This document is a Draft Bid Schedule for a federal contract opportunity related to stream and wetland meadow restoration. The key details are:

The Bureau of Land Management (BLM) in Utah is seeking a contractor to implement demonstration projects to showcase the use of Zeedyke and Low-Tech Process-Based Restoration (LTPBR) techniques on BLM-administered lands in Rich County, Utah. The bid schedule outlines the various contract line items (CLINs) for the stream restoration and wetland/mesic meadow restoration work, including tasks such as condition assessments, restoration plans, pre/post-monitoring, permitting, materials/equipment provision, and on-site training. The anticipated period of performance is not specified.

The BLM plans to issue a Request for Proposal in late November 2024 and is seeking responses from interested small businesses by November 18, 2024. Respondents should provide information on their relevant experience, capabilities, feasibility of completing the work, and estimated costs. The government anticipates conducting a competitive acquisition and may consider a small business or other socio-economic set-aside.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Stream and Wetland Meadow Restoration Bid Schedule
Base Year (Stream Restoration)CLIN 10Description of WorkPriceOptional Task 1 (Stream Restoration)CLIN 30Description of WorkPriceTasksCLIN 50Description of WorkPriceTasksCLIN 70Description of WorkPrice
1Complete a detailed riparian and geomorphic condition assessment using a variety of tools (e.g., BRAT, RCAT)$ - 01Complete a detailed riparian and geomorphic condition assessment using a variety of tools (e.g., BRAT, RCAT)$ - 0Optional Task 2 (Stream Restoration)1Complete a detailed riparian and geomorphic condition assessment using a variety of tools (e.g., BRAT, RCAT)$ - 0Optional Task 3 (Stream Restoration) BLM will Construct Structures (No Training Required)1Complete a detailed riparian and geomorphic condition assessment using a variety of tools (e.g., BRAT, RCAT)$ - 0
2Complete a restoration plan using LTPBR techniques and principles$ - 02Complete a restoration plan using LTPBR techniques and principles$ - 02Complete a restoration plan using LTPBR techniques and principles$ - 02Complete a restoration plan using LTPBR techniques and principles$ - 0
3Pre and Post Monitoring (e.g., drone flights, aerial imagery, stream surveys, photos)$ - 03Pre and Post Monitoring (e.g., drone flights, aerial imagery, stream surveys, photos)$ - 03Pre and Post Monitoring (e.g., drone flights, aerial imagery, stream surveys, photos)$ - 03Pre and Post Monitoring (e.g., drone flights, aerial imagery, stream surveys, photos)$ - 0
4Restoration Design Plan and Permitting (e.g., stream alteration permits) (Final Submitted to BLM)$ - 04Restoration Design Plan and Permitting (e.g., stream alteration permits) (Final Submitted to BLM)$ - 04Restoration Design Plan and Permitting (e.g., stream alteration permits) (Final Submitted to BLM)$ - 04Restoration Design Plan and Permitting (e.g., stream alteration permits) (Final Submitted to BLM)$ - 0
5Provide materials (e.g., LTPBR handbook and pocket guide) to stakeholders and partners (30 students)$ - 05Provide materials (e.g., LTPBR handbook and pocket guide) to stakeholders and partners (30 students)$ - 05Project Implementation (provide materials (e.g., posts, willow, hydraulic post pounder, etc…) and contractor will build LTPBR structures)$ - 05Final Monitoring Report$ - 0
6Provide on-the-ground training (e.g., 4-days (40 hours) (30 students)$ - 06Provide on-the-ground training (e.g., 4-days (40 hours) (30 students)$ - 06Final Monitoring Report$ - 0CLIN 70 Total$ - 0
7Provide Materials and equipment to complete the on-the-ground training (e.g., posts, willow, hydraulic post pounder, etc…)$ - 07Provide Materials and equipment to complete the on-the-ground training (e.g., posts, willow, hydraulic post pounder, etc…)$ - 0CLIN 50 Total$ - 0CLIN 80Description of WorkPrice
8Final Monitoring Report$ - 08Final Monitoring Report$ - 0CLIN 60Optional Task 2 Stream Restoration Total$ - 0Optional Task 3 (Stream Restoration) BLM will Construct Structures (No Training Required)1Complete a detailed wetland and mesic meadow condition assessment$ - 0
CLIN 10 Total$ - 0CLIN 30 Total$ - 0Optional Task 2 (Wetland and Mesic Meadow Restoration1Complete a detailed wetland and mesic meadow condition assessment$ - 02Complete a restoration plan utilizing Zeedyke techniques and principles$ - 0
2Complete a restoration plan utilizing Zeedyke techniques and principles$ - 03Pre and Post Monitoring (e.g., drone flights, aerial imagery, wetland and mesic meadow surveys, photos)$ - 0
CLIN 20Description of WorkPriceCLIN 40Description of WorkPrice3Pre and Post Monitoring (e.g., drone flights, aerial imagery, wetland and mesic meadow surveys, photos)$ - 04Restoration Design Plan and Permitting (e.g., stream alteration permits) (Final Submitted to BLM)$ - 0
Base Year (Wetland/Mesic Meadow Restoration)1Complete a detailed wetland and mesic meadow condition assessment$ - 0Optional Task 1 (Wetland/Mesic Meadow Restoration)1Complete a detailed wetland and mesic meadow condition assessment$ - 04Restoration Design Plan and Permitting (e.g., stream alteration permits) (Final Submitted to BLM)$ - 05Final Monitoring Report$ - 0
2Complete a restoration plan utilizing Zeedyke techniques and principles$ - 02Complete a restoration plan utilizing Zeedyke techniques and principles$ - 05Project Implementation (e.g., rock, UTVs haul rock to project site, etc…) and contractor will build Zeedyke structures$ - 0CLIN 80 Total$ - 0
3Pre and Post Monitoring (e.g., drone flights, aerial imagery, wetland and mesic meadow surveys, photos)$ - 03Pre and Post Monitoring (e.g., drone flights, aerial imagery, wetland and mesic meadow surveys, photos)$ - 06Final Monitoring Report$ - 0
4Restoration Design Plan and Permitting (e.g., permitting) (Final Submitted to BLM)$ - 04Restoration Design Plan and Permitting (e.g., permitting) (Final Submitted to BLM)$ - 0CLIN 60 Total$ - 0
5Provide materials (e.g., Let the Water do the Work: Induced Meandering, an Evolving Method for Restoring Incised Channels) to stakeholders and partners (30 students)$ - 05Provide materials (e.g., Let the Water do the Work: Induced Meandering, an Evolving Method for Restoring Incised Channels) to stakeholders and partners (30 students)$ - 0
6Provide on-the-ground training (e.g., 4-days (40 hours) (30 students)$ - 06Provide on-the-ground training (e.g., 4-days (40 hours) (30 students)$ - 0
7Provide Materials and equipment to complete the on-the-ground training (e.g., rock, UTVs haul rock to project site, etc…)$ - 07Provide Materials and equipment to complete the on-the-ground training (e.g., rock, UTVs haul rock to project site, etc…)$ - 0
8Final Monitoring Report$ - 08Final Monitoring Report$ - 0
CLIN 20 Total$ - 0CLIN 20 Total$ - 0

CLIN 10 & CLIN 20 Grand Total $ - 0