140L5722Q0022_SOW_and_Specs_1.pdf
PDF 2 MB Posted
- Solicitation number
- 140L5722Q0022
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 140L5722Q0022_Drawings_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Poison Spider Trailhead Access Road Rehabilitation 8/22
STATEMENT OF WORK (SOW) AND TECHNICAL SPECIFICATIONS
FOR
ACCESS ROAD REHABILITATION
AT
POISON SPIDER TRAILHEAD NEAR MOAB, UTAH
AUGUST 2022
SECTION 01009
GENERAL INFORMATION AND REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
Construction shall adhere to the plans, specifications, and this Statement of Work (SOW) unless modified in writing by the Contracting Officer. The Contractor will not be compensated for any modifications unless it receives written authorization from the Contracting Officer to make such modification(s) before performing the work.
A. Description of Work: Contractor shall furnish all labor, equipment, supplies, and materials to perform the following work:
• Hauling and placing untreated base course as specified in plans, specifications, and SOW o Material shall conform with requirements of Federal Highways Standard Specifications FP-14 Section 301 (attached) Contractor shall be responsible for meeting testing requirements of the above section (see FP-14 Table 301-1; attached) o Material shall conform with FP-14 Section 703.05 (attached) o Material shall be graded according to Table 703-2, category D (Base) o Finished gravel shall have a clean, well-graded appearance
• Hauling and placing riprap as specified in plans, specifications, and SOW o Contractor may use onsite boulders as rip rap material as directed by the Contracting
Officer (CO) or Contracting Officer’s Representative (COR)
• Install drainage pipe under paleontological trail crossing o Excavate rock as required to place pipe
The following work shall be considered as bid additives.
1. Improving site drainage as specified in plans, specifications, and SOW. Work includes:
a. Ditch excavation
b. Placing riprap in excavated section
2. Replace existing information kiosk in kind
3. Removing damaged fencing at the north side of the access road entrance
Determination of award for any bid additives is at the sole discretion of the CO. Contractor shall furnish all labor, equipment, supplies, and materials to perform any work required by any awarded bid additives.
B. Period of Performance: Performance period for this contract will be 90 days from Notice to Proceed. Payment for this work shall be in accordance with the bid schedule (see below).
C. Place of Performance: Location – Poison Spider Trailhead and trailhead access road, on the east side of Utah, adjacent to State Route 279, 4 miles south of Hwy 95 (10 miles travel southwest of Moab, UT; see attached map). (38°32'0.25"N, 109°36'27.45"W)
D. Access: Site is accessed via Utah State Route 279, a paved road. Contractor may access the site to the extent required to perform this work during normal working hours (Monday-Friday, 7:30 a.m. to 5:00 p.m. excluding Federal holidays). Contractor may stage equipment in trailhead parking lot.
E. Specific Requirements:
a. Safety and Liability: Government assumes no responsibility for injuries or damages suffered by Contractor, its officers, agents, or employees, while engaged in the performance of this Contract. Contractor agrees to take reasonable measures to provide for the safety and security of its own workforce, and for the safety and security of all others present at the work site while engaged in the performance of this Contract. The contractor shall assume any liability for any injury incurred by contractor personnel while working on site. Construction equipment shall be in good working order and shall be operated safely at all times.
b. Site Cleanup and Restoration: The contractor shall ensure the work site and areas around the work site are free of any debris and materials upon completion of work each day, as well as at the completion of the job. Site cleanup also requires raking out any tracks and cleaning any fluid spills from construction vehicles before final inspection. Contractor shall remove and properly dispose of all materials and equipment at the completion of the job.
c. Warranty: The Contractor warrants that the work performed under this Agreement conforms to the contract requirements and is free from any defect in equipment, material, design, finish, or workmanship performed by or the responsibility of the Contractor. This warranty shall continue for a period of two (2) years from the date of final acceptance. The Contractor shall remedy at the Contractor's expense any loss of or damage to the work product when such loss or damage is incurred as the result of Contractor's failure to conform to contract requirements, any defect in materials, design or workmanship, or the result of Contractor's negligence. The Contractor's warranty with respect to a work product being replaced or repaired shall run for a period of one year from the date that such replacement or repair is accepted
d. DOT Coordination: Contractor to coordinate traffic control and permitting, in advance, with the Utah Department of Transportation (UDOT) to determine any special needs regarding traffic control, signage, and flagging. Online permit required. Permit can be found on UDOT’s Encroachment permits page:
https://udot.utah.gov/connect/business/permits/encroachment-permits/.
