUMBING LEGEND SHEET

FOR MISCELLANEOUS PIPING SYMBOLS.

3. SCREENING OR SHADING OF WORK IS USED TO INDICATE

EXISTING COMPONENTS OR TO DE-EMPHASIZE PROPOSED

IMPROVEMENTS TO HIGHLIGHT SELECTED TRADE WORK.

REFER TO CONTEXT OF EACH SHEET FOR USAGE.

4. VALVE SYMBOLS SHOWN HERE ARE APPLICABLE ONLY TO

INSTRUMENTATION DIAGRAMS. SEE PROCESS, MECHANICAL

AND PLUMBING LEGEND SHEET FOR VALVE SYMBOLS USED

ELSEWHERE ON THE SHEETS.

SUCCEEDING LETTERSFIRST LETTER

CONTROL

USER'S CHOICE

HIGH

LOW

CONTROL

STATION

RATIO (FRACTION)

DIFFERENTIAL

TIME; RATE OF

CHANGE

SCAN

SENSOR (PRIMARY

LIGHT

INDICATE

VIEWING DEVICE

GLASS, GAUGE

ELEMENT)

USER'S CHOICE

ALARMA

C

B

E

D

F

H

J

I

K

M

L

G

XXX

TIME SCHEDULE

RUNNING

TIME,

LEVEL

USERS CHOICE

USERS CHOICE

USER'S CHOICE

HAND

CURRENT

(ELECTRICAL)

POWER

FLOW RATE

VOLTAGE

ANALYSIS

BURNER,

COMBUSTION

FI

M

FT

SWITCH

USER'S CHOICE

TRANSMIT

DRIVER,

UNCLASSIFIED

AUXILLIARY DEVICES

MULTIFUNCTION

VALVE, DAMPER,

LOUVER

SAFETY

INTEGRATE,

TOTALIZE

X AXIS

Y AXIS

WELL PROBE

MULTIFUNCTION

RECORD

POINT (TEST)

CONNECTION

USER'S CHOICE

ORIFICE,

RESTRICTION

UNCLASSIFIED

FINAL CONTROL

ELEMENT

ACTUATOR,

N

P

O

Q

S

R

T

U

V

X

Y

W

Z

TEMPERATURE

VIBRATION, MECH.

WEIGHT, FORCE

POSITION,

DIMENSION

UNCLASSIFIED

EVENT, STATE

OR PRESENCE

MULTIVARIABLE

ANALYSIS

TORQUE

USER'S CHOICE

RADIATION

SPEED,

FREQUENCY

PRESSURE,

VACUUM

QUANTITY

TE

FG

O O

X X

MAIN PROCESS LINE

SECONDARY PROCESS LINE

AUXILIARY PROCESS LINE

DIRECTION OF FLOW

PNEUMATIC SIGNAL

ELECTRICAL SIGNAL

HYDRAULIC SIGNAL

SOFTWARE OR DATA LINK

SIGNAL CONNECTION

CROSSOVER - NO CONNECTION

CAPILLARY

OFF PAGE CONNECTOR

I

ORIFICE PLATE

PITOT TUBE OR ANNUBAR

ROTOMETER

SONIC OR ULTRASONIC FLOWMETER

MAGNETIC FLOWMETER

MASS DISPERSION FLOWMETER

FLUME

WEIR

PROPELLER OR TURBINE METER

VENTURI TUBE

VENTURI FLUME

FLOAT SWITCH

TEMPERATURE ELEMENT WITH THERMOWELL

SIGHT FLOW GLASS

LOCALLY MOUNTED FIELD INSTRUMENTATION

MOUNTED ON PANEL FRONT

MOUNTED INSIDE PANEL

FRONT PANEL MOUNTED ON AUXILIARY PANEL

(SUBSCRIPT INDICATES PANEL)

