140L6220Q0080 AMD 0005 Question and Answer_0005.docx

DOCX document 16 KB Posted

Attached to
RAWLINS WY SECURITY SYSTEMS Federal contract opportunity
Solicitation number
140L6220Q0080
Issued by
Department of the Interior Bureau of Land Management Wyoming Region

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

140L6220Q0080 Amendment: 0005

1. Does all security & CCTV cabling required to be in conduit between the panel and end of line devices inside the buildings?

Per the Rawlins S.O.W. – Section A.2.4.2 Cable Routing

· Cables are to be routed in conduit where necessary for its protection and concealment from vandalism.

· Cables and wires are to be routed and neatly bundled together.

· No cable or wire will be left hanging or unsupported across ceiling tiles, HVAC ductwork, or pipe insulation. All wire runs must be suspended and secured via plenum rated wires ties or industry approved fasteners.