Questions_Addressed_0001.docx

DOCX document 18 KB Posted

Attached to
DRYFORK/SMITH'SFORK LOWER CROSSING FENCE
Solicitation number
140L6223Q0020
Issued by

About this file

This document contains questions and answers related to federal contract solicitation number 140L6223Q0020 for fence construction along the Dryfork/Smithsfork Lower Crossing in Wyoming. The Bureau of Land Management is seeking to install approximately 1,009 feet of fencing with two 14-foot cattle guards and gates. Clearing up to 5 feet on each side of the fence line is permitted. A map of the layout is provided indicating the fence route and cattle guard locations. The timing of the work will need to be coordinated with a related project by Trout Unlimited which is scheduled to begin on September 18, 2023. Access to the fence area should be available by October 15, 2023.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L6223Q0020

AMD 001

Questions Addressed 140L6223Q00020 Dry Fork Smiths Form Lower Crossing Fence

1. Can fenceline be cleared?

a. Yes, it has been determined that 5-ft each side of fence may be cleared using equipment such as a brush hog.

2. Timing with TU project; when does TU plan to do their project?

a. TU is starting September 18, 2023.

3. Is the fence length accurate?

a. It is approximately 1,009 feet, so the 1,200-ft provides extra.

4. is there a more accurate map available of the fence layout?

a. Map attached. The map indicates two cattleguards. Each cattleguard is 14-ft. Fence will need to tied in with H braces on each side of the road, with 1 wire gate next to each cattleguard (2 gates total).

5. Is there an estimated beginning date for the fence, or a window for completion?

Fence area should be accessible by October 15, 2023.