REPAIR OF SOUTH COW MTN OHV TRAIL BRIDGE
Solicitation number
140L1221R0012
Issued by

View the file

Other files

File Type Posted
Sol_140L1221R0012_Amd_0002.pdf PDF
Amendmend_0002_-_140L1221R0012_0002.pdf PDF
Sol_140L1221R0012_Amd_0001.pdf PDF
Solicitation_No__140L1221R00012.pdf PDF
Sol_140L1221R0012.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question and Answers for South Cow Mountain OHV Bridge Replacements

Solicitation #140L1221R0012

Q: Can the date for questions be extended a few days for staff that did not attend the job walk on the 11th to review bid documents and field pictures to generate additional questions?

A: An extension to the question and answer period cannot be given at this time due to fiscal deadlines.

Q: Is it permitted for crew members repairing these bridges to camp at any of the site campgrounds during construction?

A: It may be possible to accommodate this request, but a guarantee cannot be given without further information. The awarded contractor is encouraged to submit a written request to the COR detailing the number of individuals, expected time‐frame of use, list of vehicles and equipment likely to be in the campground during the time of use, and the preferred campground to be used.

Q: What is the lumber grade that is to be used on the bridge deck planks, specified UC3B to be used for the repair work? Availability for some grades may be long lead items.

A: All lumber must meet a minimum Extreme Fiber Stress in Bending (Fb) of 1,400 psi.

Q: Please confirm starting date for the work to begin.

A: The period of performance will be April 1, 2022 through September 30, 2022. After award, the selected contractor will be required to submit a proposed construction start date and schedule for approval.

Q: Information described in the bid documents state that the Spruce Canyon Bridge previously had 4” x 12” transverse and 4” x 12” longitudinal planks. Is it the intent to include two layers of planks on this specific bridge?

A: The Statement of Work will be updated to reflect the correct two‐layer requirement of 4" x 12" transverse decking with 2" x 12" longitudinal planks, per the original drawings.

Q: Please confirm longer working hours will be acceptable.

A: Work will be allowed to occur prior to 7:00 am PST given a 1‐week notice is provided to the

COR.

Q: It was mentioned at the job walk that there was 50 tons of base rock that would be supplied for the bridge approaches. The bid documents states for the contractor is to supply. Please confirm and if it is supplied by the owner, what is the location this material will be for loading/pickup?

A: Please include the cost to supply (Contract line items 2 and 3) and place rock (Contract line items 10 and 15) as detailed in the Statement of Work. The Contracting Officer, in consultation with the technical representative may opt to not exercise any or all of the associated contract line items.

Q: Where larger loads of base rock is needed for bridge approach work, will stockpiling be allowed adjacent to main roads if the area is restored to the RE or IOR satisfaction?

A: Two stockpile locations will be provided for this purpose. The locations are contained in the Appendix of the updated Statement of Work.

Q: Please provide drawing for Spruce Canyon Bridge depicting how to rebuild guardrails.

A: Original drawings of Spruce Canyon Bridge, along with recent inspection reports will be updated to the solicitation.

Q: Please confirm we are to use Standard Form 24 for bid bond.

A: Standard Form 24 is the correct form to use for a bid bond.

Q: Will a Resident Engineer be on‐site for inspections and approval?

A: The COR/Engineer will certify acceptance for all work and may utilize other authorized BLM employees to conduct routine or spot inspections to do so. Generally, a representative will inspect work at crucial points as determined by the COR or upon an approved request from the Contractor but will not be on‐site at all times of active work.

Q: Can water be pulled from surrounding creeks for use in compaction?

A: Unfortunately, the BLM does not have authority to allow for such water use from creeks in the Management Area without consultation with other entities. Potential bidders are encouraged to factor in the cost of supplying water for the purposes described in the Statement of Work into the “backfill and grading” line items.

CLIN Description of Work Quantity Unit Unit Cost Cost

1 Mobilization/Demobilization LS 1 $ $

2 Surface course rock TON 15 $ $

3 Spillway rock TON 50 $ $

Panther Creek Bridge

4 Timber removal and disposal LS 1 $ $

5 Timber installation LS 1 $ $

6 Backfill and grading LS 1 $ $

Benmore Bridge

7 Debris removal and disposal LS 1.0 $ $

8 Timber installation LS 1.0 $ $

9 Backfill and grading LS 1.0 $ $

10 Drainage swale installation EA 2.0 $ $

11 Vegetation removal LS 1.0 $ $

Spruce Canyon Bridge

12 Debris removal and disposal LS 1.0 $ $

13 Timber installation LS 1.0 $ $

14 Backfill and grading LS 1.0 $ $

15 Drainage swale installation EA 4.0 $ $

16 Vegetation removal LS 1.0 $ $

TOTAL FOR SCHEDULE $ ________________________

United States Department of the Interior

Bureau of Land Management

Repair of South Cow Mountain OHV Trail Bridges

Location: South Cow Mountain OHV Management Area

Lake County, California

Address: U.S. Department of the Interior

Bureau of Land Management

Ukiah Field Office

2550 N State St, Suite 2

Ukiah, CA 95482

April 2021 (Updated September 17, 2021)

