This document is a Bid Schedule for a vault pumping contract for the Bureau of Land Management (BLM) Kemmerer Field Office (KFO) Recreation Sites. The contract is for a base year in 2024 with four option years through 2028. The bid schedule outlines the specific locations, quantities, unit costs, and total costs for pumping the vault toilets at 9 different recreation sites, as well as dump fees. The total estimated cost for the base year plus all four option years is provided.

The related federal contract opportunity is a solicitation (Solicitation Number: 140L6224R0001) for this vault pumping contract. The solicitation provides additional details, including a description of the required services, a list of the specific recreation sites and facilities to be serviced, and information about an optional site visit on 5/22/24. The contract is open to all interested parties, and responses are due by a specific deadline not included in the provided documents.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

VAULT PUMPING BID SCHEDULE FOR KFO BASE YEAR 2024
LOCATION/VAULTQUANTITYUNITSUNIT COSTTOTAL COST
NAMES HILL/SINGLE1EA$$
FONTENELLE/DOUBLE2EA$$
FONTENELLE DUMP STATION1EA$$
RIVER ACCESS/SINGLE1EA$$
TAIL RACE /DOUBLE1EA$$
WEEPING ROCK/DOUBLE1EA$$
SLATE CREEK/DOUBLE2EA$$
PINE CREEK/SINGLE1EA$$
SPILLWAY VAULT TOILET/DOUBLE1EA$$
DUMP FEES1EA$$
TOTAL COST BASE YEAR 2024$
VAULT PUMPING BID SCHEDULE FOR KFO OPTION YEAR 1 2025
LOCATION/VAULTQUANTITYUNITSUNIT COSTTOTAL COST
NAMES HILL/SINGLE1EA$$
FONTENELLE/DOUBLE2EA$$
FONTENELLE DUMP STATION1EA$$
RIVER ACCESS/SINGLE1EA$$
TAIL RACE /DOUBLE1EA$$
WEEPING ROCK/DOUBLE1EA$$
SLATE CREEK/DOUBLE2EA$$
PINE CREEK/SINGLE1EA$$
SPILLWAY VAULT TOILET/DOUBLE1EA$$
DUMP FEES1EA$$
TOTAL COST OPTION YEAR 1 2025$
VAULT PUMPING BID SCHEDULE FOR KFO OPTION YEAR 2 2026
LOCATION/VAULTQUANTITYUNITSUNIT COSTTOTAL COST
NAMES HILL/SINGLE1EA$$
FONTENELLE/DOUBLE2EA$$
FONTENELLE DUMP STATION1EA$$
RIVER ACCESS/SINGLE1EA$$
TAIL RACE /DOUBLE1EA$$
WEEPING ROCK/DOUBLE1EA$$
SLATE CREEK/DOUBLE2EA$$
PINE CREEK/SINGLE1EA$$
SPILLWAY VAULT TOILET/DOUBLE1EA$$
DUMP FEES1EA$$
TOTAL COST OPTION YEAR 3 2026$
VAULT PUMPING BID SCHEDULE FOR KFO OPTION YEAR 3 2027
LOCATION/VAULTQUANTITYUNITSUNIT COSTTOTAL COST
NAMES HILL/SINGLE1EA$$
FONTENELLE/DOUBLE2EA$$
FONTENELLE DUMP STATION1EA$$
RIVER ACCESS/SINGLE1EA$$
TAIL RACE /DOUBLE1EA$$
WEEPING ROCK/DOUBLE1EA$$
SLATE CREEK/DOUBLE2EA$$
PINE CREEK/SINGLE1EA$$
SPILLWAY VAULT TOILET/DOUBLE1EA$$
DUMP FEES1EA$$
TOTAL COST OPTION YEAR 4 2027$
VAULT PUMPING BID SCHEDULE FOR KFO OPTION YEAR 4 2028
LOCATION/VAULTQUANTITYUNITSUNIT COSTTOTAL COST
NAMES HILL/SINGLE1EA$$
FONTENELLE/DOUBLE2EA$$
FONTENELLE DUMP STATION1EA$$
RIVER ACCESS/SINGLE1EA$$
TAIL RACE /DOUBLE1EA$$
WEEPING ROCK/DOUBLE1EA$$
SLATE CREEK/DOUBLE2EA$$
PINE CREEK/SINGLE1EA$$
SPILLWAY VAULT TOILET/DOUBLE1EA$$
DUMP FEES1EA$$
TOTAL COST OPTION YEAR 4 2028$