Curlew_Road_Maintenance_2022_Pre-Bid_Site_Tour_0001.docx

DOCX document 15 KB Posted

Attached to
CURLEW ROAD MAINTENANCE 2022
Solicitation number
140L2622R0003
Issued by

About this file

This document summarizes a pre-bid site tour for the Curlew Road Maintenance 2022 federal contract opportunity. The site tour included representatives from three construction contractors who were given additional details on the project. Specifically, attendees were informed that no water sources would be provided by the government but nearby ranchers and farmers may allow access. A map of existing well locations was provided. Additionally, the period of performance was increased from 90 to 120 days and the start date changed to July 18, 2022. The related federal contract opportunity is solicitation number 140L2622R0003 issued by the Department of the Interior Bureau of Land Management Idaho Region for road maintenance services along Curlew Road in 2022. Contractors must contact the specified BLM resource specialist and landowners for access to portions of the work site.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Curlew Road Maintenance 2022 Pre-Bid Site Tour: 06/09/2022 List of Attendees

Contractor
E-mail
Phone
Knife River (Sunny Inglestrom)
sunny.inglestrom@kniferiver.com
(208) 600-2643
Harper Construction (Bryce Harper)
bryce@harperconst.com
(208) 684-5117
Mike Kesler (Richard Hearst)
crystalsprings999@yahoo.com
(435) 999-1900

1. Do you have any information on water sources?

There are no water sources provided by the Government. There are ranchers and farmers in the area that you might be able to work out a deal with. See attached map for some well locations.

2. Is there haul route access through the private to get to the lower end of Glen Canyon?

You will need to contact the BLM, Resource Specialist Kasey Hill (208) 478-6365. He can provide the phone number of the landowner.

3. Could the Period of Performance be switched from 90 days to 120 days?

The POP has been changed to 120 days.

4. What is the start date? Can the date be moved up?

The start date has been changed to July 18, 2022.

File details come from the government source that posted it. Updated .