Amendment_0001_140L5724Q0001_Attachment_05_Q_A_0001.pdf
PDF 111 KB Posted
- Attached to
- Peekaboo Trailhead Expansion
- Solicitation number
- 140L5724Q0001
About this file
This document contains questions and answers related to solicitation number 140L5724Q0001 from the Department of the Interior Bureau of Land Management Utah Region for the Peekaboo Trailhead Expansion project. The period of performance is December 1, 2023 to April 30, 2024, with work to be completed within 45 days of notice to proceed. Fencing was eliminated from the project. A bid bond is required for quotes over $150,000, with payment and performance bonds required over $35,000 and $150,000 respectively. No SWPP, silt fence or straw wattle will be needed due to established native vegetation. Fixed elevations or grading plans will not be provided - the area should generally be graded to a 5% slope. The existing soil and parking lot may be used for subgrade and staging. The existing parking lot and trail will remain open during construction. Quotes must be submitted electronically to the specified contracting staff by the due date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Peekaboo Trailhead Expansion Solicitation: 140L5724Q0001 Questions & Answers
Ref. # Date Method Submitted
Question Answer Posted Amendment #
1 11/7/2023 Email Please clarify the period of performance.
The work can be done anytime during the period of 12/01/2023 ‐ 04/30/2024 but once the Notice to Proceed is issued you have 45 days to complete it. 11/9/2023 001
2 11/7/2023 Email The plans speak of a 2 rail wood fence and gives a detail reference I cannot seem to find anywhere on the plans?
The fencing has been eliminated from this project. Please ignore any reference to any fencing. 11/9/2023 001
3 11/7/2023 Email Will the project need to be bonded only if the price is over 150k or bonded no matter the price?
Bid Bond is required for quotes over $150,000 Payment Bond required for awards over $35,000 Performance Bond required for awards over $150,000 11/9/2023 001
4 11/7/2023 Email I do not see anything in the specs or on the plans about SWPP, silt fence or straw wattle, will these items be required?
No, there is no SWPP plan required on this project. The native variation is well established in this area. 11/9/2023 001
5 11/8/2023 Email
The spec says that the finish grade will be tested with a straight edge and required to be within 1/2" in 10 feet but there is no grading plan with future contours or existing provided‐Will a CAD file be provided with a grading plan so we can meet specified grades? The plan only shows making it slope at 5% and does not give fixed elevations.
Correct, the plan does not have fixed elevations and a CAD file will not be provided. This is for a rural parking lot and the elevations are not critical on this project. Delete paragraph 3.03 B from Section 02233 that references the grade being tested with a straight edge. The existing slope is presently close to 5% slope.
The low and high spots will need to be graded out to insure proper drainage. 11/9/2023 001
6 11/8/2023 Email Will a scarify/compact of the native materials be sufficient to create the subgrade?
Yes, the existing soil is a sandy loam that will compact sufficient for subgrade material. 11/9/2023 001
7 11/8/2023 Email Can we just grade the native materials to create a general 5% slope or will fixed elevations be provided?
Yes, the existing native material can be graded to create a general 5% slope. No elevations will be provided. 11/9/2023 001
8 11/8/2023 Email
There are a large number of trees in the area shown to be improved‐will we have to protect all those trees or is the intent to remove them if they fall inside the pit run boundary?
All trees that need to be protected are on the edge of the parking area. Any trees you are seeing on a topo in the parking area have been removed with mulchers by the government. However, the stumps will need to be removed during the clearing and grubbing procedures. It is recommended if you have additional questions about this topic that you visit the site. 11/9/2023 001
9 11/8/2023 Email Can we use the existing parking lot for staging during construction?
No, the contractor can use the side of the old highway road on the west side of the parking lot. Contractor will be required to allow public to get by their equipment and supplies 11/9/2023 001
10 11/8/2023 Email Will the existing parking lot/trail be open during construction? Yes, the existing parking lot will be open during construction 11/9/2023 001
11 11/8/2023 Email What is the best way to submit the bid and required documentation?
See page 17 of the solicitation under Quotation Submittal…"Quotes must be submitted via email to the contract specialist and contracting officer by the due date and time specified on the cover page of this document." 11/9/2023 001