2 | P a g e Repair of South Cow Mountain OHV Trail Bridges Statement of Work

Contents

I. BACKGROUND ON THE GOVERNMENT’S REQUIREMENT :

II. GENERAL SCOPE OF WORK:

III. OVERALL OBJECTIVE(S):

IV. REQUIREMENTS AND TASKS:

V. DELIVERY SCHEDULE:

VI. GOVERNMENT-FURNISHED PROPERTY, MATERIALS, SERVICES:

VII. SECURITY AND ADMINISTRATIVE MATTERS:

VIII. DEFINITIONS:

APPENDIX

APPENDIX A: BEST MANAGEMENT PRACTICES FOR THE PROTECTION OF WATER

QUALITY

APPENDIX B: RECOMMENDED BEST MANGEMENT PRACTICES FOR BRIDGES

APPENDIX C: MAPS OF PROJECT LOCATIONS

APPENDIX D: ROCK STOCKPILE LOCATIONS

APPENDIX E: BLM FIELD OFFICE CONTACTS

I. BACKGROUND ON THE GOVERNMENT’S REQUIREMENT :

In late-2018, the Mendocino Complex Fire burned over 450,000 acres in northern California and damaged Bureau of Land Management (BLM) infrastructure. Some of the damaged infrastructure included three off-highway vehicle (OHV) trail bridges: Panther Creek Bridge, Benmore Bridge, and Spruce Canyon Bridge within South Cow Mountain OHV Management Area. The goal of this contract is to repair the three damaged bridges to their original condition.

II. GENERAL SCOPE OF WORK:

The contractor shall repair and replace damaged bridge components on three OHV trail bridges: Panther Creek Bridge, Benmore Bridge, and Spruce Canyon Bridge. The types of work involved shall include removal of damaged timber and bridge structure components, bridge structure excavation and backfill, replacement of timber and damaged bridge structural components, and mobilization/de-mobilization.

The general tasks and project specific tasks are described in the Requirements section.

Location of Work:

The project sites are all located within South Cow Mountain OHV Management Area in Lake County, California. South Cow Mountain OHV Management Area, Lake County, California is located 9.8 miles southeast of Ukiah, California and 4.8 miles west of Lakeport, California. See attached maps (Appendix C).

The main road through South Cow Mountain is Mendo-Lake Road. All project sites are accessible from Mendo-Lake Road. Mendo-Lake Road may be accessed via Ukiah or Lakeport. Access to Mendo-Lake Road through the southeastern entrance via Scotts Creek Road may be impassible when Scotts Creek is flowing, which is usually during the wet season (October to March). Access to Mendo-Lake Road through the northwest entrance via Mill Creek Road, may be challenging or impassible during the wet season.

Vehicles with four-wheel drive are recommended to access all project sites.

Project Site Locations:

Panther Creek Bridge (39.082548°, -123.060341°)

• Directions (from Westside Staging Area, South Cow Mountain OHV Management Area):

Head south on Mendo-Lake Road. Turn left at the fork onto Oakwood Springs Road. Turn right onto Eight Mile Valley Road. Continue for 1.9 miles.

Benmore Bridge (39.031948°, -123.025152°)

• Directions (from the south east entrance of South Cow Mountain OHV Management Area):

Head north on Mendo-Lake Road for 3.7 miles. Turn left onto Buckhorn Road. Turn left onto Trail 23 (Benmore Trail). Continue on Trail 23 for 0.7 miles.

Spruce Canyon Bridge (39.063644°, -123.010025°)

• Directions (from the south east entrance of South Cow Mountain OHV Management Area):

Head north on Mendo-Lake Road for 1.7 miles. Turn right onto Trail 17. Continue on Trail 17 for 1.8 miles.

Period of Work Performance:

The period of work performance for this contract shall be April 1, 2022 through September 30, 2022.

Contract work including the pre-work conference meeting, site visits and planning meetings, mobilization, construction, and de-mobilization must be completed within the Period of Performance.

III. OVERALL OBJECTIVE(S):

The objectives of this Contract are to:

• Remove and replace damaged and weakened structural components of Panther Creek Bridge, Benmore Bridge, and Spruce Canyon Bridge.

• Improve structural integrity of Panther Creek Bridge, Benmore Bridge, and Spruce Canyon Bridge.

• Improve public access on off-highway vehicle trails crossing waterways.

IV. REQUIREMENTS AND TASKS:

General Requirements

1) Timber and Timber Treatments All lumber must meet a minimum Extreme Fiber Stress in Bending (Fb) of 1,400 psi.

