This is a Bid Sheet for DDC Security Shutters for the Bureau of Land Management 2026 project. The document outlines line items for pricing submission across thirteen tasks involving the supply and installation of security shutter systems, control mechanisms, and related components for various window and door locations.
The scope of work includes: Shutter Systems and installation for Circular Windows (4 EA), Rear Glass Window/door (1 EA), Large Glass Window Sections (3 EA), Glass Window/Door Section (1 EA), Rear Glass Window (1 EA), Front Entry (1 EA), Front Square Window Section (1 EA), and Exterior Restroom Window Section (2 EA). Additional tasks encompass Manual Hand Crank Systems (3 EA with installation), Key Switch System (1 EA with installation), and Master 15 Channel Remote Controls (3 EA with installation and commissioning services). Bidders are required to provide unit costs for each line item, with quantities specified in each/per unit (EA), lump sum (LS), or ton (TON) as applicable. The bid sheet contains blank columns for Unit Cost and Cost, indicating that bidders must complete pricing for all listed deliverables and services.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1226Q0035_Amd_0002.pdf | ||
| Security_Shutter_Q_A_0001.docx | DOCX document | |
| Sol_140L1226Q0035_Amd_0001.pdf | ||
| Sign-in_DDC_0001.pdf | ||
| Sol_140L1226Q0035.pdf | ||
| B08_Attachment_No__1_SOW.pdf | ||
| B08_Attachment_No__2_Davis-Bacon_Act_WD___CA20260026.pdf | ||
| B08_Attachment_No__3_Bid_Sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Sheet – DDC Security Shutters Bureau of Land Management 2026
Site Location/Task Quantity Unit Unit Cost Cost Circular Windows (Task 2 and 3)
4 EA
Shutter System 4 EA Install 4 EA
Rear Glass Window/door (Task 4)
Shutter System 1 EA Install 1 EA
Large Glass Window Sections (Task 5)
Shutter System 3 EA Install 3 EA
Glass Window/Door Section (Task 6)
LS
Rear Glass Window (Task 7)
Front Entry (Task 8)
Install 1 EA
Front Square Window Section (Task 9)
TON
Shutter System 1 EA
Install 1 EA
Exterior Restroom Window Section (Task 10)
Shutter System 2 EA
Site Location/Task Quantity Unit Unit Cost Cost
Manual Hand Crank System (Task 11)
Manual Crank System 3 EA
Key Switch System (Task 12) Key Switch 1 EA
Master Remote Controls (Task 13)
Master 15 Channel Remote 3 EA
Commission 3 EA