B09_Amendment_0001_QandA_Doc_0001.pdf
PDF 284 KB Posted
- Attached to
- Woodhawk Bottom Fence Project Federal contract opportunity
- Solicitation number
- 140L3625Q0024
About this file
This document is an Amendment 0001 Questions and Answers document dated 06/27/2025 for the Woodhawk Bottom Fence Project. The amendment addresses three key questions from potential contractors: (1) Project award and Notice to Proceed will occur prior to the start of the Performance of Performance (POP) on September 1, 2025, (2) Contractors must exclude cattle from the Lower Woodhawk riparian area during the period of 8/16 - 10/31, and (3) Welding or connectors are permitted for steel pipe braces. An additional technical question was resolved regarding steel diagonal braces, with the government confirming that 2 3/8" steel oilfield pipe is the required specification, and directing contractors to a specific vendor (Hedman, Inc.) for sourcing the correct materials. The amendment provides clarification on technical specifications and project constraints to ensure bidders have accurate information for preparing their quotes.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140L3625Q0024_Amd_0001.pdf | ||
| B08_Past_Performance_Questionnaire.doc | DOC document | |
| A06_Woodhawk_Fence_Specifications.pdf | ||
| Bid_Schedule.pdf | ||
| Sol_140L3625Q0024.pdf | ||
| B03_WD_MT20250077_date_5_30_2025.pdf | ||
| A06_Woodhawk_Fence_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment 0001 06/27/2025 Questions and Answers
Site Visit Questions and Answers:
1. Will Period of Performance (POP) be addressed as award and notice to proceed may occur after POP has started (see 60 day timeline mentioned in Solicitation)?
a. Project will be awarded and Notice to Proceed given PRIOR to start of POP (Sept 1, 2025). POP will stand as is.
2. Will contractor be required to exclude cattle during construction of fence?
a. Yes. Period of use for cattle in this allotment is 8/16 – 10/31. Cattle must be excluded from the Lower Woodhawk riparian area during this time.
3. The drawings and specs conflict for welding or use of connectors for steel pipe braces, please confirm which is correct?
a. The use of welding or connectors is permitted for steel pipe braces.
Other Questions Received and Answers:
1. Steel Diagonal braces, it is calling out a brace rail that is 2 3/8" in diameter, this but the picture is showing our brace rail that is only 1 7/8" in diameter, I would like to know that it is ok to bid the standard super brace, I am attaching 2 images of the brace that I think you are wanting to use, the first image is a in line double, or stress panel, and the second photo is a H style brace. the flattened tab measures close to 2 3/8" but the brace rail itself is 1 7/8" in diameter. Please advise.
I just need confirmation that these brace rails will work. They are 1.875 OD 11 gauge steel, pinched, angle cut and punched for a 3/8" bolt. No one makes these out of 2 3/8" diameter.
a. Hedman, Inc. Per BLM Lewistown FO, “This is the type of diagonal that would meet spec, steel oilfield pipe, 2 3/8”. Here is a source for the 2 3/8” brace rail https://hedmaninc.com/ Please quote to specs.
https://hedmaninc.com/