The contractor shall submit to the COR, for approval, a list of all proposed timber and timber treatments along with proof of Fb grade. Base requirements for timber and timber treatments, where applicable, are provided below. The submittal list will not be approved for installation until the COR can verify that basic requirements have been met.

All preservative treatment shall be in accordance with the current American Wood Protection Association (APWA) specifications using the treatment materials listed below. Treatment shall comply with the requirements of the current edition of Western Wood Preservers Institute (WWPI) “Best Management Practices for the use of Treated Wood in Aquatic Environments”.

Bridge decking

• AWPA use category system (U1) for use category 3B above ground – exposed

(UC3B)

• Pentachlorophenol in light oil (Type C Solvent)

• Copper Napthenate (CuN) in light oil (Type C Solvent)

Sills, backing planks, cribs, timber walls (wingwalls and backwalls)

• AWPA use category system (U1) for use category 4B ground contact – heavy duty (UC4B)

• Pentachlorophenol in light oil (Type C Solvent)

• Copper Napthenate (CuN) in light oil (Type C Solvent) A copper napthenate (2% solution) shall be furnished for field treatment. All abrasions and field cuts, approved by the COR, shall be carefully trimmed and given three brush coats of the field treatment solution. Where approved field drilling of bolt or nail holes is required, the holes shall be filled with preservative prior to inserting fasteners.

2) Mechanical Fasteners The contractor shall use steel mechanical fasteners for securing timber to existing structural components which have been hot-dip galvanized. All installed hardware shall meet the requirements of AASHTO M270, Grade 36, with nuts and bolts conforming to

ASTM A307, Grade A. Weathering steels and hardware shall meet the requirements of

AASTHO M270, Grade 50W, with bolts and nuts conforming to ASTM A325, Type 3. The use of malleable iron washers against wood shall be required.

3) Drainage Swale Rock The contractor shall furnish and install rock associated with roadway drainage features

(swales) located in approaches to Benmore and Spruce Canyon bridges. A typical drawing is provided in the technical exhibits which demonstrates a typical installation of a drainage swale to be completed in association with this contract.

Surface course rock shall be angular and meet the following grading requirements:

Spillway rock shall be angular, not be smaller than 6” nominal diameter and not larger than 12” nominal diameter.

The contractor shall submit for COR approval, the specifications of both types of rock to be proposed for use in constructing the drainage swale features.

The contractor shall furnish 5 tons of surface course and 10 tons of spillway rock to the southwest approach of Benmore Bridge. Similarly, the contractor shall furnish 10 tons of surface course and 40 tons of spillway rock, split between the two approaches of Spruce

Canyon Bridge.

Site Specific Tasks Panther Creek Bridge o Task 1: Removal and Disposal of Timber: Deck, Abutment, and Wingwall

Contractor shall remove and properly dispose of all existing deck timber regardless of age or condition, and all timber associated with back and wing walls at Abutment 1 (northwest).

o Task 2: Replacement of Timber: Deck, Backwall, and Wingwall

Contractor shall install treated 4”x12” timber, transversely, on existing steel girders to restore original configuration of decking. Planks shall be spaced to maintain a nominal 3/8” gap in decking.

Contractor shall install treated 3”x12” timber to reestablish backwall and wingwalls at

Abutment 1.

o Task 3: Backfill and grading

The contractor shall backfill and compact any soil removed to accommodate timber replacement at Abutment 1. The contractor shall compact soil in six (6) inch lifts by mechanical vibratory compactor. Soil must be compacted when in optimum moisture content range as determined by COR. The contractor shall be required to furnish water for use in compaction when site conditions are determined as dry by the COR.

The contractor shall regrade up to 100 feet of approach to Abutment 1 and install up to two drainage swales to improve drainage on the road. The exact slope of grading and location and orientation of drainage swales shall be determined in the field upon consultation with COR and other BLM personnel.

Benmore Bridge o Task 1: Removal and Disposal of Timber: Deck, Abutments, and Wingwalls

The contractor shall remove and properly dispose of all existing deck timber, including planks above abutments, and all timber associated with back and wing walls for both abutments.

o Task 2: Replacement of Timber: Deck, Abutments, and Wingwalls

Contractor shall install treated 4”x12” timber, transversely, on existing steel girders to restore original configuration of decking. Planks shall be spaced to maintain a nominal 3/8” gap in decking.

Contractor shall install treated 3”x12” timber to reestablish backwall and wingwalls at both abutments.

o Task 3: Backfill and grading

The contractor shall backfill and compact any soil removed to accommodate timber replacement for both abutments. The contractor shall compact soil in six (6) inch lifts by mechanical vibratory compactor. Soil must be compacted when in optimum moisture content range as determined by COR. The contractor shall be required to furnish water for use in compaction when site conditions are determined as dry by the COR.