MOUNTED INSIDE AUXILIARY PANEL

PILOT LIGHT

INSTRUMENT FUNCTIONS SHARING COMMON HOUSING

COMPLEX INTERLOCK AS DEFINED IN CONTROL DIAGRAM OR IN

SPECIFICATIONS

SHARED DISPLAY, SHARED CONTROL,

FIELD MOUNTED

SHARED DISPLAY, SHARED CONTROL, PRIMARY LOCATION -

NORMALLY ACCESSIBLE TO OPERATOR

PROGRAMMABLE LOGIC CONTROL, PRIMARY LOCATION -

NORMALLY ACCESSIBLE TO OPERATOR

PROGRAMMABLE LOGIC CONTROL, FIELD MOUNTED

UNCLASSIFIED

MULTIFUNCTION

MIDDLE,

INTERMEDIATE

USER'S CHOICE

USER'S CHOICE

CLOSED

READOUT OR

PASSIVE

FUNCTION

OUTPUT/ACTIVE

FUNCTION

FUNCTION

MODIFIER

MEASURED OR

INITIATING

VARIABLE

VARIABLE

MODIFIER

INSTRUMENT SYMBOLOGYPRIMARY ELEMENT SYMBOLOGY

LINE TYPES

CROSS REFERENCE SYMBOLOGY

INSTRUMENT IDENTIFICATION LETTERS MISCELLANEOUS

SYMBOLOGY

CONTROL SWITCH NOTATION ABBREVIATIONS

DEVIATION

SCAN

INTEGRATE

TOTALIZE

RUN

STOP

ACCESSORY DEVICES

UNCLASSIFIED

Z AXIS SAFETY

INSTRUMENTED

SYSTEM

XXX

zzz

YYY

SUBSCRIPTS

XXX - CONNECTOR NUMBER

YYY - SHEET CONTINUATION

ZZZ - SERVICE ABBREVIATION

A

IA

ES

NG

HYD

PLANT COMPRESSED AIR

INSTRUMENTATION AIR

ELECTRIC SUPPLY

NATURAL GAS

HYDRAULIC

TYPES OF POWER SUPPLY

ANALOG INPUT

ANALOG OUTPUT

CHLORINE (ANALYZER MODIFIER)

DIGITAL INPUT

DENSITY (ANALYZER MODIFIER)

DIGITAL OUTPUT

VOLTAGE TO PNEUMATIC

INPUT/OUTPUT

CURRENT TO PNEUMATIC

OPERATOR INTERFACE

OXYGEN (ANALYZER MODIFIER)

CARBON MONOXIDE (ANALYZER MODIFIER)

CARBON DIOXIDE (ANALYZER MODIFIER)

COMBUSTIBLES (ANALYZER MODIFIER)

CONDUCTIVITY (ANALYZER MODIFIER)

DISSOLVED OXYGEN (ANALYZER MODIFIER)

HYDROGEN SULFIDE (ANALYZER MODIFIER)

HYDROGEN CHLORIDE (ANALYZER MODIFIER)

NITROGEN OXIDE (ANALYZER MODIFIER)

PROCESS AND INSTRUMENTATION DIAGRAM

AO

CO

AI

DO

DO

DI

I/O I/P

OI

O2

CL2

CO2

COMB

COND

DEN

E/P H2S

HCL

NOX

P&ID

TURBIDITY (ANALYZER MODIFIER)

WIDE AREA NETWORK

TURB

WAN

SUSPENDED SOLIDS (ANALYZER MODIFIER)SS

MISCELLANEOUS INSTRUMENTATION ABBREVIATIONS

PHOSPHATEPHOS

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA

INSTRUMENTATION

P&ID

INSTRUMENTATION LEGENDG001

09-

205 235

GENERAL NOTES:

1. THIS IS A STANDARD INSTRUMENTATION SYMBOLOGY AND

ABBREVIATIONS SHEET. LISTING OF SYMBOLS AND

ABBREVIATIONS DOES NOT IMPLY ALL SYMBOLS AND

ABBREVIATIONS HAVE BEEN USED ON THIS PROJECT.

2. SEE PROCESS, MECHANICAL AND PLUMBING LEGEND SHEET

FOR MISCELLANEOUS PIPING SYMBOLS.

3. SCREENING OR SHADING OF WORK IS USED TO INDICATE

EXISTING COMPONENTS OR TO DE-EMPHASIZE PROPOSED

IMPROVEMENTS TO HIGHLIGHT SELECTED TRADE WORK.

