Sol_140L1221R0014_-_Amendment_No__0001_0001.pdf
PDF 521 KB Posted
- Attached to
- SAMOA OHV FENCE REPLACEMENT
- Solicitation number
- 140L1221R0014
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1221R0014_Amd_0001.pdf | ||
| Sol_140L1221R0014.pdf | ||
| Solicitaion_No__140L1221R00014.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Samoa Dunes Wetland and Bunker Fencing
Solicitation No. 140L1221R0014
Amendment No. 0001
Samoa Dunes Wetland and Bunker Fencing - Pre Bid Tour - 10:00 am on 8/3/2021
Pre-Bid Tour Notes
Attendees:
Jesse Renner - Humboldt Fence Co. - 707-726-7965 - jesse@humboldtfence.com
Gavin Miller - Miller Farms - 707-834-1519 - gavin@mfn@gmail.com
Travis Carmesin - Carmesin Const. - 707-496-1637 - traviscarmesin@aol.com
Chris Woida - Arrow Fencing - 707-485-1128 - chris@arrowfencingca.com
Questions:
1. Q: What hours is the area open?
A: The area is open from 1 hr. before sunrise to 1 hr. after sunset.
2. Q: Do we have access with equipment to remove post and drill holes ?
A: It is all accessible by equipment.
3. Q: Do you have a place for treated wood waste to be dumped? The land fill/dump will not take it.
A: BLM will be responsible for disposing the wood waste. The contractor will stage in a specific location and then will be removed and disposed of by the BLM.
4. Q: Do we need to do any brush clearing and grubbing, or just follow the contours that are existing?
A: Some clearing or grubbing and small amounts of grading may be necessary, but the fence line will follow the contours.
5. Q: I don’t see specifications for cable size, should it be replaced with the same size?
A: This is in the Statement of Work:
For the "Wetland Area" section- "Cable from the current fence will be re-used. If a section of cable is not reusable, it will be replaced with 1/2” galvanized cable, only where necessary. For the "bunker fencing" the cable will be replaced with 1/2 inch galvanized cable."
For the "Bunker Area" section- "Cable around bunkers will be replaced with 1/2” galvanized cable."
mailto:jesse@humboldtfence.com mailto:gavin@mfn@gmail.com mailto:traviscarmesin@aol.com mailto:chris@arrowfencingca.com
Solicitation No. 140L1221R0014
Amendment No. 0001
Samoa Dunes Wetland and Bunker Fencing
SOW 4.0 Specific Tasks
See Exhibit 1 and 2 for reference.
Task 1: Replace approximately 8,000 ft of post and cable fencing that surrounds the area labeled “Wetland Area” in “Exhibit 1”.
• All new posts will be 7”-8” pressure treated agriculture posts.
• Posts will be placed at least 30” in the ground with approximately 36-42” above ground.
• If posts are cut, exposed ends will be coated with wood preservative (similar to
Green Products Co. 30001 Copper Green Wood Preservative) to prevent rot.
• Posts will be spaced 15 ft apart.
• Cable from the current fence will be re-used. If a section of cable is not re-useable, it will be replaced with 1/2” galvanized cable, only where necessary.
• Galvanized cable clamps placed on both sides of every fourth post to prevent unnecessary cable sagging.
• Old cable will be disposed of by the contractor.
• Old posts will be staged by the contractor at the location indicated on the map labeled "Exhibit 3, Wood Waste Staging Location". BLM will be responsible for the disposal of all pressure treated wood waste.
Task 2: Replace approximately 2,800 ft of post and cable fencing that surrounds the areas labeled “Bunker Area” in “Exhibit 1”.
• All new posts will be 7”-8” pressure treated agriculture posts.
• Posts will be placed at least 30” in the ground with approximately 36-42” above ground.
• Posts will be spaced 10 ft apart.
• If posts are cut, exposed ends will be coated with wood preservative (similar to
Green Products Co. 30001 Copper Green Wood Preservative) to prevent rot.
• Cable around bunkers will be replaced with 1/2” galvanized cable.
• Galvanized cable clamps will be placed on both sides of every third post to prevent unnecessary cable sagging.
• Old cable will be disposed of by the contractor.
• Old posts will be staged by the contractor at the location indicated on the map labeled "Exhibit 3, Wood Waste Staging Location". BLM will be responsible for the disposal of all pressure treated wood waste.
Exhibit 3
File details come from the government source that posted it. Updated .