The contractor shall regrade up to 150 feet of approach to Abutment 2 (southwest) and install up to two drainage swales to improve drainage on the road. The exact slope of grading and location and orientation of drainage swales shall be determined in the field upon consultation with COR and other BLM personnel. In association with the construction of drainage swales, the contractor shall remove vegetation from areas adjacent to the roadway where drainage swales are to be constructed, limited to a total of 250 square feet of impacted area per drainage feature.

o Task 4: Vegetation removal

The contractor shall remove all vegetation located within ten (10) feet of the bridge including abutments. Any vegetation with vertical growth in excess of 4” diameter shall be cut as close to ground level as possible with the remaining structure to be treated with approved herbicide.

Spruce Canyon Bridge o Task 1: Removal and Disposal of Remaining Debris

The contractor shall remove and properly dispose of any remaining timber, including remaining curbs and railing and any debris that cannot be reclaimed for continued use, including mechanical fasteners.

o Task 2: Replacement of Timber: Deck, Backwall, and Wingwall

The contractor shall install 4”x14” treated nailing boards and treated 4”x12” timber on existing steel girders to restore original configuration of decking per original drawings.

The first layer of timber shall be installed transversely, relative to the superstructure beams using continuous planks spaced nominally 3/8” apart. The second layer of timber shall be installed longitudinally, relative to the superstructure beams.

The contractor shall install curb structure (wheel guard) and railing to match original orientations per original drawings.

o Task 3: Grading and Erosion Control

The contractor shall regrade 150 feet of both approaches to the bridge and install up to four drainage swales or other drainage control features within the 200 feet of road to be regraded to improve drainage on the road. The exact slope of grading and location and orientation of drainage swales or drainage features shall be determined in the field upon consultation with COR and other BLM personnel.

In association with the construction of drainage swales, the contractor shall remove vegetation from areas adjacent to the roadway where drainage swales are to be constructed, limited to a total of 250 square feet of impacted area per drainage feature.

o Task 4: Vegetation removal

The contractor shall remove all vegetation located within ten (10) feet of the bridge including abutments. Any vegetation with vertical growth in excess of 4” diameter shall be cut as close to ground level as possible with the remaining structure to be treated with approved herbicide.

General Tasks o Task 1: Environmental Controls

a. The Best Management Practices (BMPs) listed in Technical Exhibit 1 are required to satisfy Clean Water Act requirements for Non-point source pollution.

b. The presence of archaeological resources, sensitive soils and private lands within the project area requires that all vehicles and equipment operate on existing roadways and designated trails and up to 50 feet from the trail centerline as required to complete work at designated sites.

o Task 2: Site Use Plan

a. All vehicle and equipment use shall be restricted to the existing roadway and trails.

Equipment work may occur within 50 feet of the road/trail centerline. Equipment operations on areas beyond 50 feet require approval from the Contracting Officer (CO).

b. Existing pull-outs may be used for equipment staging and materials storage. Other sites may be utilized for staging or storage subject to the Contracting Officer or their representative’s approval.

c. At the conclusion of work, all storage and staging areas shall be restored to a free-draining condition and be free of any inorganic debris.

d. All excess soils will be groomed to match existing topography as feasible.

e. No hazardous materials or fuels shall be stored within 150 feet of a watercourse.

f. The Contractor shall provide a Site Usage Plan to be approved by the COR and the CO prior to the Notice to Proceed. Plan details shall include but not limited to: equipment storage locations, materials stockpile, and planned staging areas.

o Task 3: Cultural Resource Protections and Controls

The project will not cause a substantial adverse change in the significance of a historical resource per Section 106 of the National Historic Preservation Act (NHPA) of 1966 (as amended) described in 36 CFR 800.5(a)(1).

However, we make the following recommendations to ensure that cultural resources are not adversely affected by the proposed project. The project is not expected to have an adverse effect on cultural resources. The Contractor must adhere to the following stipulations:

a. Cultural Resource Awareness Training Prior to the initiation of the project a cultural resources training will be provided to supervisors, contract foreman, construction crew members, and any additional key construction personnel. The agency and or consulting archaeologist will administer the training. The purpose of the training is to increase awareness and knowledge of cultural resources and appropriate protocols in the event of an inadvertent discovery. The training will include a discussion of the unanticipated discovery protocol with an emphasis on the procedures for stopping work and notification of key personnel.

Appropriate protocols in the event that human remains are discovered will also be discussed. A training pamphlet Cultural Resources Guide to Identification and Protocols will distributed to all construction personnel. Upon completion of the training, participants will be able to define cultural resources, describe the policies and procedures for identifying and protecting cultural resources, know how to locate and receive assistance from the professional archaeologist and coordinate with other sources, and describe steps to be taken when cultural resources are encountered during project implementation. All new construction personnel added after construction commences will receive the same training and orientation before working on-site. In the event that Native American monitors are used, it will be necessary for tribal representatives to also participate in the training.