REFER TO CONTEXT OF EACH SHEET FOR USAGE.

4. VALVE SYMBOLS SHOWN HERE ARE APPLICABLE ONLY TO

INSTRUMENTATION DIAGRAMS. SEE PROCESS, MECHANICAL

AND PLUMBING LEGEND SHEET FOR VALVE SYMBOLS USED

ELSEWHERE ON THE SHEETS.

MISCELLANEOUS

SYMBOLOGY

EQUIPMENT

DIAPHRAGM PUMP

DOUBLE DISC PUMP

PROGRESSIVE CAVITY PUMP

POSITIVE DISPLACEMENT PUMP

HYDRAULICALLY ACTIVATED PISTON PUMP

HAND PUMP

PERISTALIC PUMP

PROPELLOR PUMP

POLYMER PUMP

EDUCTOR PUMP

CENTRIGUAL SUMP PUMP

CARBON FEED PUMP

CENTRIFUGAL PUMP

HORIZONTAL CENTRIFUGAL PUMP

RECIRCULATION PUMP

PROPORTING PUMP

SLUDGE LAGOON PUMP

ROTORY LOBE PUMP

SCREW PUMP

SUBMERSIBLE PUMP

VERTICAL INLINE PUMP

VACUUM PUMP

VERTICAL TURBINE SUBMERSIBLE PUMP

VERTICAL CAN PUMP TYPE 1

VERTICAL CAN PUMP TYPE 2

EQUIPMENT VALVES

BALL VALVE

BUTTERFLY VALVE

CHECK VALVE

CONE VALVE

BALL CHECK VALVE

DIAPHRAGM VALVE

DOUBLE-DISK CHECK VALVE

GATE OR GENERAL VALVE

GLOBE VALVE

KNIFE GATE VALVE

NEEDLE VALVE

PLUG VALVE

PINCH VALVE

THREE-WAY PLUG VALVE

THREE-WAY BALL VALVE

PRESSURE-REGULATING VALVE

PRESSURE-REDUCING VALVE

VAC = VACUUM

A = AIR RELEASE

AIR-RELEASE VACUUM VALVE

PRESSURE-RELIEF VALVE

X

OR

THREE-WAY CONTROL VALVE

SOLENOID

FLOAT OPERATOR

S

SPRING-OPPOSED SINGLE-ACTING

PNEUMATIC CYLINDER

DOUBLE-ACTING PNEUMATIC CYLINDER

PNEUMATIC DIAPHRAGM

PNEUMATIC DIAPHRAGM WITH POSITIONER

ACTUATOR SYMBOLOGY

M = MOTOR

P = PNEUMATIC

X OPERATOR ABBREVIATIONS:

ANNULAR SEAL

STACKED ANNULAR SEALS

FLEXIBLE HOSE

AERATION DIFFUSER

CAMERA

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA

INSTRUMENTATION

P&ID

INSTRUMENTATION LEGENDG002

206 235

PRESSURE INSTRUMENTATION

WITH ANNULAR SEAL

NOT TO SCALE

NOTES:

1. SEAL UNITS TO BE FACTORY ASSEMBLED.

2. MODIFY ORIENTATION OF INSTRUMENT WHERE INSTALLED ON VERTICAL PIPE.

1/4" SST PIPE FITTINGS

PRESSURE GAUGEPRESSURE INDICATING TRANSMITTER

WITH PRESSURE SWITCH

PRESSURE INSTRUMENTATION

WITH ANNULAR SEAL

NOT TO SCALE

NOTES:

1. SEAL UNITS TO BE FACTORY ASSEMBLED.

2. MODIFY ORIENTATION OF INSTRUMENT WHERE INSTALLED ON VERTICAL PIPE.

1/4" SST PIPE NIPPLE

PRESSURE GAUGE

FLANGE BOLT

FLANGE GASKET

FLANGE BOLT

FLANGE GASKET

2 GROUNDING RINGS

MAGMETER

BONDING STUD ON BODY

GROUND RING BOND TO

METER BODY WITH #10

STRANDED COPPER WIRE

MAGNETIC FLOW METER GROUNDING

RING BONDING DETAIL

NOT TO SCALE

NOTES:

1. THREADOLET TO BE MOUNTED ON THE

HORIZONTAL CENTERLINE OF THE PIPE.

