About this file
This document is an amendment (Amendment 0001) to a solicitation (Solicitation No. 140L4324Q0125) issued by the Bureau of Land Management (BLM) Oregon-Washington region for the Wildwood Recreation Site Parking Lot Striping project in Clackamas County, Oregon. The purpose of the amendment is to replace the original SF-1442 form and Section C of the solicitation with updated versions that incorporate answers to questions received during the site visit and as requests for information.
The project involves parking lot striping and symbol placement at the Wildwood Recreation Site. It is a total small business set-aside with a North American Industry Classification System (NAICS) code of 237310 and a small business size standard of $45.0 million. The estimated magnitude of the construction project is between $25,000 and $100,000. Offers are due by August 12, 2024 at 2:00 PM PDT. The contractor shall begin performance within 12 calendar days after award and complete the work within 60 calendar days. A payment bond is required per clause 52.228-13.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L4324Q0125_Amd_0001.pdf | ||
| B08_Drawings_Wild_Wood_attachment.pdf | ||
| Sol_140L4324Q0125.pdf | ||
| B08_Solicitation_140L4324Q0125_WildWoodParkingLot.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
LHA
The purpose of Amendment 0001 is for the following:
1. SF-1442 - To address questions received as requests for information by removing and replacing the SF-1442 in its entirety with the attached SF-1442
2. Section C - To incorporate answers to questions received as requests for information and at the site visit by removing and replacing Section C in its entirety with the attached Section C.
The due date for submission of proposals remains unchanged: 8/12/2024 at 2 p.m. PDT.
BUREAU OF LAND MANAGEMENT
OREGON STATE OFFICE
1220 SW 3RD AVENUE
PORTLAND, OREGON 97204
40658211
140L4324Q0125
07/10/2024
Anita MacAuley
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040658211
BLM OR-ST OFC PROC MGMT BR(OR952)
1220 SW 3rd Avenue, 12th Floor
PORTLAND OR 97204
LHA
Tiffany Eckert, teckert@blm.gov and
Anita MacAuley, amacauley@blm.gov and blm_or_so_952_mail@blm.gov
Tiffany Eckert
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
503-808-6493
140L4324Q0125
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 180 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10 Alt 1
08/12/2024
NSN 7540-01-155-3212
x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d) x
3. DATE ISSUED
07/10/2024
Wildwood Parking Lot Striping, Welches, Oregon, in Clackamas County, Oregon for BLM
Northwest Oregon District
THE ESTIMATED MAGNITUDE OF CONSTRUCTION PROJECT IS BETWEEN $25,000.00 AND $100,000.00
This acquisition is a total small business set aside, and the North American Industry Classification System (NAICS) code is 237310 and the small business size standard is $45.0 million.
Proposals between $35,000 and $150,000 require a payment bond per Clause 52.228-13
Company Name: _______________________________________________________
SAM UEI: ____________________________________________________________
Point of Contact Name: ______________________________________________
Email: ______________________________________________________________
Phone Number: _______________________________________________________ x
Amendment 0001 - see changes in red font
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Anita Macauley
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 49
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140L4324Q0125
00010 Wildwood Parking Lot Striping
Product/Service Code: Z1LZ
Product/Service Description: MAINTENANCE OF
PARKING FACILITIES
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment 0001 – SEE CHANGES IN RED FONT Wildwood Recreation Site Parking Lot Striping, Welches Oregon SOLICITATION NO. 140L4324Q0125 BLM Northwest Oregon District Page 4 of 49
SECTION C – SPECIFICATIONS/DRAWINGS
See Description/Specification attachment
Attachments to Section C
ATTACHMENT PAGES
Specifications 19
Brand Name or Equal Specifications Salient Features 1
Answers to Questions 1
PART 2: PRODUCTS
Shall meet the requirements of the State of Oregon’s regulations.
PART 3: EXECUTION
3.01 HAZARDOUS MATERIAL CONTAINMENT/CLEANUP
A. During contractor operations on lands managed by the BLM, in event of a release as defined in Oregon Administrative Rules (OAR), Chapter 340, Division 142, Oil and Hazardous Materials Emergency Response Requirements, the Contractor shall immediately implement the SPCC plan as referenced herein and notify the on-site Government Contract Representative (COR or PI). The Government Representative will initiate the District’s Hazardous Materials Contingency Plan and/or Spill Containment Plan reporting requirements. The Government Representative will remain on scene until relieved by the District Hazardous Materials Management Coordinator (HMMC) or his/her representative.
B. Spill Prevention, Control, and Countermeasure Plan (SPCC): The Contractor shall develop an SPCC Plan as defined under 40 CFR Part 112. The SPCC Plan will be reviewed and accepted by the Contracting Officer prior to initiating project work. The SPCC Plan shall, as a minimum, contain the following information:
1. Response Priorities
2. Contractor Representative in Charge
3. Duties of Contractor Personnel
4. Contractor Emergency Response Procedures
5. Contents of Spill Containment Kit (SCK)
6. Spill Response Diagram
Upon request, an example of a SPCC may be obtained from the District Environmental Protection Specialist for Hazardous Materials.
C. Spill Containment Kit (SCK): The Contractor shall have a SCK, as described in the SPCC, on-site during any operation and provide training to employees on how components of the SCK are used. The SCK must be designed for use with petroleum products, and must contain, as a minimum, the following items:
1. Two Bales (4 Booms/Bale, of 8" dia. X 10’ length Oil-only Absorbent Booms)
Amendment 0001 – SEE CHANGES IN RED FONT Wildwood Recreation Site Parking Lot Striping, Welches Oregon SOLICITATION NO. 140L4324Q0125 BLM Northwest Oregon District Page 5 of 49
2. Two Bales (100 Pads/Bale, of Oil-only Absorbent Pads, minimum of 17"x19"x1/4")
3. One Oil-only Absorbent Sweep (minimum of 18" dia. X 100' length)
4. One Floating On-Water Containment Boom (minimum 18” width x 100’ length) (only required for in-stream or riparian work within 50 feet or less of a waterway.)
5. Gloves (PVC and Latex), Goggles, and Garbage Bags sufficient to contain soiled absorbents.
D. The Contractor shall implement the Emergency Response Actions described in the SPCC plan. Those actions include, but are not limited to, immediate action to protect employee health and safety, immediate action to stop the flow of product from the equipment, removal of equipment from the waterway if required and/or possible, deployment of the absorbent booms and pads downstream from the equipment, and any other immediate action as specified by Federal and/or State On-Scene Coordinators or his/her representative. The Contractor shall be responsible for cleanup/removal and proper disposal of contaminated materials from the site.
E. If the HMMC determines that additional resources are needed, the HMMC will implement the District’s Hazardous Materials Contingency Plan and the District Spill Containment Plan. The Contractor may be responsible for any or all costs associated with this level of effort. The amount of actual damage will be deducted by the Government from the amount due the Contractor prior to final payment.
(End of Section C)
Amendment No. 0001 Wildwood Parking Lot Striping, Clackamas County, Oregon Solicitation No. 140L4324Q0125 BLM Northwest Oregon District Page 1 of 1
Questions & Answers
Government responses/answers to Contractor questions posed during the site visit on 07/18/2024
Q1: Is contractor to power wash just where the striping/symbols are to go, or is contractor to power wash all of the parking lot?
A1: Only pressure wash where the striping/symbols are to go. In the specifications on page 1 of 19 under Description of Work, the contract states, “The base work includes sweeping or pressure washing pavement to be striped or receive symbols…” Also on the Drawing Set on page 8 of 8 in the Notes section, the contract states, “If there is any vegetation (i.e. moss) growing on the pavement where symbols are to be placed, contractor shall power wash or sweeper the area before any painting is performed…”
Q2: When can this project be done?
A2: In the specifications on page 1 of 19 under Description of Work, the contract states, “Contractor's use of premises is limited only by Government right to perform work or to retain other Contractor’s on portions of Project. Contractor shall coordinate with the COR and on-site BLM manager for parking lot closures; site will still be open to the public during construction, only one parking lot can be painted at a time unless prior permission is given in writing by CO. Parking lot shall be marked closed to public by sunset the day before and 24 hours after painting work is complete”.
Q3: Are all requested symbols existing?
A3: Some of the symbols exist and some will be new. On the Drawing Set on pages 3 through 7 in the Notes section, the contract states, “If striping or symbol on plans do not exist on site, contractor to work with COR on placement location.”
Answers to questions received as Requests for Information submitted in writing no later than 07/25/2024, 2:00 PM Pacific Time.
Q4: The Standard Form 1442 states that the Contractor is not required to furnish any bonds – however, the "52.228-2 ADDITIONAL BOND SECURITY" clause has been incorporated by reference into the solicitation. Does this work require that the Contractor furnish any bonds?
A4: In accordance with clause 52.228-13 – Alternative Payment Protections (JUL 2000), provided in full text in Section I of the solicitation, the contractor shall submit a payment bond.
| B09 Amd1 SF30 Print DRAFT.pdf |
| B09 Amd1 A1 SF1442.pdf |
| B09 AMD C.pdf |
| B09 Amd1 Qs.pdf |
| 2024-07-26T11:45:49-0700 | |
| ANITA MACAULEY |
File details come from the government source that posted it. Updated .