1.2 QUALITY ASSURANCE
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference, with the same force and effect as when they were given in full text.
B. Conflict: Where a conflict occurs between reference documents and project specifications, the project specifications shall govern.
1.3 GOVERNMENT-FURNISHED EQUIPMENT AND MATERIALS
A. There are no Government-furnished materials or equipment involved in this work.
1.4 PROJECT/SITE CONDITIONS
A. Field Measurements: Contractor will field-verify locations, measurements, and layout for final placement of untreated base course, fence and rock removal, and drainage features.
B. Environmental Considerations: Contractor shall provide for adequate erosion, air pollution, and excessive noise pollution controls. Contractor shall adhere to all Federal, State, and Local highway load limitations when transporting demolished material.
C. See figures below for illustrations of common site conditions. Images may not represent all pertinent site conditions. Contractor to field-verify all relevant site conditions.
D. Location Map
1.5 SEQUENCING AND SCHEDULING
A. Work Schedule: The schedule shall be submitted at the pre-work conference. As a minimum, the estimated start and completion dates shall be shown in the schedule.
PART 2: PRODUCTS
(There are no applicable requirements.)
PART 3: EXECUTION
3.1 PROJECT MEETINGS
A. Pre-Work Conference:
1. Will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date, and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. The Contractor, any subcontractors, and the persons responsible for coordination of the work shall be present at the meeting.
B. Final Inspection:
1. To be held at the project site, or as determined by the Contracting Officer.
2. Notify the Contracting Officer in writing at least 2 working days before the completion date so the Government can schedule final inspection.
3. The Contractor’s site superintendent shall be present during this inspection.
4. BLM reserves the right to inspect the construction process to ensure project is built to acceptable standards of quality.
3.2 PREPARATION
A. Work Layout: The Government will identify work locations. The Contractor shall exercise care to prevent any disturbance or damage beyond the work limits.
B. Work Limits: Will be established by the Contracting Officer’s Representative.
PART 4: MEASUREMENT AND PAYMENT
4.1 BID SCHEDULE (BASE BID)
A.
ITEM
NO. DESCRIPTION UNIT TOTAL
QTY
UNIT
COST TOTAL COST
1 Mobilization/Demobilization LS 1 $
2 Drainage Pipe (18” dia. CMP galvanized;
16 ga. w/ coup) LF 15
3 Riprap TON 240 $
4 Untreated Base Course (3/4”); 12” depth TON 1905 $
TOTAL
(Base) $_____________
BID SCHEDULE (BID ADDITIVES)
B.
ITEM
NO. DESCRIPTION UNIT TOTAL
QTY
UNIT
COST TOTAL COST
1 Ditch Excavation LF 430 $
2 Replace Existing Information Kiosk LS 1 $
3 Remove existing fencing LS 1
TOTAL
(Additives) $_____________
4.2 BASIS OF PAYMENT
A. Measurement of pay items shall be as listed in the bid schedules.
END OF SECTION
02370-1
INDEX OF SPECIFICATIONS AND TABLES
FP-14 SECTION 301— UNTREATED AGGREGATE COURSES
FP-14 TABLE 301-1— SAMPLING, TESTING, AND ACCEPTANCE REQUIREMENTS
FP-14 SECTION 703.05—SUBBASE, BASE, AND SURFACE COURSE AGGREGATE
FP-14 TABLE 703-2—TARGET VALUE RANGES FOR SUBBASE AND BASE GRADATION
STANDARD
SPECIFICATIONS
FOR CONSTRUCTION OF
ROADS AND BRIDGES
ON FEDERAL HIGHWAY
PROJECTS
FP-14
U.S. Department of Transportation Federal Highway Administration
Federal Lands Highway
DIVISION 300
AGGREGATE AND BASE
COURSES
Section 301
Section 301. — UNTREATED AGGREGATE COURSES
Description
301.01 This work consists of constructing one or more courses of aggregate on a prepared surface.
Subbase and base aggregate grading is designated according to Table 703-2. Surface course aggregate grading is designated according to Table 703-3.
Material
301.02 Conform to the following Subsections:
Subbase, base, and surface course aggregate 703.05 Water 725.01(c)
Construction Requirements
301.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.
