B09_amend3_QUESTIONS_AND_ANSWERS_0003.docx

DOCX document 153 KB Posted

Attached to
INTERIM FACILITY MOVING SERVICE Federal contract opportunity
Solicitation number
140L4324Q0101
Issued by
Department of the Interior Bureau of Land Management Oregon-Washington

About this file

This document is a Questions and Answers (Q&A) amendment related to a federal contract opportunity for an Interim Facility Moving Service. The contract is being solicited by the Department of the Interior Bureau of Land Management Oregon-Washington.

The key details include:

  • The current location has 22 staff and is 12,800 square feet (6,100 sq ft office, 6,700 sq ft warehouse)
  • The contractor will be required to move cabinets containing flammable/hazardous materials, but not the materials themselves
  • No forklift or electrical/data cable work is required
  • There are 2 pallets of seed weighing 1,500 lbs each that need to be moved
  • No bid bond or payment/performance bond is required
  • The contractor must have liability insurance per the contract requirements
  • Payment will be made in full upon completion and acceptance of the work
  • The contractor does not need an Oregon Department of Transportation household goods mover license
  • There are no height restrictions for vehicles, and a federal employee will be on site during the move

View the file

Other files for this federal contract opportunity

Other files attached to INTERIM FACILITY MOVING SERVICE, newest first.
File Type Posted
B09_amend3_Detailed_BLM_Move_Inventory_0003.pdf PDF
B09_amend3_Tillamook_office_loading_dock_0003.pdf PDF
Sol_140L4324Q0101_Amd_0003.pdf PDF
Sol_140L4324Q0101_Amd_0002.pdf PDF
A06_Warehouse_1_0002.jpg JPG image
Sol_140L4324Q0101_Amd_0001.pdf PDF
amend1_Tillamook_Facility_RFQ_EqualOrLessThanSAT_0001.docx DOCX document
Sol_140L4324Q0101.pdf PDF
A06_Attachment_1_-_Photos_(1).docx DOCX document
B03_WD_2015-5577_Rev__23.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT #3 – VENDOR QUESTIONS AND ANSWERS

Q- How many staff are there currently working at this location?

A- Currently 22 staff work at this location.

Q- What is the square footage of the facility?

A- The office is 6,100 sq. ft, the warehouse is 6,700 sq. ft.

Q- Do you have an overhead floorplan layout of the origin?

A- Yes, please see layout of current Tillamook office and warehouse below.

Q- Will we be required to move flammable or HazMat items?

A- No, we will be transporting flammable and HazMat items ourselves. You will only be required to move the cabinets that stores them.

Q- Will we be required to move the forklift?

A- No.

Q- Will we be able to use your forklift?

B- No.

Q- How many cubicles, fireproof file cabinets, and other items will be moved? Can we get a detailed inventory of what items will move where and what items will be disposed of?

C- Yes, Detailed Inventory (5 pages) added as an attachment in SAM.gov.

Q- Will the electrical and data cables be out of the cubicles prior to move?

A- Yes.

Q- What is the weight of the seed pallets?

A- There are two pallets of seed. The seed on each pallet weighs 1,500 pounds.

Q- Will any deposit be authorized given the scope of the work to be completed?

A- Payment in full to be provided when work is completed and accepted. No pre-payment is allowed.

Q- Is this a BOLI prevailing wage job?

A- Wage Determination 2015-5577 Revision 23 from Department of Labor will apply. Wage Determination is attached to the original solicitation on SAM.gov. This is for a moving service and is not determined to be construction.

Q- What is the liability for warehouse damage at the receiving location?

A- See 1452.228-70 Liability Insurance in the contract which requires contractor to carry liability insurance.

Q- What are the payment terms for collection?

A- After all material is moved and disposed of, it will be inspected by a government employee. Once move is complete and approved, invoice may be sent for processing through IPP.gov.

Q- Do you know how many dumpsters would be required?

A- We will provide a detailed inventory of what will be disposed of so you can determine the number of dumpsters you will need.

Q- Can dumpsters be placed and left on site?

A- Yes, there’s plenty of room for the dumpsters to be placed within the gated parking lot behind the building.

Q- Please confirm that no Bid Bond is required?

A- No bid bond is required. This is a request for quotation.

Q- Please advise if a Payment and Performance Bond will be required?

A- No payment of performance bond is required.

Q- Please provide a Rough Order of Magnitude (ROM) for the project?

A- This is not considered a contraction contract; it is for moving services only. Hopefully the layout and article inventory will provide the information you need.

Q- Will contractor be required to provide and pallets or pallet wrapping for items to be relocated and or stored elsewhere?

A- No.

Q- Is there a limitation on how long rolloff dumpster may be left onsite?

A- It is preferred that dumpsters are removed when moving is completed.

Q- Will building be occupied while work is taking place?

A- No, but there will be a BLM representative at the location during the move.

Q- Please provide photos of the loading area.

A- See attachments from amendment #2, photo of warehouse location. Also see amendment #3 photo of origin loading dock.

Q- Is there a loading dock designated for removal activities?

A- Yes, there is a loading dock available for use during removal activities. See photo.

Q- SOW indicates that contractor is to be licensed by Oregon Department of Transportation as a household good mover. Due to the time frame this license may have a lead time beyond our control. Please confirm that this requirement can be waived.

A- Yes, this requirement can be waived, it was meant as a means to ensure liability but that will be covered by contractor’s liability insurance.

Q- Will the contractor require badging to access the location where work is to take place?

A- No, there will be a Federal Employee on site while contractor is working.

Q- Should the contractor require an additional site visit can the contractor schedule an additional one with the BLM?

A- At this time, there is not enough time left for another site visit.

Q- Please advise if there are any height restrictions for vehicles.

A- There are no height restrictions for vehicles.

Q- Please provide photos of the loading area.

A- See attachments, photos of origin and warehouse location loading areas.

Q- Please provide additional photos from 5-16-24 site visit.

A- No further photographs were taken during site visit.

TILLAMOOK FIELD OFFICE LAYOUT