A04_-140L1722Q0031-_Revised_Bid_Schedule_0001.pdf
PDF 138 KB Posted
- Attached to
- GAOA LSFO IRISH CANYON VAULT TOILET REPL
- Solicitation number
- 140L1722Q0031
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1722Q0031_Amd_0002.pdf | ||
| Sol_140L1722Q0031_Amd_0001.pdf | ||
| A06_-__140L1722Q0031-Section_033000.docx | DOCX document | |
| A06_-_140L1722Q0031-Section_033533.docx | DOCX document | |
| A06_-_140L1722Q0031-Section_311000.docx | DOCX document | |
| A06_-_140L1722Q0031-_Section_329200.docx | DOCX document | |
| A06_-_140L1722Q0031-Section_033550.docx | DOCX document | |
| Sol_140L1722Q0031.pdf | ||
| A06_-_140L1722Q0031-Maps_and_Plans.pdf | ||
| A06_-_140L1722Q0031-Section_013201.docx | DOCX document | |
| B13_-_140L1722Q0031_-Past_Performance_Questionnaire.doc | DOC document | |
| A06__-_140L1722Q0031-_Section_034150.docx | DOCX document | |
| A06_-_140L1722Q0031_-_Section_010090.docx | DOCX document | |
| A04_-140L1722Q0031-_Bid_Schedule.pdf | ||
| B13-140L1722Q0031-_Form_889.pdf | ||
| A06_-140L1722Q0031-Section_013300.docx | DOCX document | |
| B03_-140L1722Q0031-_Wage_Rate.pdf | ||
| A06_-__140L1722Q0031-Section_312000.docx | DOCX document | |
| A06_-_140L1722Q0031-_Section_129300_00.docx | DOCX document |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
BID SCHEDULE
Company Date
Contract Number
Project Description
Item Spec. Bid No. Description Unit Quantity Unit Price Cost Amount Days
1 01 00 90 Mobilization/Demobilzation [1/2 GAOA] LS 1.00 Irish Canyon Area
2 03 41 50 Remove and repair existing Vault Toilet, replace door and toilet [GAOA] LS 1.00
3 31 20 00 Fill hole [GAOA] LS 1.00 4 31 10 00 Clearing [GAOA] LS 1.00 5 31 20 00 Grading [GAOA] LS 1.00 6 03 41 50 Furnish Vault Toilet [GAOA] LS 1.00 7 03 41 50 Install Vault Toilet [GAOA] LS 1.00 8 03 35 33 Concrete flatwork, colored [GAOA] SY 105.00 9 12 93 00 Kiosk EA 1.00
10 CDOT Aggregate Surfacing [GAOA] TN 80.00 11 12 93 00 Furnish and Install Barrier Rock [GAOA] TN 20.00 12 32 92 00 Seeding [GAOA] LS 1.00
Sand Wash Basin
13 03 41 50 Transport and Install Existing Irish Canyon Vault Toilet LS 1.00
14 31 10 00 Clearing LS 1.00 15 01 22 00 Grading LS 1.00 16 03 35 33 Concrete flatwork,colored SY 83.00 17 CDOT Aggregate Surfacing TN 60.00 18 12 93 00 Furnish and Install Barrier Rock TN 20.00 19 32 92 00 Seeding LS 1.00
Total Estimated Construction Cost (TECC) $
Move an existing vault toilet from the Irish Canyon Parking area to Sand Wash Basin area. Install a new vault toilet at the Irish Canyon parking area.
Grade area around each installed vault toilet. Install concrete flatwork around each installed vault toilet area. Add aggregate base to a portion of each parking area. Add barrier rock around each vault toilet area. Add a kiosk to the Irish Canyon Parking area. Mulch and seed disturbed areas.
Contract/Project Name
GAOA LSFO IRISH CANYON VAULT TOILET REPLACEMENT
Project Location Northwest Colorado, Irish Canyon Parking Lot and Sand Wash Basin Rec. Area PR 40578261
File details come from the government source that posted it. Updated .