b. Unanticipated Discovery Protocol An Unanticipated Discovery Protocol will be developed for this project prior to the initiation of construction. The Unanticipated Discovery Protocol will describe the procedures to be followed if potential significant archaeological resources or human remains are encountered during project-related activities. The document will provide an outline of the unanticipated discovery protocol, potential reporting needs in the event of a discovery and the post-testing and monitoring reporting requirements, references and a list of contacts. The document will list key personnel and include specific contact information for those individuals. The Unanticipated Discovery Protocol will be available on-site during construction.

c. Unanticipated Discovery of Cultural Resources If previously unidentified cultural resources are encountered during project implementation, avoid altering the materials and their stratigraphic context. A qualified professional archaeologist should be contacted to evaluate the situation. Project personnel should not collect cultural resources. Prehistoric resources include, but are not limited to, chert or obsidian flakes, projectile points, mortars, pestles, and dark friable soil containing shell and bone dietary debris, heat-affected rock, or human burials. Historic resources include stone or abode foundations or walls; structures and remains with square nails; and refuse deposits or bottle dumps, often located in old wells or privies.

d. Encountering Native American Remains Although unlikely, if human remains are encountered, all work must stop in the immediate vicinity of the discovered remains, and an agency representative notified immediately. It should be noted that the “Most Likely Descendent” also known as the MLD process is state of California code and does not apply to human remains identified on federal lands. Per 43 CFR Section 10.4(b), inadvertent discoveries, NAGPRA notes that the responsible Federal agency official must be notified immediately via telephone with written confirmation. Additionally per subpart c, if the discovery occurred in connection with on-going activity on Federal lands, the activity must stop. Subpart d identifies the next steps as (i) certifying receipt of the notification; (ii) take steps to secure and protect the discovery; (iii) notify lineal descendants; (iv) initiate consultation;

(v) if excavation or removal is necessary follow Section 10.3(b), procurement of an ARPA permit; and (vi) ensure disposition of inadvertent discoveries follows Section 10.6.

e. Site Visition If deemed necessary and or to facilitate communication, the agency archaeologist may monitor construction either formally or informally. This may entail anything from being on-site during construction hours to occasionally checking-in with the contractor to ensure that everything is going smoothly and that nothing out of the ordinary has been encountered such as Native American and or historic-era artifacts, as well as paleontological finds.

Warranty Materials and equipment furnished under this Contract shall be covered by the most favorable commercial warranties given to customers for such materials or equipment. The rights or remedies provided herein are in addition to and do not limit rights afforded to the Government by other clauses of this Contract. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the Contract the Contractor shall:

1. Obtain warranties that would be given in normal commercial practices.

2. Require warranties to be executed, in writing, for the benefit of the Government.

3. Submit warranties to the Contracting Officer prior to the final inspection.

V. DELIVERY SCHEDULE:

Standards

• Moving of Equipment and Supplies: The moving of equipment and supplies to the job site and between job sites shall be the responsibility of the Contractor.

• Replacement of Equipment: Contractor shall provide quality equipment capable of safely performing the work under the terms of the contract. If equipment is rejected because it does not meet minimum requirements, including but not limited to safety and operability, or if it becomes inoperative, the Contractor shall correct the deficiencies or furnish replacement equipment meeting contract requirements within 2 calendar days. All repairs are the total responsibility of the Contractor.

• Equipment Standards: Contractor shall make equipment available for inspection and approval before use. The Contractor must satisfy all applicable OSHA and DOT requirements or certifications for the operation of offered equipment. There will be no obligation to make payment for any equipment delivered that does not meet the Technical Specifications.

• Existing Facilities: All existing facilities such as signs, cattle guards, drainage structures and road surfacing damaged by the Contractor's operations shall be replaced or repaired by the

Contractor at no cost to the Government.

• Watershed Protection and Erosion Control: During all operations under this contract, the

Contractor shall exercise reasonable measures to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and equipment maintenance areas shall be stored and collected in a sanitary manner and disposed of in a State-approved sanitary landfill, per local, State, and Federal regulations.

Oil from crankcases or gear boxes, equipment waste or spilled or excess fuel shall be placed in containers and removed from the work site and disposed of as approved and required by local, State, and Federal regulations.

Contractor shall undertake every reasonable measure to minimize erosion and soil damage in connection with any operations under this contract. Contractor shall immediately discontinue any operations under this contract that due to weather or soil moisture conditions, such operations will cause excessive damage to the soil as determined by the Contracting Officer.

Equipment shall not be fueled nor fluids changed within 100 feet of waters of the state. Any equipment operated adjacent to state waters shall be maintained in a good state of repair and have no damaged hoses, fittings, lines, tanks, etc. that may release pollutants into the water.

Waste oil and fluids shall not be stored on site. If any such material is released into the waters, the responsible person must make an effort to contain the spill and notify the Contracting Officer within 24 hours. If unable to contain spill, immediately notify the Contracting Officer and call the National Response Center (NRC) at 1-800-424-8802.

• Emergency Spill Kit: Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum produce spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operations.

