B09_A7_Questions_and_Answers_0001.pdf
PDF 593 KB Posted
- Attached to
- UINKARET MTNS LRP-LANG'S RUN MASTICATION
- Solicitation number
- 140L6424Q0007
About this file
This document is a questions and answers file related to a federal solicitation for mastication services. The Bureau of Land Management Arizona State Office is seeking quotes for vegetation treatment through mastication on the Lang's Run project area in the Uinkaret Mountains by February 8, 2024. Maps of the project area are attached. The statement of work indicates treatment is needed on slopes up to 58% but will not take place on slopes too steep for equipment. The incumbent contractor is not identified, indicating this is a new contract opportunity. Quotes should be submitted to the identified contracting specialist and contracting officer by the specified due date.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
BUREAU OF LAND MANAGEMENT
Arizona State Office One North Central Avenue, Suite 800
Phoenix, AZ 85004-4427 www.az.blm.gov
Solicitation: 140L6424Q0007 Uinkaret LRP Langs Run Mastication
Amendment 01
The purpose of this amendment (01) is to respond to all questions received.
Question 1: We would like to know if this is a brand-new contract OR if there is (was) an incumbent performing these services.
If not brand new, could you please provide the current / previous contract number?
Answer 1: This is a brand-new contract.
Question 2: I would like to get the maps/kml filesfor lang’s run 2 mastication so I can come look at location to get a proper bid.
Answer 2: Maps/kml files are attached.
Question 3: I am requesting maps for the Langs run project please.
Answer 3: Maps are attached.
Question 4: In the SOW on page one, in site specifics, it states slopes “range from flat to 58%.’ Is there mastication to be done on slopes of 58%?
Answer 4: The SOW is accurate about the slope but it should be added that treatment will not take place on slope where it is not feasible for equipment to do so and maintain soils.
Due to this modification all terms and conditions remain unchanged.
Quotes are due no later than February 8, 2024, by 12:00 pm (MS) to Cindy Gonzalez, Contract Specialist (CS), by email: chgonzalez@blm.gov, and Lisa Hariper, contracting Officer by email:lhariper@blm.gov.
Attachments:
A7. LangsRun_2 Transportation (Adobe Acrobat Document) A8. LangsRun_2_Project Area Final (Adobe Acrobat Document) A9. Langs_Run_2_Project_Area_Final.cpg A10. Langs_Run_2_Project_Area_Final.dbf A11. Langs_Run_2_Project_Area_Final.prj A12. Langs_Run_2_Project_Area_Final.sbn A13. Langs_Run_2_Project_Area_Final.sbx A14. Langs_Run_2_Project_Area_Final.shp A15. Langs_Run_2_Project_Area_Final.shx