After a representative quantity of aggregate is produced, submit proposed target values for the appropriate sieve sizes along with a representative 300-pound (150-kilogram) sample at least 14 days before incorporating the aggregate into the work.
Set target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading.
301.04 Mixing and Spreading. Determine the optimum moisture content according to AASHTO T 180, Method D. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content within 2 percent of the optimum moisture content. Spread and shape the mixture on the prepared surface in a uniform layer.
Do not place the mixture in a layer exceeding 6 inches (150 millimeters) in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 301.05 before placing the next layer. Route hauling equipment uniformly over the full width of the surface to minimize rutting or uneven compaction.
301.05 Compacting. Determine the maximum density of the mixture according to AASHTO T 180, Method D.
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.
Along curbs, headers, walls, and places not accessible to the roller, compact the material with approved tampers or compactors.
Compact each layer to at least 95.0 percent of maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures.
301.06 Surface Tolerance. If grade finishing stakes are required, finish the surface to within ±0.05 feet (±10 millimeters) from staked line and grade elevation.
If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot (3-meter) straightedge. Defective areas are surface deviations in excess of ½ inch (13 millimeters) in 10 feet (3 meters) between two contacts of the straightedge with the surface.
Correct defective areas by loosening the material, adding or removing material, reshaping, and compacting.
301.07 Maintenance. Maintain the aggregate course to the correct line, grade, and cross-section by blading, watering, rolling, or combination thereof until placement of the next course. Correct defects according to Subsection 301.06.
301.08 Acceptance. See Table 301-1 for sampling, testing, and acceptance requirements; including the category for quality characteristics.
Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.05. Other aggregate quality properties will be evaluated under Subsections 106.02 and 106.04.
(a) Aggregate gradation. The upper and lower specification limits are equal to the calculated mean of all test results plus or minus the allowable deviations shown in Tables 703-2 and 703-3, except as follows:
(1) If the calculated mean value for a tested sieve exceeds the maximum gradation value shown in Table 703-2 or 703-3, then the upper specification is equal to the maximum gradation value plus the allowable deviation, and the lower specification is equal to the maximum gradation value minus the allowable deviation.
(2) If the calculated mean value for a tested sieve is less than the minimum gradation value shown in Table 703-2 or 703-3, then the upper specification is equal to the minimum gradation value plus the allowable deviation and the lower specification is equal to the minimum gradation value minus the allowable deviation.
(b) Plasticity index. The upper and lower specification limits for surface courses are shown in Subsection 703.05(c)(3).
Construction of untreated aggregate courses will be evaluated under Subsections 106.02 and 106.04.
Measurement
301.09 Measure the Section 301 pay items listed in the bid schedule according to Subsection 109.02 and the following as applicable:
When measuring aggregate by the cubic yard (cubic meter), measure in place.
When measuring aggregate by the square yard (square meter), measure the length horizontally along the centerline of the roadway. Measure the width horizontally to include the top of aggregate width, including designed widenings.
Payment
301.10 The accepted quantities will be paid at the contract price per unit of measurement adjusted according to Subsection 106.05 for the Section 301 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
Table 301-1 Sampling, Testing, and Acceptance Requirements
Material or Product
(Subsection)
Type of Acceptance (Subsection)
Characteristic Category Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Remarks
Source Aggregate quality (703.05(a)
(b) (c))
Measured and tested for conformance (106.04 & 105)
LA abrasion (coarse)
− AASHTO
T 96
1 per type & source of material
Source of material
Yes Before using in work
Not required when using
Government-provided sources
Soundness using sodium sulfate (coarse & fine)
− AASHTO
T 104
Fractured faces
− ASTM
D5821
Liquid limit − AASHTO R58 & T 89, Method A
Surface course aggregate
(703.05(c))
" Plasticity index − AASHTO R 58, T 89, & T 90
" Crusher belt or after processing
