A04_Arrow_Canyon_Kiosks_SOW_44057084_Final.pdf
PDF 205 KB Posted
- Attached to
- ARROW CANYON KIOSKS DESIGN AND INSTALLATION
- Solicitation number
- 140LL027Q0032
- Issued by
- Not on record
About this file
This is a Statement of Work for the Arrow Canyon SNPLMA Project covering the procurement and installation of outdoor interpretive kiosks managed by the Bureau of Land Management (BLM) Las Vegas Field Office.
The Contractor shall furnish three new, commercial-grade, double-panel outdoor metal interpretive kiosks, each accommodating two 48-inch x 48-inch interpretive panels, designed for permanent outdoor installation in southern Nevada with a minimum 20-year service life. The kiosks must be constructed of corrosion-resistant metal, include vandal-resistant hardware, plexiglass protective coverings, and comply with BLM Visual System Guidelines. The Contractor is responsible for all design coordination with BLM personnel, graphic layout and production of interpretive panels using UV-resistant, weather-resistant materials, transportation to Government-designated staging areas, and complete installation including excavation, foundations, concrete footings, anchoring, assembly, and site restoration. The Government will provide approved installation locations within the Arrow Canyon Archaeological District, substantive interpretive content, and review/approval of designs. The Contractor must incorporate a minimum of two rounds of Government comments without additional cost and comply with all BLM requirements governing wilderness access, cultural resource protection, wildlife protection, fire prevention, and safety.
The anticipated period of performance is from contract award in October 2026 through September 30, 2027. Key milestones include preliminary shop drawing and sign layout submittal within 30 calendar days after award, Government review and comments within 15 calendar days, kiosk and sign delivery by May 15, 2027, and installation completion no later than June 15, 2027. The Contractor must provide final inspection-ready documentation, manufacturer warranty information, photographs, and electronic copies of approved artwork. A minimum five-year warranty against defects in materials and workmanship is required. An optional site visit will be offered prior to quotation submission to familiarize offerors with site conditions, access requirements (including potential 4x4 road travel up to 2.5 miles), and terrain. The Contractor bears all responsibility for labor, materials, equipment, transportation, mobilization, and logistical requirements in developing firm-fixed-price quotations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140LL027Q0032.pdf | ||
| B03_SCA_Wage_Determinations_2015-5593_Rev33.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Arrow Canyon SNPLMA Project – Kiosk Purchase and Installation
1. Background
The Arrow Canyon SNPLMA Project (BL90) supports the protection, interpretation, and public education of the significant cultural and natural resources associated with Arrow Canyon. As part of the project, the Bureau of Land Management (BLM) requires the procurement and installation of three outdoor interpretive kiosks and associated interpretive panels.
Arrow Canyon is managed by the BLM Las Vegas Field Office and includes designated wilderness. The Contractor shall perform all work in accordance with applicable BLM requirements governing access, resource protection, safety, and use of equipment.
2. Objective
The objective of this requirement is to provide, deliver, and install three durable outdoor interpretive kiosks and associated interpretive panels at BLM-approved locations within the Arrow Canyon project area.
The completed kiosks will provide visitors with educational information concerning the cultural, archaeological, wildlife, and natural-resource values of Arrow Canyon and appropriate resource-protection practices.
3. Scope of Work
The Contractor shall:
1. Furnish three (3) double-panel, outdoor-rated metal interpretive kiosks. Each kiosk shall accommodate two (2) 48-inch x 48-inch interpretive panels and meet the technical requirements specified in this Statement of Work.
2. Coordinate with designated BLM personnel regarding the layout and graphic design of interpretive panels.
3. Produce and print the final approved interpretive panels using materials and printing processes suitable for permanent outdoor exposure in southern Nevada.
4. Transport the kiosks and interpretive panels to the Government-designated staging/location area.
5. Assemble and install the kiosks at three (3) Government-approved locations.
6. Furnish all labor, materials, fasteners, anchors, concrete, foundations/footings, excavation, tools, equipment, transportation, handling, mobilization, and other items necessary to complete the installation unless specifically identified as Government-furnished.
7. Clean each installation area and restore areas disturbed by Contractor activities.
8. Provide final documentation and electronic copies of the approved sign artwork and as-built information for the kiosk installations.
4. Government-Furnished Information
The Government will provide:
• Government-approved kiosk installation locations following contract award.
• Interpretive subject matter and substantive interpretive content.