Project site construction not completed during dry weather periods shall be winterized (along with Contractor’s approved onsite staging areas and storage sites) to minimize erosion and other damage to roadways, trails, watercourses, and sensitive habitat, as directed by the Contracting Officer.

• Disposal of Debris: The Contractor shall transport and dispose of all debris and excess material off-site at an approved facility, per local, State, and Federal regulations.

Any debris left onsite after the completion of the Contract shall become the property of the Contractor, and the Contractor shall be responsible for it. Dispose of materials in a legal manner and payment of fees required is the Contractor's responsibility. Sale of material onsite is not allowed unless authorized in writing by the Contracting Officer. Burning of removed materials is not permitted on the work site.

• Project Boundary: Prior to implementation of Contract deliverables, a pre-work meeting will be held at the project sites with the Contractor, Contracting Officer Representative (COR), and/or Project Inspector (PI). The intent is to ensure the Contractor understands where the project sites are located, project site specifics and specifications of the contract, and review the Contractor’s plan of operations. It is encouraged that all potential Contractors complete a thorough site visit before bidding on the contract.

• Access: Access to the project area is identified on the map. If roads or any type of access become subject to damage, because of adverse weather conditions or other natural causes, the Contracting Officer or COR will relay that information to the Contractor by phone, email, or in person and the contract could be delayed.

• Notification of Cessation or Restart of work: The Contractor shall notify the Contracting

Officer prior to ceasing operations for three or more days, and before re-starting operations after a shutdown of three or more days. This can be done by phone, E- mail, or in person.

• Protection of Cultural Resources: If objects of cultural value on the project area are discovered, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and notify the Authorized Office of the findings.

• Weed Prevention: To reduce the potential for introduction of noxious weeds to the contract area, the Contractor shall, prior to moving in motorized equipment to be used for mastication, clean all such equipment to remove all dirt, plant parts and materials that may carry noxious weed seeds. All equipment shall be inspected by the Contracting Officer prior to moving said equipment to the contract area.

• Fire Prevention: Contractor shall take necessary measures for prevention and suppression of fire on the contract area and other adjacent Government lands used or traversed by the

Contractor in connection with operations as are required by applicable laws and regulations.

Contractor shall comply with all applicable local, State, and Federal fire prevention regulations and standards. At all times during closed fire season, each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

• Fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating

• Shovel, round point #0 lady or equal

• Axe, 2 pounds or over, 26-inch minimum length, or one pulaski

Delivery

The Contractor shall complete all treatments within 100 calendar days after notice to proceed. Due to permitting requirements for the protection of water quality and sensitive species, all mobilization, construction, and demobilization must occur between August 1, 2021 and September 30, 2021.

Within 15 business days of the completion of work, the Contractor shall provide site-specific photographs clearly showing the before and after repair conditions to document compliance with applicable BMPs. The photographs should be clearly labeled with the project site name, date(s), and a description of what was being photographed. The photos shall be submitted to the BLM in a digital format and should be clearly organized and labeled.

Final Inspection and Acceptance

The Contracting Officer’s Representative or designated government representative will review all work.

The Government’s final project inspections shall take place 1-3 business days following the Contractor’s written notification to the CO and COR of the completion of work. At the conclusion of the work, the Contracting Officer, or their representative, will inspect all sites for conformance with the specifications and requirements. Any deficiencies noted during the inspection will be corrected by the Contractor prior to release of final payment, at no additional cost to the Government. Prior to final payment the Contractor shall properly disposed of all waste materials including excess soil, completed site resurfacing and grooming of staging and storage areas, and submitted project photographs and project reports.

Work Schedule The schedule shall be submitted at the pre-work conference. When requested by the CO or COR, submit an updated work schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.

Health and Safety Plan Before construction commences, the Contractor shall submit a health and safety plan to the CO for approval. The health and safety plan shall include the location of the nearest hospital and procedures to follow in case of an emergency. The Contractor is required to have a portable toilet on-site for the duration of construction.

VI. GOVERNMENT-FURNISHED PROPERTY, MATERIALS, SERVICES:

General: The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Statement of Work.

The Contractor shall furnish all necessary hardware for securing the deck and railing members to be replaced in-kind.

The Contractor shall furnish fencing and signage (where applicable) for project sites, staging areas, and storage areas. The Contractor will be responsible for the installation and removal of fencing and signage during project construction. The Contractor shall furnish all materials to secure project sites, staging areas, and storage areas during use by the Contractor. These materials and operations shall be considered incidental to the work required and shall not be paid separately.

The Contractor’s proposed on-site storage and staging areas are required to be approved of by the CO and COR before mobilization and construction begin.

