Crooked_Road_Maintenance_2022_Pre-Bid_Site_Tour_Additional_Questions_0001.docx

DOCX document 15 KB Posted

Attached to
CROOKED ROAD MAINTENANCE 2022
Solicitation number
140L2622R0007
Issued by

About this file

This document includes notes from a pre-bid site tour and answers to questions from potential offerors for the CROOKED ROAD MAINTENANCE 2022 solicitation. The site tour notes list attendees from two construction companies. Questions and answers cover ownership of a staging area, water sources, working hours, road thickness and width specifications, use of on-site materials to fill lava ridges or build up the crown, and inverted crown areas. The related federal contract opportunity is solicitation number 140L2622R0007 for Crooked Road Maintenance 2022 from the Department of the Interior Bureau of Land Management Idaho Region. The description provided does not include any additional details on required products or services.

View the file

Other files

File Type Posted
Sol_140L2622R0007_Amd_0001.pdf PDF
FP-14_SUPPS_-_Crooked_Road_Maint_2022.docx DOCX document
Sol_140L2622R0007.pdf PDF
Map_Packet_-_Crooked_Road_Maintenance_2022.pdf PDF
SF-24_Bid_Bond.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Crooked Road Maintenance 2022 Pre-Bid Site Tour: 06/10/2022 List of Attendees

Contractor
E-mail
Phone
Harper Construction (Bryce Harper)
bryce@harperconst.com
(208) 684-5117
RC Heavy Haul (Tracey Scott)
RCHeavyHaulBids@yahoo.com
Office: (208) 523-3176

Cell: (208) 360-1940

1. Who owns the material staging area next to crooked road?

The staging area is owned by the State of Idaho

2. Do you have any information on water sources?

There are no water sources provided by the government. There are ranchers and farmers in the area that you might be able to work out a deal with. You may be able to work out a deal with the town of Parker, it is about 11.5 miles from Crooked Road.

3. What are the working hours?

Typical working hours are between 6AM and 6PM excluding weekends and federal holidays. Other hours can be agreed upon if needed.

4. What is the required thickness of the road?

The road shall be 14 feet wide with a thickness of 5 inches.

5. There are many lava ridges along the roadway. Can on-site material be barrowed to fill over these areas or do the lava ridges need to be removed?

The lava ridges are intended to stay. On-site shoulder/ditch material may be used to fill ridges if necessary. However, the 5 inches of placed cinder should be enough to cover lava ridges in most cases.

6. There are areas with inverted crown. Can waste material from digging ditches be used to build up the crown?

Yes, shoulder/ditch material may be used to build up the crown of the road.