This is Amendment 0001 to Solicitation 140L4326Q0120, issued by the Bureau of Land Management (BLM) Roseburg District on September 15, 2026, with an effective date of September 15, 2026. The amendment is not extended and includes answers to contractor questions submitted on September 30, 2026, regarding the Tioga Bridge Rehabilitation project in Roseburg, Oregon.

The solicitation is for one firm fixed price construction contract with a performance period of October 22, 2026 to January 5, 2027. The bid schedule consists of two line items: CLIN 0001 for Mobilization (lump sum) and CLIN 0002 for Coating and Full Containment System (lump sum). Key contractual requirements include developing and submitting a Spill Prevention, Control, and Countermeasure (SPCC) Plan compliant with 40 CFR Part 112 for government approval prior to work initiation. Work operations are restricted to the period between October 22, 2026 and January 5, 2027 for full bridge closure, with limited site use permitted October 14-21, 2026 for staging and material storage. Additional constraints include no work one-half hour before sunrise or after sunset, no weekend work without written approval, snow removal at contractor expense, and compliance with Manual on Uniform Traffic Control Devices (MUTCD) for road closure devices. The current wage determination #OR20260001 dated July 30, 2026 applies, with potential updates provided by award if posted to sam.gov before contract award. The amendment also clarifies that the pricing schedule structure addresses prior contractor questions regarding the scope of resealing, containment, coating, and waste-control work incorporated into the two lump sum contract line items.

View the file

Other files

File Type Posted
Sol_140L4326Q0120.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Matthew Duane

See continuation page

BLM OR-ST OFC PROC MGMT BR(OR952)

1220 SW 3rd Avenue, 12th Floor

PORTLAND OR 97204

BLM OR STATE OFC PROC MGMT-OR952

1220 SW 3rd Avenue, 12th Floor

PORTLAND OR 97204

LHA

LHA

140L4326Q0120

09/15/2026

09/15/2026

1 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140L4326Q0120/0001

Tioga Bridge Rehabilitation, Roseburg, Oregon

The purpose of this amendment is to include answers to contractor questions submitted on

Wednesday September 30, 2026.

Period of Performance: 10/22/2026 to

01/05/2027

140L4326Q0120 Tioga Bridge Rehabilitation

Questions and Answers

Q1. The controlling bid schedule. Section B shows Mobilization and Aggregate Surfacing, while the continuation sheet identifies Tioga Bridge resealing. We did not locate a priced CLIN for the principal resealing, containment, coating, and waste-control scope. Please identify how all rehabilitation work, options, and schedule-of-values items are to be priced.

A1. See updated schedule B attached. Pricing schedule consists of CLIN 0001, mobilization and CLIN 0002, coating and full containment system as lump sums.

Q2. The controlling access, staging, closure, and performance dates; the requirements refer to September 1–November 15 and October 22–January 5 closure windows.

A2. See attached updated “section 108 Prosecution and Progress “of the specifications for updated dates. Please note, dates may be subject to change.

Q3. Whether the latest applicable construction wage determination will be provided by amendment.

A3. The most current wage determination #OR20260001 dated 07/30/2026 is attached to solicitation 140L4326Q0120. If an updated wage determination is posted on sam.gov prior to award, the updated wage determination will be included with the award.

Tioga Bridge Rehabilitation, Roseburg, Oregon SOLICITATION NO. 140L4326Q0120 BLM Roseburg District Page 4 of 49

SECTION B – BID SCHEDULE

This requirement is for one (1) Firm Fixed Price Construction contract for the Tioga Bridge Rehanilitation in Roseburg, Oregon.

BASE

Item no. Item Description Quantity Unit of

Measure Unit Price Total

0001 Mobilization AR LS $ $ 0002 Coating and Full Containment

System

AR LS $ $

GRAND TOTAL – Base plus Options

*Estimated Quantity LS = Lump Sum

PERFORMANCE PERIOD: See Section F below.

THIS SOLICITATION IS OPEN MARKET NO RESTRICTIONS.

(End of Section B)

SECTION C – SPECIFICATIONS/DRAWINGS

See attachements for specifications/drawings

PART 2: PRODUCTS

A. Spark Arresters: Shall meet the requirements of the State of Oregon’s regulations.

PART 3: EXECUTION

3.01 HAZARDOUS MATERIAL CONTAINMENT/CLEANUP

A. During contractor operations on lands managed by the BLM, in event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, the Contractor shall immediately implement the SPCC plan as referenced herein and notify the on-site Government Contract Representative (COR or PI). The Government Representative will initiate the District’s Hazardous Materials Contingency Plan and/or Spill Containment Plan reporting requirements. The Government Representative will remain on scene until relieved by the District Hazardous Materials Management Coordinator (HMMC) or his/her representative.