Applicable Publications (Current Editions)

• Best Management Practices for the Protection of Water Quality (see Technical Exhibit 1)

• Water Quality Construction Best Management Practices Manual o https://www.waterboards.ca.gov/water_issues/programs/cwa401/docs/certifications/snrse

_h.pdf

• Recommended Best Management Practices for Bridges (see Technical Exhibit 2) o https://www.fws.gov/daphne/section7/BMPs-bridges.pdf

• The Standard Specifications for the Construction of Roads and Bridges on Federal Highway Projects (FP-14) o https://highways.dot.gov/federal-lands/specs

VII. SECURITY AND ADMINISTRATIVE MATTERS:

Contingency Plan:

Sudden or unusual events could result in a negative impact to the delivery/work of these requirements.

As an aid to properly plan for such events, the Contractor shall prepare and submit for approval a Contingency Plan for each Location of Work for these requirements. The Contractor will outline in detail https://www.waterboards.ca.gov/water_issues/programs/cwa401/docs/certifications/snrse_h.pdf https://www.waterboards.ca.gov/water_issues/programs/cwa401/docs/certifications/snrse_h.pdf https://www.fws.gov/daphne/section7/BMPs-bridges.pdf https://highways.dot.gov/federal-lands/specs the method(s) that the Contractor shall use in meeting Contract requirements in the following circumstances:

• a natural disaster occurs which impacts upon the Contractor's ability to perform

• a labor strike occurs which impacts upon the Contractor's ability to perform.

• a hazardous materials spill which impacts the Contractor’s ability to perform or which may affects public safety

• an incident which causes major damage which impacts the Contractor's ability to perform

• other unforeseen circumstances

In all cases, the Contractor will assume that government cannot provide supplemental forces, and continues to need the same or additional work under the Contract, which the Contractor must meet.

This Contingency Plan shall be submitted as a part of the Contractor proposal.

Emergency Response:

Response to emergency service calls outside of the normal business hours shall not exceed four (4) hours regardless of the time during the day or night, weekends or holidays. Response to emergency service during normal business hours shall not exceed two (2) hours. Response is defined as having all personnel and equipment required to correct an emergency at the site of the emergency or at a pre-approved staging area, ready willing and able to perform the emergency work. The Contractor will provide a draft emergency response plan prior to Contract start date.

Emergency Services:

On occasion, services may be required to support an activation or exercise of contingency plans outside the normal business hours described above. The Contractor's responsibilities for emergency support will be in accordance with the contingency plan.

Hazardous Materials and Hazardous Response:

The Contractor will conform to all Reclamation, Federal, State, and local regulations in the use and disposal of hazardous materials and hazardous waste. The Contractor will provide the appropriate response to any emergency involving hazardous materials at any of the facilities covered by this Contract. The Contractor will provide proof/certification of its personnel qualified to work with hazardous materials and wastes to Reclamation. The Contractor will notify Reclamation immediately upon discovering a release of hazardous waste into the environment.

Public Contact:

Contractor personnel may have a close working relationship with adjacent landowners within their area of responsibility.

Contractor personnel will inform any trespassers along the right of way, of hazards and when necessary request trespassers to leave fence restricted areas immediately.

When Contractor personnel are confronted with the news media, they may respond to general questions of the media with common sense approach and will refer all controversial questions to the O&M Manager. The Contractor Manager will keep the COR informed of all news media contacts.

When Contractor personnel are confronted with emergency personnel, policemen or firemen along the right of way, the Contractor personnel will notify the O&M Manager.

Government Observations:

Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations. However, these personnel will not interfere with Contractor work performance.

Regular Work Hours:

The work period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 4:00pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made for access to the work site.

Communications:

“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.

Federal Holidays:

The following Federal Legal Holidays are observed:

New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Juneteenth Independence Day Labor Day Columbus Day Veterans Day Thanksgiving Day Christmas Day

Fire Danger Season:

If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

Preservation of Historical and Archeological Data:

(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.

(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.

(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of work performance and/or changes in the work. If such delays and/or changes are ordered, the time of work performance and contract price shall be adjusted in accordance with the Changes clause.

(d) The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.

VIII. DEFINITIONS:

Standard Definitions:

• Physical Condition

The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.

• Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.

• Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.

• Quality Assurance (QA) Surveillance of Contractor work to determine work requirements are met.

• Work Requirements Summary (WRS) (see Technical Exhibit 6) The WRS identifies the key work performance indicators of the Contract that will be evaluated by the Government to assure Contract work performance standards are met by the Contractor.

• Quality Control (QC) Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the work statement.

• Approvals Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing. After approval of an item, submit a substitute for approval when the approved item cannot be purchased or delivered in time to avoid delay in completion of the project.

