This is Amendment 0001 to solicitation 140L4326Q0042, issued by the Bureau of Land Management (BLM) Oregon-Southern Idaho Office Procurement Management Branch on March 24, 2026. The amendment responds to a Request for Information (RFI) and provides clarifications regarding a pavement crack maintenance and repair project with a period of performance from May 1, 2026 to October 31, 2026.

The amendment addresses six RFI inquiries: estimated crack quantity in linear feet per mile, average pavement width, crack types and widths expected, routing requirements versus blow-and-go acceptability, traffic control requirements, and a map of the place of performance. The government response indicates that crack quantity, pavement width, and crack type details are to be determined by the contractor during their assessment. A map with red-highlighted sections showing designated starting and stopping points is attached. All cracks must be thoroughly cleaned of vegetation and debris prior to maintenance work. The contractor is responsible for providing traffic control measures, including two certified flaggers and signage compliant with MUTCD standards. Offerors must acknowledge receipt of this amendment prior to the hour and date specified in the original solicitation by completing the form and returning it, acknowledging receipt on each copy of their offer, or submitting a separate letter or electronic communication referencing the solicitation and amendment numbers. Failure to acknowledge receipt may result in offer rejection.

View the file

Other files for this federal contract opportunity

Other files attached to MIDDLE CK PREVENTATIVE PAVEMENT MAINT CB, newest first.
File Type Posted
Middle_cr_crack_seal_0001.pdf PDF
Sol_140L4326Q0042.pdf PDF
B03_Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Matthew Duane

See continuation page

BLM OR-ST OFC PROC MGMT BR(OR952)

1220 SW 3rd Avenue, 12th Floor

PORTLAND OR 97204

LHA

140L4326Q0042

03/24/2026

03/24/2026

1 2

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140L4326Q0042/0001

Amendment one (1) is issued in response to an

RFI. The RFI is below:

1. What is the estimated crack quantity (LF per mile)

2. What is the average pavement width (ft)

3. Crack types and widths expected

4. Is routing required or blow-and-go acceptable?

5. Will traffic control be required?

6. Can you provide a map of the place of performance?

The response from the end user is as follows:

a. Map is attached. Please note that the red highlighted sections indicate the designated starting and stopping points for the project.

Regarding your inquiries about crack types, estimated quantities, and average pavement width, these details are to be determined by the contractor during their assessment. It will be necessary to thoroughly clean all cracks of vegetation and debris prior to any maintenance work.

b. For traffic control, the contractor is responsible for providing appropriate measures, which include employing two certified flaggers and installing proper signage in full compliance with MUTCD standards.

Period of Performance: 05/01/2026 to

10/31/2026

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .