QUESTIONandANSWERdocx_0001.docx
DOCX document 23 KB Posted
- Attached to
- PFO FENCE MATERIALS Federal contract opportunity
- Solicitation number
- 140L6220Q0086
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| QUESTIONandANSWER3docx_0003.docx | DOCX document | |
| Sol_140L6220Q0086_Amd_0003.pdf | ||
| Sol_140L6220Q0086_Amd_0002.pdf | ||
| QUESTIONandANSWER2docx_0002.docx | DOCX document | |
| pfo fence BidSchedule and MaterialsList_0001.xlsx | XLSX spreadsheet | |
| Sol_140L6220Q0086_Amd_0001.pdf | ||
| BidSchedule and MaterialsList.xlsx | XLSX spreadsheet | |
| DeliveryLocationMap.docx | DOCX document | |
| Sol_140L6220Q0086.pdf | ||
| FenceMaterialSpecs.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140L6220Q0086
AMEND 1
QUESTION & ANSWER
1. Q: What is the diameter of the CCA 16.5’ rails, and CCA 16.5’ split rails?
A: 4’’ diameter for all rails.
2. Q: What is the size and description of the wood laydown clips?
A: The wood laydown clips have been removed from the Bid schedule, these are no longer a requirement.