• Government review and approval of proposed graphic layouts.
• Government-furnished maps, logos, photographs, graphics, and other information when available and approved for use.
• Government comments concerning cultural-resource, wildlife, geological, and resource-protection information to be incorporated into the interpretive panels.
• Site access and resource-protection requirements applicable to the approved installation locations.
The kiosk locations will be within the Arrow Canyon Archaeological District. Specific installation locations will be identified following contract award in coordination with the Contractor and BLM personnel, including the appropriate district archaeologists.
The Government will identify the designated Contracting Officer and, as appropriate, technical personnel responsible for reviewing cultural-resource, wildlife, geological, and interpretive content.
The Contractor shall not independently alter substantive cultural-resource, wildlife, geological, or other Government-furnished interpretive information without Government approval.
5. Kiosk Requirements
The Contractor shall furnish three (3) new, commercial-grade, outdoor interpretive kiosks.
Each kiosk shall:
• Be a double-panel configuration accommodating two (2) 48-inch x 48-inch interpretive panels.
• Be designed for permanent outdoor installation.
• Be fabricated of metal.
• Be constructed of corrosion-resistant materials suitable for the southern Nevada environment.
• Have a color that complements the surrounding landscape and complies with applicable BLM Visual System Guidelines.
• Have a durable outdoor finish resistant to UV exposure, weather, dust, and normal public use.
• Include vandal-resistant/tamper-resistant hardware.
• Include plexiglass protective coverings for the interpretive panels.
• Include all required structural supports, framing, hardware, and anchoring components.
• Be capable of securely supporting the approved interpretive panels.
• Be anchored into the ground using concrete footings.
• Be designed and installed to remain stable under anticipated local wind and weather conditions.
• Have no sharp, exposed, or hazardous edges following installation.
• Have a minimum expected service life of twenty (20) years.
No substitutions in kiosk configuration or major materials shall be made without prior written Government approval.
6. Interpretive Panel Requirements
The Contractor shall provide graphic design, production, and printing of the interpretive panels.
BLM will provide the substantive written content for the panels, as well as applicable maps, logos, photographs, graphics, and other supporting information. The Contractor shall be responsible for professional graphic layout, formatting, incorporation of Government-furnished materials, and preparation of final production-ready artwork.
Each kiosk shall contain two (2) interpretive panels measuring 48 inches x 48 inches.
Panels shall:
• Be suitable for permanent outdoor exposure.
• Use UV-resistant, weather-resistant printing and materials.
• Have an expected service life of approximately twenty (20) years.
• Provide clear and legible text and graphics.
• Comply with applicable BLM Visual System Guidelines.
• Be compatible with the kiosk system furnished by the Contractor.
• Be securely mounted within the kiosk.
• Be capable of replacement if future interpretive updates are required.
The Contractor shall submit proposed graphic layouts to the Government for review and approval before printing.
The Contractor shall incorporate a minimum of two (2) rounds of Government comments into the final design without additional cost.
No panels shall be printed until final artwork has been approved by the Government.
7. Design and Approval Process
Within [30] calendar days after contract award, the Contractor shall submit proposed kiosk shop drawings, product information, and preliminary sign layouts.
The Government will review the submittals and provide comments within [15] calendar days, subject to Government workload and required technical review.
The Contractor shall incorporate Government comments and submit final production-ready artwork for approval.
Government approval of interpretive content shall not relieve the Contractor of responsibility for the quality, accuracy, legibility, dimensions, or production quality of the manufactured products.
8. Site Access and Installation
The Government will identify the three approved kiosk locations following contract award.
The kiosk locations will be within the Arrow Canyon Archaeological District. The Contractor shall coordinate with the Government and appropriate BLM personnel to confirm the approved installation locations prior to mobilization.
Prior to mobilization, the Contractor shall verify physical site conditions, access, staging requirements, and other conditions necessary to safely perform the installation.
Access to some installation locations may require travel on non-maintained 4x4 roads requiring high-clearance vehicles. Materials may need to be transported approximately 2.5 miles from a paved road to the kiosk locations.
The Contractor may use vehicles and/or mechanical equipment to transport materials to the installation sites, subject to applicable BLM requirements and approval.
The Government will provide a designated staging/parking area.
There are no existing foundations or pads for the kiosks. The Contractor shall provide all new foundations, footings, anchors, concrete, excavation, and other installation materials necessary for complete installation.
