This document contains questions and answers regarding technical specifications for a water testing and well repair project at the Wells Fire Station. The project requires total coliform bacteria testing and allows the use of SCH 120 PVC piping. The drive/control panel for the well pump is located indoors at the same building as the pressure tanks. The well casing diameter is 10 inches steel, but the existing pump diameter is unknown. This opportunity is considered residential rather than heavy construction.

View the file

Other files for this federal contract opportunity

Other files attached to EKDO FIRE STATION WELL REPAIRS, newest first.
File Type Posted
Sol_140L3923Q0104_Amd_0001.pdf PDF
A06_Midas_Pump___Motor.pdf PDF
A06_Current_Wells_Pump_Specs.pdf PDF
Sol_140L3923Q0104.pdf PDF
A06_1992_Wells_FS_Plans.pdf PDF
A04_combined_Well_Repair_SOW_Solicitation.docx DOCX document
A06_Midas_FS_Well_Info.pdf PDF
A06_1992_Wells_FS_Specs.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers

Water Testing - Are one of these three types of testing are adequate for your requirements. 1)Fecal Coliform Bacteria test, 2)Total coliform bacteria test, or 3)Domestic well test (tests for metals, other biologics, turbidity, etc.

· Total coliform testing is all that will be required.

Pipe requirements - Sch 80PVC is mentioned, however our standard practices, and supplier recommendations, have dictated sch120 pipe as adequate, especially with higher weighted and longer column pump systems. Volume of flow is restricted slightly due to smaller inner diameter. Can sch120 be proposed?

· No issue with Sch 120 being proposed

Wells Fire Station - Any info available on the proposed location of the drive/control panel? Mainly interested in physical area and outdoor/indoor exposuer.

· Drive/control panel is located indoors at same building as pressure tanks.

What is the diameter of the existing pump and well casing?

· Pump diameter at Wells FS is unknown, well casing is 10” steel.