Amendment_01_-_140LO5721Q0040_JNM_Dino_Replicas_Q_A_0001.pdf
PDF 62 KB Posted
- Solicitation number
- 140L5721Q0040
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_02_-_Question_Addressing_Scale_0002.pdf | ||
| Sol_140L5721Q0040_Amd_0002.pdf | ||
| Sol_140L5721Q0040_Amd_0001.pdf | ||
| Sol_140L5721Q0040.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140L5721Q0040 JNM Dinosaur Replicas
Questions and Answers
Q1: Is our pricing for delivery and off load with install by the park?
A1: Correct. Install will be completed by the BLM. Pricing needs to include the delivery and the off-loading of the sculptures at the Jurassic National Monument.
Q2: Are we to include rigging of the statues in place? Without seeing the site and access this is difficult to price?
A2: The sculptures will be set in place by the BLM.
Q3: The sizes are specific within 6” but don’t appear to be full size replicas. Do you have a scale or a pose these sizes were taken from? Can you provide images?
A3: We need them scaled down, but there is not a set scale. The dimensions were taken from known specimens on the market. BLM can provide images. But the pose needs to be sturdy due to the environmental elements and the fact that children may climb on the replicas.
Q4: Will there be footings preformed for these statues?
A4: Footings will be provided by the BLM. We will need specific dimensions of footings and detailed installation instructions a few weeks prior to the delivery of the sculptures.
Q5: Do we allow for hardware to support and attach these statues to footings by others?
A5: Yes.
Q6: These are not sculptures “off the shelf” but have to be modeled and fabricated. Can the proposal include a SOV with progress payments at pre-approved benchmarks rather than the pay upon delivery?
A6: Yes.
Changes to the SOW are as follows:
Under Section III we state the contractor will install sculptures in coordination with the BLM. This is changed to BLM will install the sculptures and the contractor will provide specific dimensions of footings and detailed installation instructions no less than 4 weeks prior to the delivery of the sculptures.
Under Section VIII it states that no partial payments will be made. This is changed to allow for partial payments. Contractor is to provide proposed payment schedule.
File details come from the government source that posted it. Updated .