The Contractor shall comply with all applicable BLM requirements concerning:
• Wilderness;
• Access;
• Motorized and mechanical equipment;
• Cultural resources;
• Wildlife;
• Fire prevention;
• Safety;
• Waste disposal; and
• Protection of public lands.
The Contractor shall not disturb archaeological sites, artifacts, rock art, wildlife habitat, vegetation, or other resources except as specifically authorized by the Government.
The Contractor shall not relocate an approved kiosk location without written Government approval.
Installation shall include all excavation, foundations/footings, anchoring, assembly, leveling, mounting, cleanup, and restoration necessary for a complete installation.
9. Cultural and Natural Resource Protection
The Contractor shall take all reasonable measures to avoid damage or disturbance to cultural, archaeological, historical, paleontological, wildlife, and other natural resources.
The Contractor is not authorized to conduct archaeological investigations, collect artifacts, disturb cultural resources, or modify approved installation locations.
The Arrow Canyon Archaeological District contains numerous cultural sites. The Contractor shall coordinate with the appropriate BLM archaeologist regarding approved installation locations and shall avoid identified cultural resources.
If previously unknown cultural materials, artifacts, archaeological features, human remains, or other potentially sensitive resources are encountered during performance, the Contractor shall immediately cease work in the affected area and notify the Contracting Officer or designated Government representative. Work shall not resume in the affected area until directed by the Government.
10. Schedule
The anticipated Period of Performance is Date of Award through September 30, 2027.
The Government anticipates the following milestone schedule:
• Contract award/NTP: October 2026.
• Preliminary kiosk/shop drawing submittal: within 30 calendar days after award.
• Preliminary sign layout: within 30 calendar days after award.
• Government review/comments: within 15 calendar days after receipt of submittals.
• Final design approval: estimated timeframe to be established following Government review and Contractor revisions.
• Kiosk and sign delivery: May 15, 2027.
• Installation: completed no later than [June 15, 2027].
• Final inspection/correction: within [15] calendar days following installation.
The Contractor shall coordinate all field work with the Government.
11. Deliverables
The Contractor shall provide:
1. Three (3) new outdoor double-panel metal interpretive kiosks.
2. Kiosk shop drawings and product information.
3. Preliminary and final interpretive panel layouts.
4. Three (3) complete sets of final printed interpretive panels, consisting of two (2) 48-inch x 48-inch panels per kiosk.
5. Installation of all three kiosks at Government-approved locations.
6. All required foundations, anchors, concrete, hardware, and installation materials.
7. Photographs documenting completed installation.
8. Manufacturer warranty documentation.
9. Final electronic copies of all approved interpretive artwork in PDF format and, when applicable, native/editable design format.
10. As-built information documenting the completed kiosk installations.
12. Acceptance
The Government will inspect the completed work.
The kiosks and associated panels will be accepted when:
• Three kiosks have been delivered and installed at the Government-approved locations.
• Kiosks conform to the approved submittals and specifications.
• Kiosks are secure, level, structurally sound, and properly anchored.
• Interpretive panels conform to the approved final artwork.
• Panels are securely installed and free of significant printing or manufacturing defects.
• Installation areas have been cleaned and disturbed areas restored.
• Required documentation, warranty information, photographs, as-built information, and electronic artwork have been provided.
The Contractor shall correct deficiencies identified by the Government at no additional cost when such deficiencies are attributable to Contractor performance or failure to meet the requirements of the contract.
13. Warranty
The Contractor shall provide a minimum five-year warranty against defects in materials and workmanship for the kiosks, sign panels, hardware, and installation.
Manufacturer warranties exceeding the five-year minimum shall be provided to the Government.
14. Site Visit
Optional Site Visit:
The Government will offer an optional site visit prior to submission of quotations. The solicitation will provide the date, time, location, and RSVP requirements.
Offerors are encouraged to participate in the optional site visit to familiarize themselves with site conditions, access, terrain, staging requirements, and other conditions that may affect performance and pricing.
15. Contractor Responsibility
The Contractor shall provide all labor, supervision, materials, equipment, transportation, tools, mobilization, installation services, and other resources necessary to complete the work described in this Statement of Work unless specifically identified as Government-furnished.
The Contractor shall be responsible for coordinating its work and shall comply with all applicable Federal, State, and local requirements and BLM direction applicable to the work.
The Contractor shall be responsible for considering all known site access, transportation, installation, material, and logistical requirements when developing its firm-fixed-price quotation.