Questions asked and responses given:

Q: Will hydrants be replaced with this contract?

A: No, contract will solely focus on replacing the well and the supply line from the well head to the pump house.

Q: Will the galvanized pipe be replaced?

A: Yes, the galvanized pipe from the well head to the pump house will be replaced with 1-1/4” HDPE Pipe. Refer to amended specs Q: Does the electrical need to be buried in conduit?

A: Yes, the status of the existing conduit is unknown, but it may be used if in suitable condition. Otherwise new conduit will be run.

Q: What depth will new waterline and electrical be placed at?

A: 36” depth – waterline. 24” depth – electrical. 8” depth – marking tape Q: What repairs are expected in the pumphouse?

A: New pump controller, any electrical conduit needed for this run, and installation of one pressure gauge in the system.

Q. Can Dept of Labor form WH347 be used for payrolls?

A. Yes, that form or any other form that contains all of the same information is acceptable.