2. SWITCH "FLAT-UP AND LEVEL" INDICATOR

SHALL BE ADHERED TO.

3. ALL CONDUIT RUNS MUST BE SUPPORTED AT

LEAST EVERY 10 FEET AND WITHIN 2 FEET OF

EACH END. ALL MOUNTED BRACKETS ARE TO

BE ANCHORED SECURELY TO AN I-BEAM, WALL,

OR STAND.

REMOTE PRESSURE TRANSMITTER-

LIQUID APPLICATIONS

NOT TO SCALE

1/2" SS TUBING, TYPICALBALL VALVE

PROCESS PIPE

SLOPE DOWN

1/2 INCH

PER FOOT

SLOPE DOWN

1/2 INCH

PER FOOT

PRESSURE

TRANSMITTER

2-VALVE MANIFOLD

THERMAL FLOW SWITCH

GENERAL INSTALLATION

NOT TO SCALE

FURNISHED WITH SWITCH

FURNISHED WITH SWITCH

NOTE 1

NOTE 1

NOTE 2

NOTE 2

PIPE SPEC. #

ITEM DESCRIPTION

MATERIAL LIST

SPEC.NUM.

1 1" THREADOLET

2 FLOW SWITCH

REMOTE MOUNT

LOCAL MOUNT

1/2" PIPE

PROCESS PIPE

2-VALVE MANIFOLD

PRESSURE

TRANSMITTER

NOTES

ALL MATERIALS AND TYPE FITTINGS FOR EACH

INSTALLATION ARE PER PIPING SPECIFICATION.

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA

INSTRUMENTATION

INSTRUMENT

INSTALLATION DETAILSY501

207 235

TYPICAL INSTALLATION DETAIL

WET WELL LEVEL FLOATS

NOT TO SCALE

JUNCTION BOX

ACCESS OPENING

(SEE NOTE 1)

TOP OF WET WELL

WET WELL WALL

PROVIDE SLACK IN CABLE

TO ENABLE FUTURE ADJUSTMENT

1"PVC MOUNTING PIPE

STRAP FLOAT SWITCH CABLE TO

PIPE EVERY 12"

PIPE CLAMP & 3/8" SS BOLTS WITH

EXPANSION ANCHORS EVERY 3' MAX

CABLE

FLOAT

FLOAT

NOTES:

1. LEVEL FLOATS TO BE MOUNTED WITHIN 18" TO ONE SIDEOF ACCESS

OPENING.

2. WHEN FLOATS ARE SET CLOSER THAN 18" OF LEVEL DIFFERENCE,

ROTATE FLOATS AROUND PIPE TO AVOID INTERFERENCE.

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA

INSTRUMENTATION

INSTRUMENT

INSTALLATION DETAILSY502

208 235

PROCESS

HMI

PLC-2

B 09-Y623

DRAIN FROM

WINTER SOLIDS BUILDING

MANHOLE MANHOLE CHANNEL SCREEN

03-SCR-1

LIT

LI

MA

FAULT

M

FE

US

FIT

SAMPLER

FI

BAR SCREEN

(MANUAL)

INFLUENT CHANNEL

8" SCREEN OVERFLOW

A 09-Y602

TO EQ BASIN

6"-SS

DUMPSTER

M

MA

M

LI

FI

HS

ESTOP

FOR

HOA

LCS 03-SCR-01

LOCAL CONTROL STATION

S

S

S

SV-105C

SV-105B

SV-105A

NPW

RUN

O/L

KQI

HOURS

R

TEMP

HS

RESET

CP 03-SCR-1

CONTROL PANEL

SANITARY SEWER

FROM PARK

(V)

(V)

(V)

(V)

(V)

(V)

GENERAL NOTES:

1. THE PROCESS AND INSTRUMENTATION

DIAGRAM IS NOT USED TO PROVIDE

COMPLETE DETAIL OF ALL MECHANICAL

COMPONENTS (E.G. ISOLATION VALVES).

