Attachment_6_-_Q_A_0003.pdf

PDF 103 KB Posted

Attached to
BLM-CO VULCAN RECLAMATION Federal contract opportunity
Solicitation number
140L1724Q0024
Issued by
Department of the Interior Bureau of Land Management Colorado Region

About this file

This document is a question-and-answer attachment related to RFQ 140L1724Q0024 for the BLM-CO Vulcan Reclamation project. The BLM-CO Gunnison Field Office requires reclamation services for unauthorized excavation pits on public land. The Q&A addresses questions about the need for additional soil, compaction equipment, and seed application methods. No special equipment is required for the compaction or seeding work. The onsite material will be adequate for filling the trenches, and the seed must be raked into the soil. The RFQ has a technical response evaluation, consideration of past performance, and price as the award basis. It is a total small business set-aside with a proposal due date of July 17, 2024.

View the file

Other files for this federal contract opportunity

Other files attached to BLM-CO VULCAN RECLAMATION, newest first.
File Type Posted
Sol_140L1724Q0024_Amd_0003.pdf PDF
Attachment_5_-_Pre-Quote_Meeting_Notes_Vulcan_0002.pdf PDF
Attachment_4_-_Site_Locations_and_Pictures_0002.pdf PDF
Sol_140L1724Q0024_Amd_0002.pdf PDF
Sol_140L1724Q0024_Amd_0001.pdf PDF
Attachment_3_-_Map_0001.pdf PDF
Attachment_2_-_Wage_Determination.pdf PDF
Sol_140L1724Q0024.pdf PDF
Attachment_1_-_Statement_of_Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A for RFQ 140L1724Q0024

BLM-CO Vulcan Reclamation

Q: Will additional soil be needed for filling the trenches?

A: No additional soil will be needed. Onsite material will be adequate for filling the trenches.

Q: Will special compacting equipment be needed for the project?

A: No special equipment is needed for compaction. The machine being used for the work can be used to do the compacting.

Q: Are you guys wanting anything other than the actual spreading of the seed. Rotor tilling, harrowing, raked etc.?

A: The seed will need to be raked into the soil.