Table 301-1 (continued) Sampling, Testing, and Acceptance Requirements
Material or Product
(Subsection)
Type of Acceptance (Subsection)
Characteristic Category Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Remarks
Source (continued) Subbase, base, or surface course aggregate (703.05(b) (c))
Process control
(153.03)
Gradation − AASHTO T 11 & T27
2 per day per stockpile (minimum)
Crusher belt
No 24 hours
Not required when using a pre-crushed commercial source Fractured faces − ASTM
D5821
Surface course aggregate
(703.05(c))
" Plasticity index − AASHTO R 58, T 89, & T 90
" Crusher belt or after processing
Production Subbase course
Grading A & B
Statistical (106.05)
Gradation AASHTO T 27 & T 11
1 per 1000 tons
(900 metric tons)
From windrow or roadbed after processing
Yes 4 hours
No. 4
(4.75 mm) I
No. 200 (75µm)
I
Other specified sieves
II
Table 301-1 (continued) Sampling, Testing, and Acceptance Requirements
Material or Product
(Subsection)
Type of Acceptance (Subsection)
Characteristic Category Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Remarks
Production (continued) Base course Grading C, D, & E
Statistical (106.05)
Gradation AASHTO T 27 & T 11
1 per 1000 tons
(900 metric tons)
From windrow or roadbed after processing
Yes 4 hours
⅜ inch
(9.5 mm) I
No. 4 (4.75 mm)
I
No. 200 (75µm)
I
Other specified sieves
II
Subbase & base course Grading A, B, C, D, & E
Measured and tested for conformance (106.04)
Liquid limit − AASHTO R 58 & T 89, Method A
1 per 1000 tons
(900 metric tons)
From windrow or roadbed after processing
Yes 4 hours
Moisture-density
(max density)
− AASHTO
T 180, Method D (1)
1 per type & source of material
Stockpile or production output
Density − AASHTO T 310 or other approved procedures
1 per 500 tons
(450 metric tons)
In-place after compaction
No End of shift
Moisture content
(in-place)
Table 301-1 (continued) Sampling, Testing, and Acceptance Requirements
Material or Product
(Subsection)
Type of Acceptance (Subsection)
Characteristic Category Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Remarks
Production (continued) Surface course aggregate
Statistical (106.05)
Gradation AASHTO T 27 & T 11
1 per 1000 tons
(900 metric tons)
From windrow or roadbed after processing
Yes 4 hours
No. 4 (4.75 mm)
I
No. 40 (4.75 µm)
I
No. 200 (75 µm)
I
Other specified sieves
II
Plasticity index I AASHTO R 58, T 89, & T 90
Measured and tested for conformance (106.04)
Moisture-density
(max density)
− AASHTO
T 180, Method D (1)
1 per type & source of material
Stockpile or production output
Yes " −
Density − AASHTO T 310 or other approved procedures
1 per 500 tons
(450 metric tons)
In-place after compaction
No End of shift −
Moisture content
(in-place)
Fractured faces
− ASTM
D5821
1 per 1000 tons
(900 metric tons)
From windrow on roadbed after processing
Yes 4 hours
Table 301-1 (continued) Sampling, Testing, and Acceptance Requirements
Material or Product
(Subsection)
Type of Acceptance (Subsection)
Characteristic Category Test Methods Specifications
Sampling Frequency
Point of Sampling
Split Sample
Reporting Time
Remarks
Finished Product Subbase, base, and surface course
Measured and tested for conformance (106.04)
Surface tolerance & grade
− Subsection 301.06
Determined by the CO
Surface of final course
No Before placement of next layer or as requested
(1) Minimum of 5 points per proctor.
DIVISION 700
MATERIAL
Section 703
Section 703. — AGGREGATE
703.01 Fine Aggregate for Concrete. Furnish sand conforming to AASHTO M 6, Class B, except as amended or supplemented by the following:
(a) Material passing No. 200 (75-µm) sieve, 3.0 percent max.
AASHTO T 11
(b) Alkali-silica reactivity. Test the aggregate for alkali silica reaction and conform to one of the following (1) through (5):
(1) Alkali-silica reactivity, ASTM C1260 ≤ 0.10 percent at 16 days after casting
(2) Alkali-silica reactivity, ASTM C1260 0.11 percent to 0.20 percent at 16 days after casting
And one of the following examinations:
(a) Petrographic examination of aggregates, Favorable report for use ASTM C295, performed within 1 year from time of submittal
(b) Petrographic examination of hardened Favorable report for use concrete, ASTM C856, performed on ASTM C1260 specimens after test
(3) Alkali-silica reactivity with cementitious ≤ 0.10 percent at 16 days after casting material, ASTM C1567, performed on approved mix design mass percent combinations. Do not use lithium compounds as mitigation measures
(4) Alkali silica reaction, ASTM C1293 < 0.04 percent at 12 months
(5) Alkali-silica reaction with cementitious material, < 0.04 percent at 24 months ASTM C1293, performed on approved mix design mass percent combinations
For lightweight fine aggregate, conform to AASHTO M 195.
