Sol_140L6323Q0041_Amd_0002.pdf
PDF 92 KB Posted
- Attached to
- HI-YU MINE Engineering Evaluation/Cost Analysis Federal contract opportunity
- Solicitation number
- 140L6323Q0041
About this file
This document is an amendment to a solicitation issued by the Bureau of Land Management seeking proposals for engineering evaluation and cost analysis services related to the Hi-Yu Mine site. The amendment extends the proposal due date from September 19, 2023 to September 21, 2023 to allow offerors time to conduct a site visit. The period of performance for the resulting contract is expected to be from October 1, 2023 through March 28, 2025. The amendment clarifies that approximately 200 linear feet of fencing at the site will require repair or replacement and consists of chain link material. Public access is permitted for site visits via Fairbanks Creek Road, though entry into fenced areas or on-site buildings is discouraged until a work plan is approved. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L6323Q0041_Amd_0001.pdf | ||
| SOW_Hi-Yu_Mine_EECA_mh.pdf | ||
| Sol_140L6323Q0041.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L6323Q0041 x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LAA
ANCHORAGE AK 99513
222 W 7TH AVENUE, #13
BLM AK-STATE OFC BUS&FISC BR(AK952)
08/29/20230002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/29/2023
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project Title: Hi-Yu Mine Engineering Evaluation/Cost Analysis
This is a combined synopsis/ solicitation in accordance with FAR 13.105.
The Bureau of Land Management (BLM) has a requirement for Hi-Yu Mine Engineering
Evaluation/Cost Analysis. See Standard Form (SF) 1449 for items, technical specifications and quantities required.
All items must be in compliance with the Buy American Act.
Total cost to include delivery to the BLM Alaska Delivery address in block 15 unless
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Patrick Euler
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140L6323Q0041/0002 otherwise stated in the statement of work or specifications.
Include UEI or CAGE Code with quote or proposal.
The Government anticipates award of a single firm fixed price contract resulting from this solicitation but may award multiple contracts if more advantageous to the government.
Quotes should be submitted electronically to:
Patrick Euler at peuler@blm.gov
LIST OF CHANGES:
Bids due date: 19-SEP-23 changed to 21-SEP-23
This modification is to clarify and list questions and answers.
-What is the linear footage of fence that will need repair/replacement.
Answer: Approximately 200 linear feet of fence will need repair/replacement.
-What is the material of the existing fence?
Answer: The fence is chain link.
-Is the location open to public access for site visit.
Answer: The location is open to the public and accessible via Fairbanks Creek Road. From EIFO¿s
Field Manager, Tim Hammond: ¿In terms of public access, there is no restriction on public access to the land in general, but the purpose of the fence is to keep people away from hazardous conditions and we don't encourage anyone to go into the fenced area or the building, or to dig in potentially contaminated sites, before a contract is awarded, and a work plan approved.
Just looking and taking reference photos should not be a problem.¿
-If site is open to public access, can we please get an extension to gather more information from the site visit?
Answer: I have extended this until 9/21/2023.
All other terms and conditions remain unchanged.
Period of Performance: 10/01/2023 to 03/28/2025