This document is a Scope of Work for the Bureau of Land Management (BLM) soliciting a contractor to deliver aggregate base rock to two locations in Monterey County, California. The contract requires delivering 2,500 tons of Class II 3/4-inch minus crushed aggregate base (AB): 1,400 tons to Crescent Bluff Road and Barloy Canyon, and 1,100 tons to the Fort Ord Work Center. Additionally, the contractor must deliver 300 tons of 3/8-inch minus angular crusher fines to the Fort Ord Work Center.
Key specifications include using virgin hard rock with multiple angular faces, being weed-free, and meeting specific particle size requirements. The material cannot be river run or contain recycled metals. The contractor must provide weighmaster certificates daily, allow government inspection of quarry sites, and complete delivery within 21 consecutive calendar days. Noxious weed prevention is required, with suppliers expected to follow California Invasive Plant Council best management practices. The solicitation (140L1225Q0014) is funded under the Gears of Acquisition (GAOA) program and is issued by the Department of the Interior Bureau of Land Management California Region.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1225Q0014.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work 4/10/2025
OBJECTIVE:
The Bureau of Land Management (BLM) has a requirement for a contractor/vendor to deliver Class II, 3/4 inch minus crushed aggregate base rock (AB) and 3/8 inch minus AB to the Fort Ord Work Center. The supplies to be delivered, and all related work to be accomplished, under this contract includes all labor, transportation, equipment, tools, supplies, and materials necessary for producing and delivering aggregate base as specified.
A. Description: Furnishing labor, equipment, supplies, and material, to complete the necessary work as described.
| 1) Deliver 2,500 tons of Class II ¾-inch minus crushed AB meeting Caltrans 3/4” Class II AB Specification: |
| 1a. 1,400 tons to Crescent Bluff Road and Barloy Canyon (see Delivery Location below for more details). |
| 1b. 1,100 tons to the Fort Ord Work Center (see Delivery Location below for more details). |
2) Deliver 300 tons of 3/8-inch minus angular crusher fines to the Fort Ord Work Center meeting the following salient characteristics and including a Certificate of Conformance with the Contractor's bid:
Particle Size % of Passing 3/8" 100% #4 90 - 100% #8 55 - 80% #16 40 - 70% #30 25 - 50% #200 6 - 15%
3) Must be quarried hard rock, virgin material with multiple angular faces (river run or alluvial materials will NOT be accepted). This base will never be covered in asphalt and will be loosely spread
4) Must be weed free and must not contain any recycled materials that may contain remnants of metals.
5) The contractor shall provide the weighmaster certificate tickets to BLM Technical Point of Contact (TPOC) at the end of each day for signature and receipts.
6) Daily total quantities shall be documented by the contractor by a certified scale master and available to the COR within 24 hours. No deliveries shall be made above the contracted amounts without the Contacting Officer’s written approval.
B: Inspection: The government maintains the right to inspect the source of the offered materials and quarry sites prior to award of this contract and/or delivery of materials. Contractor must submit in their quote which quarry they are using to provide AB.
PERFORMANCE PERIOD:
Once delivery begins the contractor will have 21 consecutive calendar days to deliver all AB.
Weekend delivery will only be allowed if approved at the time by the BLM point of contact.
DELIVERY LOCATION
There are two delivery locations for this project:
1,400 tons of Class II ¾-inch minus crushed AB get delivered to the intersection of Crescent Bluff Road and Barloy Canyon Road at 36 degrees 38 minutes 50.84 seconds north, 121 degrees 43 minutes 54.06 seconds west (36.647446, -121.731758 Monterey County)
1,100 tons of tons of Class II ¾-inch minus crushed AB and 300 tons of 3/8 inch minus angular crusher fines get delivered to the BLM, Fort Ord Work Center – near Eucalyptus Road and Parker Flats Road intersection at 36 degrees 37 minutes 15.11 seconds north, 121 degrees 46 minutes 15.86 seconds west (36.6209359, -121.7707359 Monterey County)
NOXIOUS WEED CONCERNS
All AB shall be provided by suppliers who incorporate noxious weed vegetation control Best Management Practices (BMP’s) as identified by the California Invasive Plant Council (https://www.cal-ipc.org/docs/ip/prevention/WeedFreeLandManagers_web.pdf) and to the extent possible provide AB free of noxious weeds.