THE PRIMARY FUNCTION OF THIS

DIAGRAM IS TO DEPICT

INSTRUMENTATION, CONTROL

FUNCTIONS AND SIGNALS ASSOCIATED

WITH THE PROCESS.

SC

SC

INFLUENT SAMPLER

(CS-1)

INSTRUMENTATION

P&ID

HEADWORKS

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA

Y601

209 235

PLC-2

FROM SOUTH BUILDING SUMP PUMP

A 09-Y601

FROM HEADWORKS

B 09-Y611

FROM CLARIFIERS

(VIA SCUM PIT)

B 09-Y610

FROM RWAS

PUMPS

INFLUENT FLOW

EQUALIZATION BASIN

AERATED SLUDGE

HOLDING TANK

D 09-Y606

FROM AERATION

BLOWERS

A 09-Y604

TO AERATION

BASINS 2A, 1B, 2B

C 09-Y603

TO EQUALIZATION

BASIN

M

LIT

03-EQMX-1

E 09-Y603

TO EQUALIZATION

D 09-Y616

TO DEWATERING

BASIN DECANT

FE

FV

OVERFLOW

FV

B 09-Y604

BASINS 1A

M

EQ BASIN BYPASS

FV-125

LIT

ZC

FI

FI

ZC

FI

FI

LI

LIT

LI

M

M

RUN

MA

MA

FAIL

ZC

ZC

A 09-Y603

FROM EQUALIZATION BASIN

LPA

B 09-Y619

FROM LOADOUT

TGS

WAS / SCUM

A 09-Y601

FROM SOUTH BUILDING

UPPER LEVEL DRAINS

A 09-Y601

FROM HEADWORKS

CEN

A 09-Y619

CENTRATE FROM CENTRIFUGES

AND LOADOUT DRAIN

FV-225

I P

I P

GENERAL NOTES:

1. THE PROCESS AND INSTRUMENTATION

DIAGRAM IS NOT USED TO PROVIDE

COMPLETE DETAIL OF ALL MECHANICAL

COMPONENTS (E.G. ISOLATION VALVES).

THE PRIMARY FUNCTION OF THIS

DIAGRAM IS TO DEPICT

INSTRUMENTATION, CONTROL

FUNCTIONS AND SIGNALS ASSOCIATED

WITH THE PROCESS.

FIC

FLOW

FIC

FLOW

B 09-Y620

FROM FERRIC CHLORIDE SYSTEM

A 09-Y620

FROM FERRIC CHLORIDE SYSTEM

B 09-Y621

FROM SODIUM HYDROXIDE SYSTEM

A 09-Y621

FROM SODIUM HYDROXIDE SYSTEM

FC

FC

MS

TSH

GRINDER

03-ABIGR-1

KEYNOTES

# DESCRIPTION

Y01 BID OPTION #5, PROVIDE NEW AERATION

BASIN INFLUENT GRINDER (03-ABIGR-1),

CONTROL PANEL, VALVES AND PIPING.

THE BASE BID EXCLUDES THE ADDITION

OF THIS EQUIPMENT.

Y##

R

RUN

A

FAIL

HS

HOA

W

PWR

HS

M

MA

YL

HS

S/S M

RUN

MA

FAIL

YL

AUTO

M

Y01

480V

CONTROL PANEL

CP 03-ABIGR-1

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA INFLUENT EQ BASIN & AERATED

SLUDGE HOLDING TANKY602

09- INSTRUMENTATION

210 235

PLC-2

C 09-Y602

FROM INFLUENT FLOW

F 09-Y602

FROM AERATED SLUDGE

HOLDING TANK

EQUALIZATION BASIN #2

OVERFLOW

EQUALIZATION BASIN #3

M

LSLL

SUMP

M

LSLL

TO INFLUENT FLOW

03-EQMX-3

03-EQMX-2

LALL

LALL

M

M

RUN

MA

MA

FAIL

LALL

LALL

M

M

RUN

MA

MA

FAIL

GENERAL NOTES:

1. THE PROCESS AND INSTRUMENTATION

DIAGRAM IS NOT USED TO PROVIDE

COMPLETE DETAIL OF ALL MECHANICAL

COMPONENTS (E.G. ISOLATION VALVES).

