140L6220Q0080 AMD 0005 Question and Answer_0005.docx
DOCX document 16 KB Posted
- Attached to
- RAWLINS WY SECURITY SYSTEMS Federal contract opportunity
- Solicitation number
- 140L6220Q0080
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L6220Q0080_Amd_0006.pdf | ||
| Sol_140L6220Q0080_Amd_0005.pdf | ||
| Sol_140L6220Q0080_Amd_0004.pdf | ||
| RFO Security System Prebid Tour_0004.pdf | ||
| 140L6220Q0080 AMD 0004 Questions and Answers_0004.docx | DOCX document | |
| Rawlins Field Office Security System Installation Bid Schedule Attachment 1_0003.xlsx | XLSX spreadsheet | |
| Sol_140L6220Q0080_Amd_0003.pdf | ||
| Sol_140L6220Q0080_Amd_0002.pdf | ||
| 140L6220Q0080 AMD 0002 QUESTION AND ANSWERS_0002.docx | DOCX document | |
| Sol_140L6220Q0080_Amd_0001.pdf | ||
| RAWLINS SECURITY SYSTEM FINAL DRAWINGS BID SET 02122020_0001.pdf | ||
| BLM WY RawlinsFieldOfficeSecuritySystemInstallationSOW.docx | DOCX document | |
| Sol_140L6220Q0080.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140L6220Q0080 Amendment: 0005
1. Does all security & CCTV cabling required to be in conduit between the panel and end of line devices inside the buildings?
Per the Rawlins S.O.W. – Section A.2.4.2 Cable Routing
· Cables are to be routed in conduit where necessary for its protection and concealment from vandalism.
· Cables and wires are to be routed and neatly bundled together.
· No cable or wire will be left hanging or unsupported across ceiling tiles, HVAC ductwork, or pipe insulation. All wire runs must be suspended and secured via plenum rated wires ties or industry approved fasteners.