B. Spill Prevention, Control, and Countermeasure Plan (SPCC): The Contractor shall develop an SPCC Plan as defined under 40 CFR Part 112. The SPCC Plan will be reviewed and accepted by the Contracting Officer prior to initiating project work. The SPCC Plan shall, as a minimum, contain the following information:

Special Contract Requirements Roseburg District, Oregon Tioga Bridge Rehabilitation Bureau of Land Management

Section 108. – PROSECUTION AND PROGRESS

108.01 Commencement, Prosecution, and Completion of Work. Add the Following:

Limit operations as follows:

• Full closure of the Tioga Pedestrian Bridge is permitted between October 22, 2026 and January 05, 2027. Contractor shall implement road closure devices to restrict public access to the site during this period. Road closure devices shall be in conformance with the Manual on Uniform Traffic Control Devices (MUTCD).

• Limited use of the recreation site between October 14, 2026 and October 21, 2026 for staging and storage of materials is permitted. Storage of materials and equipment shall be performed in a manner that minimizes impacts to the recreation site users. Submit a plan to the CO detailing proposed areas for staging equipment and materials for approval. Do not begin staging or storage of materials until the plan is approved by the CO.

• Snow removal, if needed shall be the Contractor’s option and expense.

• Perform no on site work ½ hour before sunrise or ½ hour after sunset.

• Perform no on site work on Saturdays or Sundays, except as approved in writing by the CO.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

Updated Schedule B_10.7.26.pdf
CHANGES AND CHANGED CONDITIONS
52.240-93 – BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (MAR 2026 RFO Overhaul)
52.222-55 MINIMUM WAGES FOR CONTRACTOR WORKERS UNDER EXECUTIVE ORDER 14026 (MAY 2026-RFO Overhaul)
(a) Definitions. As used in this clause—
Biobased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including re...
USDA-designated product category a generic grouping of biobased products that are listed by USDA in a procurement guideline (7 CFR part 4270) and for which USDA has provided minimum biobased content standards (see https://www.biopreferred.gov/resource...
(b) Requirement. The Contractor shall—
(1) Report to https://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any biobased products in USDA-designated product categories purchased by the Contractor during the previous Government fiscal year, bet...
(2) Submit this report no later than—
(i) October 31 of each year during contract performance; and
(ii) At the end of contract performance.
(End of clause)
(2) An energy-efficient product or low standby power device (42 U.S.C. 8259b) (10 CFR part 436, subpart C) ( https://www.energy.gov/eere/femp/search-energy-efficient-products, https://www.energystar.gov/products?s=mega, and https://www.energy.gov/femp...
(3) A biobased product that meets the content requirements of the USDA under the BioPreferred® program (7 U.S.C. 8102) (7 CFR Part 4270) ( https://www.biopreferred.gov/).
(4) A substance identified in the EPA’s Significant New Alternatives Policy (SNAP) program as a safe alternative to an ozone-depleting substance (42 U.S.C. 7671l) (40 CFR part 82, subpart G) ( https://www.epa.gov/snap/unacceptable-and-acceptable-subst...
(b) Requirements. The Government has identified in the statement of work or elsewhere in the contract the sustainable products that are required during the performance of this contract. The Contractor shall ensure that it provides sustainable product...
(1) Delivered to the Government;
(2) Furnished for use by the Government;
(3) Incorporated into the construction of a public building or public work; or
(c) Furnished for use in performing services under this contract, where the cost of the products is a direct cost to this contract.
(End of Clause)
52.225-9 – BUY AMERICAN–CONSTRUCTION MATERIALS (OCT 2022)
52.226-7 DRUG-FREE WORKPLACE (MAY 2024)
52.228-13 – ALTERNATIVE PAYMENT PROTECTIONS (JUL 2000)
52.232-39 – UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
(End of clause)
(End of provision)
52.222-5 – CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)
52.225-10 – NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
A06 Special Contract Requirements Updated Section 108.pdf
3. Treatment Classification
3.1 Public Contact Timber (Linseed Oil and Pine Tar Treatment)
3.2 Non-Public Contact Timber (Copper Naphthenate Treatment)
4. Surface Preparation
4.1 General
4.2 Protection
5. Preservative Treatment Application
5.1 Copper Naphthenate
5.2 Linseed Oil and Pine Tar Mixture
6. Environmental and Safety Requirements
6.1 Environmental Protection
6.2 Public Safety
7. Quality Control and Submittals
8. Cleanup and Final Acceptance
109.03 Weighing Procedures and Devices.
Section 151. - MOBILIZATION
Payment
Pay Item Pay Unit
Section 156. – PUBLIC TRAFFIC
DIVISION 550
BRIDGE CONSTRUCTION
Section 563. — COATING
563.01
563.02
563.03 Qualifications.
563.04 Submittals.
563.05 General.
563.06 Protection of Public, Property, and Workers.
563.07 Containment System, Coating Removal, and Waste Disposal.
563.08 Worker Protection Plan.
563.09 Lumber and Timber.
563.10 Acceptance.
563.11
563.12

File details come from the government source that posted it. Updated .