THE PRIMARY FUNCTION OF THIS

DIAGRAM IS TO DEPICT

INSTRUMENTATION, CONTROL

FUNCTIONS AND SIGNALS ASSOCIATED

WITH THE PROCESS.

MS

MS

TSH

TSH

PMIS/PKG NO.

SHEET

OF

FINAL CONSTRUCTION DOCUMENTS

DATE:

DESIGNED:

TECH. REVIEW:

SUB SHEET NO.

PMIS/PKG NO.

DRAWING NO.

SHEET

TITLE OF SHEET

OFMOUNT RUSHMORE NATIONAL MEMORIAL

272051

EIS

KER

06/13/23

186787

CJA

INSTRUMENTATION

P&ID

EQUALIZATION BASINY603

211 235

PLC-1

F 09-Y605

TO AERATION BASIN 1B

09-Y606

FROM BLOWER HEADER

09-Y607

FROM ARP PUMPS

09-Y602

FROM INFLUENT FLOW

EQUALIZATION BASIN

09-Y607

FROM ARP PUMPS

PP

P

LSHH

137A

AE

DO

136B

AE

DO

M

04-ABMX-1A3

AIT

AIT

138A

AE

NO3

138B

AE

PH/TEMP

M

04-ABMX-1A1

M

04-ABMX-1A2

136A

AE

DO

M

04-ABMX-2A1

M

04-ABMX-2A2

146A

AE

DO

P

146B

AE

DO

LSHH

147A

AE

DO

M

04-ABMX-2A3

AIT

09-Y607

TO ARP PUMPS

09-Y607

TO ARP PUMPS

09-Y608

TO CLARIFIER NO. 1

RC/RAS

LPA

ABI

RC/RAS

LPA

09-Y605

FROM AERATION BASIN 2B

CLI

148A

NO3

148B

AE

PH/TEMP

ABI

ZC

136C

M

M

RUN

MA

MA

FAIL

TYPICAL OF 6 MIXERS TYPICAL OF 6 AIR VALVES

ZC

136C

P

LAHH

LAHH

TYPICAL OF 2

LEVEL SWITCHES

AI

138B

AI

138A

TI

138B

AI

138B pH

TI

138B

TEMP

AI

138A

NO3

AI

136B

AI

136B

DO

AI

136A

AI

136A

DO

AI

146B

AI

146B

DO

AI

146A

AI

146A

DO

AI

148B

AI

148A

TI

148B

AI

148B pH

TI

148B

TEMP

AI

148A

NO3

AIRZONE

1OX1b

ZONE

1AX1b ZONE

1OX1aZONE 1AX1a

AERATION BASIN 1A

AERATION BASIN 2A

ZONE

2AX1b

ZONE

2OX1b

ZONE

2OX1aZONE

2AX1a

AIR

AI

137A

AI

137A

DO

AIT

AIT

AI

147A

AI

147A

DO

A

B

A

C

B

AV-136BAV-136C

AV-136A

AV-146A

AV-146BAV-146C

A

B

C

RC

RC

CLI

HS

HS

S/S

ABI

09-Y602

FROM INFLUENT FLOW

EQUALIZATION BASIN

B

ABI

09-Y622A

ABI

P

D 09-Y605

TO AERATION BASIN 2B

E 09-Y605

TO AERATION BASINS 1B, 2B

GENERAL NOTES:

1. THE PROCESS AND INSTRUMENTATION

DIAGRAM IS NOT USED TO PROVIDE

COMPLETE DETAIL OF ALL MECHANICAL

COMPONENTS (E.G. ISOLATION VALVES).

THE PRIMARY FUNCTION OF THIS

DIAGRAM IS TO DEPICT

INSTRUMENTATION, CONTROL

FUNCTIONS AND SIGNALS ASSOCIATED

WITH THE PROCESS.

MS

TSH

AIR

AIR

AIR

AIR

AIR

AIR

CLI

CLI

FROM NORTH BUILDING

SUMP PUMP

PMIS/PKG NO.

SHEET

OF

F…

This is the start of the file's text. The full file is on GovTribe.