Acronyms:

The following is a list of acronyms with their definition that are referenced in this project:

• AASHTO American Association of State Highway and Transportation Officials

• AWPA American Wood Protection Association

• BLM Bureau of Land Management

APPENDIX

APPENDIX A: BEST MANAGEMENT PRACTICES FOR THE PROTECTION OF WATER QUALITY

APPENDIX B: RECOMMENDED BEST MANGEMENT PRACTICES FOR BRIDGES

APPENDIX C: MAPS OF PROJECT LOCATIONS

APPENDIX D: ROCK STOCKPILE LOCATIONS

APPENDIX E: BLM FIELD OFFICE CONTACTS

APPENDIX A: BEST MANAGEMENT PRACTICES FOR THE PROTECTION OF WATER

QUALITY

Best Management Practices For the Protection of Water Quality

To maintain compliance with federal Clean Water Act Requirements, Contractor is responsible for adhering to Best Management Practices. The following list of Best Management Practices (BMPs) will be employed at treatment sites depending on the nature of treatments and the applicability of a given BMP for the site.

Construction and reconstruction BMPs:

1. Minimize fill volumes at stream crossings by restricting width and height of fill to amounts needed for safe travel and adequate cover for culverts. For deep fills (generally greater than 15 feet deep), incorporate additional design criteria (e.g., rock blankets, buttressing, bioengineering techniques) to reduce the susceptibility of fill failures.

2. Place sediment-trapping materials or structures such as straw bales, jute netting, or sediment basins at the base of newly constructed fill or side slopes where sediment could be transported to waters of the State. Keep materials away from culvert inlets or outlets.

3. Construct road fills to prevent fill failure using inorganic material, compaction, buttressing, sub-surface drainage, rock facing, or other effective means.

4. Locate waste disposal areas outside wetlands, Riparian Reserve, floodplains, and unstable areas to minimize risk of sediment delivery to waters of the State. Apply surface erosion control prior to the wet season. Prevent overloading areas, which may become unstable.

5. Design stream crossings to minimize diversion potential in the event that the crossing is blocked by debris during storm events. This protection could include hardening crossings, armoring fills, dipping grades, oversizing culverts, hardening inlets and outlets, constructing critical dips, and lowering the fill height.

6. Design stream crossings to prevent diversion of water from streams into downgrade road ditches or down road surfaces.

7. On new construction, install culverts at the natural stream grade, unless a lessor gradient is required for fish passage.

8. Place instream grade control structures above or below the crossing structure, if necessary, to prevent stream head cutting, culvert undermining and downstream sedimentation.

Employ bioengineering measures to protect the stability of the streambed and banks.

9. Prevent culvert plugging and failure in areas of active debris movement with measures such as beveled culvert inlets, flared inlets, wingwalls, over-sized culverts, trash racks, or slotted risers.

10. Utilize stream diversion and isolation techniques when installing stream crossings. Evaluate the physical characteristics of the site, volume of water flowing through the project area and the risk of erosion and sedimentation when selecting the proper techniques.

11. Disconnect road runoff to the stream channel by outsloping the road approach. If outsloping is not possible, use runoff control, erosion control and sediment containment measures.

These may include using additional cross drain culverts, ditch lining, and catchment basins.

Prevent or reduce ditch flow conveyance to the stream through cross drain placement above the stream crossing.

Surface Drainage BMPs:

1. Effectively drain the road surface by using crowning, insloping or outsloping, grade reversals (rolling dips), and waterbars or a combination of these methods. Avoid concentrated discharge onto fill slopes unless the fill slopes are stable and erosion-proofed.

2. Consider using broad-based drainage dips or leadoff ditches in lieu of cross drains for low volume roads. Locate these drainage features where they will not drain into wetlands, floodplains, and waters of the State.

3. Avoid use of outside road berms unless designed to protect road fills from runoff. If road berms are used, breach to accommodate drainage where fill slopes are stable.

4. Design roads crossing low-lying areas so that water does not pond on the upslope side of the road. Provide cross drains at short intervals to ensure free drainage.

5. Divert road and landing runoff water away from headwalls, slide areas, high landslide hazard locations, or steep erodible fill slopes.

Cross Drain BMPs:

1. Locate cross drains to prevent or minimize runoff and sediment conveyance to waters of the State. Implement sediment reduction techniques such as settling basins, brush filters, sediment fences, and check dams to prevent or minimize sediment conveyance. Locate cross drains to route ditch flow onto vegetated and undisturbed slopes.

2. Choose cross drain culvert diameter and type according to predicted ditch flow, debris and bedload passage expected from the ditch. Minimum diameter is 18.”

3. Locate surface water drainage features (e.g., cross drain culverts, rolling dips, and water bars) where water flow will be released on convex slopes or other stable and non-erosive areas that will absorb road drainage and prevent sediment flows from reaching wetlands, floodplains, and waters of the State. Where possible, locate surface water drainage structures above road segments with steeper downhill grade. Locate cross drains at least 50 feet from the nearest stream crossing and allow for a sufficient non-compacted soil and vegetative filter.

4. Armor surface drainage structures (e.g., broad based dips, and leadoff ditches) to maintain functionality in areas of erosive and low-strength soils.

5. Discharge cross drain culverts at ground level on non-erodible material. Install downspout structures or energy dissipaters at cross drain outlets or drivable dips where…