703.02 Coarse Aggregate for Concrete. Conform to AASHTO M 80, Class A, except as amended or supplemented by the following:
(a) Los Angeles abrasion, AASHTO T 96 40 percent max.
(b) Grading, AASHTO M 43 All sizes, except Size Numbers 8, 89, 9, or 10
(c) Alkali-silica reactivity See Subsection 703.01(b)
For bridge decks or surface courses, do not use aggregates known to polish or carbonate aggregates containing less than 25 percent by mass of insoluble residue as determined by ASTM D3042.
For lightweight coarse aggregate, conform to AASHTO M 195.
703.03 Granular Backfill. Furnish aggregate for the following installations.
(a) Underdrain pipe with geotextile. Furnish granular backfill conforming to AASHTO M 80, Class E and AASHTO M 43, Size Number 3, 4, 5, 57, 67, or 7.
(b) Underdrain pipe without geotextile. Furnish granular backfill conforming to AASHTO M 6, except the soundness test is not required.
703.04 Reserved.
703.05 Subbase, Base, and Surface Course Aggregate.
(a) General. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Los Angeles abrasion, AASHTO T 96 50 percent max.
(2) Soundness of aggregate using sodium sulfate, 12 percent loss max.
AASHTO T 104 (5 cycles)
(3) Durability index (coarse), AASHTO T 210 35 min.
(4) Durability index (fine), AASHTO T 210 35 min.
(5) Fractured faces, ASTM D5821 50 percent min.
(6) Without organic matter and lumps or balls of clay.
(b) Subbase or base aggregate. In addition to Subsection 703.05(a), conform to the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
Table 703-2 Target Value Ranges for Subbase and Base Gradation
Sieve Size Percent by Mass Passing Designated Sieve (AASHTO T 27 and T 11) Grading Designation
A (Subbase) B (Subbase) C (Base) D (Base) E (Base) 2½ inch (63 mm) 100(1) 2 inch (50 mm) 97 – 100(1) 100(1) 100(1)
1½ inch (37.5 mm) 97 – 100(1) 1 inch (25 mm) 65 – 79 (6) 80 – 100 (6) 100(1) ¾ inch (19 mm) 64 – 94 (6) 86 – 100 (6) 100(1)
½ inch (12.5 mm) 45 – 59 (7) ⅜ inch (9.5 mm) 40 – 69 (6) 51 – 82 (6) 62 – 90 (6) No. 4 (4.75 mm) 28 – 42 (6) 40 – 60 (8) 31 – 54 (6) 36 – 64 (6) 36 – 74 (6) No. 40 (425 µm) 9 – 17 (4) 12 – 26 (4) 12 – 26 (4) No. 200 (75 µm) 4.0 – 8.0 (3) 4.0 – 12.0 (4) 4.0 – 7.0 (3) 4.0 – 7.0 (3) 4.0 – 7.0 (3)
(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviation (±) from the target values.
(c) Surface course aggregate. In addition to Subsection 703.05(a), conform to the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89, Method A 35 max.
(3) Plasticity index, AASHTO T 90 10±3
Do not furnish material that contains asbestos fibers.
Table 703-3 Target Value Ranges for Surface Course Gradations Sieve Size Percent by
Mass Passing Designate Sieve
(AASHTO T 27 & AASHTO T 11)
1 inch (25 mm) 100(1)
½ inch (12.5 mm) 70 – 80 (5)
No. 4 (4.75 mm) 40 – 50 (7)
No. 10 (2.0 mm) 25 – 40 (6)
No. 40 (425 µm) 15 – 25 (5)
No. 200 (75 µm) 8.0 – 14.0 (4)
(1) Statistical procedures do not apply.
( ) The value in the parentheses is the allowable deviation (±) from the target values.
sjjohnson Highlight sjjohnson Highlight sjjohnson Highlight sjjohnson Highlight sjjohnson Highlight sjjohnson Highlight sjjohnson Highlight
| SOW - Poison Spider Trailhead rehabilitation Final.pdf |
| PART 1 - GENERAL |
| Poison Spider access road specs.pdf |
| Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects |
| DIVISION 300 AGGREGATE AND BASE COURSES |
| Section 301. — UNTREATED AGGREGATE COURSES |
| DIVISION 700 MATERIAL |
| Section 703. — AGGREGATE |
File details come from the government source that posted it. Updated .