Amendment 0002 2 of 6
Attachment 1 Questions and Answers
Solicitation No. 140M0121R00006, Amendment 0001
Questions and Answers
Question No. 1 Over what duration is the work expected to be completed, e.g. 1 yr, 2 yr, flexible?
Answer No. 1 Since all the topics are paper studies and do not involve field or laboratory work we expect these projects to be completed within I year of award unless there are valid reasons for a longer time.
Question No. 2 What are the water depth range(s) being considered for Topic 3? Outside state 3-nautical-mile-limit (9 nm for Texas, the Gulf coast of Florida) to 200 m water depth or deeper?
Answer No. 2 Project should cover area within BOEM jurisdiction defined as beyond state waters up to 200nm distance from shore.