This document is a Questions and Answers file for Solicitation #140L4025Q0001, a Bureau of Land Management (BLM) concrete supply contract for Santa Cruz Lake Recreation Site in Rio Arriba County, New Mexico. The solicitation is a total small business set-aside under NAICS code 327320 for a new project requiring ready-mix concrete delivery. Key details include a site visit scheduled for April 9, 2025, and an estimated concrete requirement of up to 700 cubic yards during the contractual period, with 1-4 concrete pours per week and a minimum order of 8 cubic yards per scheduled pour day. The government will only pay for actual concrete ordered and delivered, with funding loaded for draw-down purposes, and BLM will direct off-load operations at the site.

View the file

Other files

File Type Posted
Sol_140L4025Q0001_Amd_0001.pdf PDF
Sol_140L4025Q0001.pdf PDF
A06_Spec_Doc_4_2_2025.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation #: 140L4025Q0001

Item # Question Answers

1 Is there any incumbent/recompete or this is a brand-new project?

New Project

2 Will there be a site visit? A site visit is available on April 9, 2025, at 10:00 AM Mountain Time. To schedule, please contact Michelle Browning at michellelentebrownin@blm.gov by 10:00 AM Mountain Time on April 8, 2025.

3 Roughly the quantity of material needed from the award through 12/31/2025 and the rough amount next fiscal year?

Per the Bureau of Land Management (BLM) Ready-Mix Concrete Purchase Specification Documentation, Part 1- General, 1.2.2 Delivery Schedule:

• BLM estimates 1 to 4 concrete pours per week. BLM may pour any combination of volume per week, including some weeks where no pours will occur.

• BLM pours shall be such that a minimum of 8 cubic yards will be ordered each scheduled pour day.

• The delivery schedule is only tentative, and the government reserves the rights to increase/decrease this schedule.

Per the Bureau of Land Management (BLM) Ready-Mix Concrete Purchase Specification Documentation, Part 1- General, 3.1 Accomplishment of Work:

• BLM may pour any combination of volume per week, including some weeks where no pours will occur.

• BLM pours shall be such that a minimum of 8 cubic yards will be ordered each scheduled pour day.

• BLM estimates the quantity up to 700 CY for established contractual period. This is just an estimate and does not guarantee a contractual requirement of a maximum order of 700 CY. Contractor shall only invoice BLM for the actual amount ordered and delivered. Funding shall be loaded but only for draw down purposes for each order, delivery, and invoice.

4 For the Ready-Mix concrete, you would like delivery only, no assistance needed with pouring or mixing, and you only want deliveries for what will be used each day, not one large 700 CY drop. Is this accurate?

Per the Bureau of Land Management (BLM) Ready-Mix Concrete Purchase Specification Documentation, Part 1- General, 1.1 Scope of Work:

• These specifications cover requirements for contractor to supply and deliver ready-mix concrete to Santa Cruz Recreation Site in Rio Arriba County, New Mexico.

General, 1.2.2 Delivery Schedule:

• BLM estimates 1 to 4 concrete pours per week. BLM may pour any combination of volume per week, including some weeks where no pours will occur.

mailto:michellelentebrownin@blm.gov

• BLM pours shall be such that a minimum of 8 cubic yards will be ordered each scheduled pour day.

General, 3.1 Accomplishment of Work:

• BLM shall direct off-load operations.

• BLM may pour any combination of volume per week, including some weeks where no pours will occur.

• BLM pours shall be such that a minimum of 8 cubic yards will be ordered each scheduled pour day.

• BLM estimates the quantity up to 700 CY for established contractual period. This is just an estimate and does not guarantee a contractual requirement of a maximum order of 700 CY. Contractor shall only invoice BLM for the actual amount ordered and delivered. Funding shall be loaded but only for draw down purposes for each order, delivery, and invoice.