Sol_140L3724R0002_Amd_0001.pdf

PDF 375 KB Posted

Attached to
NIFC HARDSTAND REPAIR
Solicitation number
140L3724R0002
Issued by

About this file

This document provides details for a federal solicitation to repair hardstands at the National Interagency Fire Center in Idaho. Solicitation number 140L3724R0002 seeks to repair hardstands, as issued by the Bureau of Land Management Idaho Region. Interested parties should review the solicitation package for work requirements, response date, and award timing. The solicitation targets hardstand repair work specifically at the National Interagency Fire Center location.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140L3724R0002 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

LFA

BOISE ID 83705

3833 S. DEVELOPMENT AVE.

BLM FA-NTL INTRAGCY FIRE CTR(FA250)

02/27/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

01/29/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PROJECT: NIFC HARDSTAND REPAIR

The purpose of this amendment is to:

1. Provide responses to questions received (see attached question/response sheet, 3 pages).

2. Provide Site Visit Roster (1 page).

3. Extend response due date to March 7, 2024 at 11 AM MT.

This amendment must be acknowledged in accordance with the solicitation.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Matthew Steele

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 6

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

140L3724R0002/0001

No further questions or extensions will be considered due to the critical timing this project needs to be completed for fire season operations.

All other terms and conditions set forth within this solicitation remain unchanged.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

United States Department of the Interior

BUREAU OF LAND MANAGEMENT

Fire and Aviation 3833 S Development Ave

Boise, Idaho 83705-5354

POST SITE VISIT Q&A February 27, 2024

NIFC Hardstand Repair Solicitation Number 140L3724R0002

CONTRACTOR QUESTIONS GOVERNMENT RESPONSE

1. Drawing G002 General note 1 – please confirm no permits are required for this work

1. It is anticipated that a Construction General Permit from the Idaho Department of Environmental Quality (DEQ) will be needed to document stormwater discharges to the hardstand catch basins, which discharges into a regulated waterbody.

2. Drawing G002 General note 2 – please confirm work should conform to project drawings and specifications and not to the ISPWC

2. The contractor will follow/adhere to the requirements of the ISPWC when referenced by the project specifications/drawings.

3. Drawing G002 General note 11 – please confirm no record drawings are required for this project

3. Record drawings reflecting the work performed are a requirement of this project.

4. Preformed compression joint seal note 3 – please provide a recommended or basis of design product spec which meets both ASTM D2628 and

USACE CRD‐C 548

4. D.S. Brown Delastic® Preforemed Pavement (Compression) Seals meet both of these requirements.

5. Concrete note 1 – utilizing a ready mix concrete via truck and chute on such small patches while maintaining max slump and air content may prove to be very challenging and require multiple trucks sent back for not meeting strict design requirements. Please confirm if a quickrete 5000 high early strength concrete bag mix or equal would be acceptable.

5. The concrete product must meet the spec.

Contractor may use a bag mix so long as they can provide documentation showing that their bag mix of choice plus any aggregate or additives they intend to add results in a mix that meets or exceeds the requirements put forth by ISPWC Section 703 for Class 4000A with ¾” aggregate.

Product submittal review will be done after the project is awarded.

6. Concrete note 5 – states that vehicles shall be kept off the hardstand until concrete has reached 28‐day strength. This would entail maintaining barriers around the hardstand after all work is completed. If that is the case, could you please adjust the total period of performance to 90 calendar days?

6. Heavy aircraft loads must be kept off the hardstand until the 28‐day strength is met.

Period of performance must remain at 60 days.

Cure time shall be incorporated into the construction schedule.

7. Concrete crack repair note 3 – states that we are to sandblast the cavity and immediate surrounding area. Please confirm that high psi air cleaning will be acceptable.

7. Sandblasting may be substituted with conditioning the concrete surface with both a steel brush and high‐pressure compressed air.

The steel brush is used to remove scaling and loose concrete.

8. Concrete crack repair note 5 – states to use expanded polystyrene to maintain joint width adjacent to the concrete repair. Please confirm it would also be acceptable to re‐cut the joint after concrete patch has cured to maintain accurate joint width.

8. Re‐cutting the joint to the maximum depth the replaced concrete infiltrates the joint is acceptable.

Contractor shall note slab thickness is 12 inches.

9. Are there any liquidated damages? 9. No, Liquidated Damages are not used in this solicitation. However, the period of performance ends prior to the fire season start date.

10. Are there any as‐builds available for the hardstand’s initial design?

10. No as‐builts are available. Slab thickness is approximately 12” and field investigation indicates rebar is located at about 6” depth.

11. Is the hardstand going to be inactive during active work performed?

a. What type of perimeter barriers are required?

b. If active, what is the estimated area of work that will be required to zone off?

c. In the event of a severe fire that required the hardstand to become active, what type of response will be expected?

11. The concrete hardstand will be inactive during the construction period. The east side asphalt ramp will be in use by aircraft during construction.

a. This is up to the awarded contractor; they are responsible to protect the construction site and keep their work personnel safe. NIFC will provide some candlesticks to ensure government personnel stay clear of the work site.

b. The asphalt ramp area will be active, the tanker base area which includes this hardstand will not be active.

c. The hardstand will not be active during the contracted construction period.

12. What sources of power are available?

a. Estimated length from source of power to furthest point of hardstand?

b. 220v?

12. A single 120V/15A receptacle is provided on the exterior of existing building near Drawing C100 gridline marker H.

b. 208V power is available.

13. Is there water access immediately available?

a. How close to the area of work?

13. ¾” hoses bib is located near Drawing C100 gridline marker E.

14. Are equipment & vehicles able to be staged overnight/weekends? I understand the staged location will be determined once awarded.

14. Yes, vehicles and equipment can be staged overnight and over weekends on the hardstand and the future identified staging area. Awarded contractor is responsible for ensuring FOD is removed from all vehicles and equipment.

15. How do you want areas of spalled/delaminated concrete that aren’t called out handled? This is a vital question to the

15. See Sheet C100, Note 1. Any areas found to need repair, not identified in the drawings, should be brough to the attention of the Government.

warranty of compression joint material in the area’s that are unsatisfactory.

16. Are there any specs for coating any exposed reinforcement?

16. No rebar is intended to be found during construction. If rebars is found it will not require any coating, but contractor should make sure the rebar is free of rust (wire brush or sandblast) before poring the patch material.

17. Any concerns with the existing inconsistency joint profiles of the hardstand slabs? It’s spec’d to install a preformed compression joint be one continuous piece. This will not happen if a single joint can range from ¼ ‐ 1 ¼”. This may void joint material warranties.

a. Would it be considered to sawcut all joints for uniformity?

b. Any considerations for additional expansion joints? Example: Estimated slab is 50’ in length. An additional expansion joint will be added in the estimated center of 25’ of each slab.

17. Each joint line was found to be fairly consistent regarding joint width. The compression joint should be installed as one continuous piece as far as is reasonable, but there will be breaks at the joint intersection locations as two continuous lines cannot pass through each other. It is not anticipated, but if a change in compression seal size is required along the length of a joint line, the break at the joint intersection may be utilized to switch out/change the compression seal size.

A. Sawcuting all of the joints is not necessary. It is up to the contractor if they would like to sawcut in their proposal.

B. There are currently no plans to add additional expansion joints.

18. If any of this additional work is an option, is there any consideration of increasing the duration of the project? Potentially broken up into phases if needed?

18. There are currently no plans to add additional work or to break the project into phases.