This document is a Contractor Questions and Government Responses document for a Cattle Guard Purchase (Solicitation Number 140L2625Q0101) involving the Bureau of Land Management (BLM). The document addresses four key questions from potential contractors regarding the procurement specifications. The primary clarifications include: (1) the requirement for zinc-enriched protective coating on cattle guards, which can be achieved through a zinc-rich metal primer or elemental zinc as a filler within a polyester powder coat, with Honey Yellow color permitted; (2) confirmation that the procurement quantity is six cattle guards, bases, and wings (despite initial conflicting documentation); and (3) instructions to incorporate delivery costs into the unit prices for each Contract Line Item Number (CLIN) using the form provided in Appendix 1 of the pricing schedule.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question Government response Reference 1 our standard cattle guard comes with a Polyester Powder Coating in Honey Yellow. Is this ok or does it need to be zinc enriched?
The protective coating is required to be zinc enriched for superior corrosion resistance. This can be achieved with a zinc-rich metal primer or by using an elemental zinc as a functional filler within a polyester powder coat. Honey Yellow for color is fine.
1. B.
2 The section B pricing schedule has six cattle guards, bases, and wings. The Statement of Work states seven cattle guards, bases, and wings. What is the amount needed quoted? Six or Seven.
Six. See revised Summary of Work. Summary of Work
3 reading through the Solicitation and the Statement of Work it mentions that the BLM would like to procure 7 cattle guards, but the pricing sheet lists a quantity of 6. If the total number of cattle guards needed could be confirmed that would be great.
Six. See revised Summary of Work. Summary of Work
4 should freight be embedded in the unit prices for each CLIN (FOB Destination), or handled differently?
Cost of Delivery to be incorporated into the cost of each item in the form provided in appendix 1 pricing schedule summary of work and appendix 1